Home / Suncorp Group / Determination 12-25-318946

Determination 12-25-318946

Cash settlement amount for cyclone water and mould damage to building, plus delay and non-financial loss

FirmSuncorp Group
Decided2026-09-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$6,656
Non-financial loss$6,300
Amount claimed—
SourceAFCA PDF

Summary

After Cyclone Alfred, the insurer partly accepted a home claim and later accepted most of the remaining damage. AFCA found the building cash settlement was too low and ordered further payments, an expert invoice reimbursement and $6,300 non-financial loss compensation.

The complainant's builder's quote reflected the reasonable cost of repairs including contingency, and the insurer's progressive acceptance and delay caused inconvenience beyond the ordinary.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-318946 | Financial firm | AAI Limited Case number: 12-25-318946 10 September 2026 1 Determination overview 1.1 Complaint The complainant (jointly) held a home building and contents policy underwritten by the financial firm (insurer). Following Cyclone Alfred in March 2025, she claimed under the policy for water and mould damage to her home and contents. The insurer partly accepted the claim but said some of the damage resulted from pre-existing roof and window defects which led to ongoing water ingress. The complainant said all the damage was caused by the cyclone. During the course of this dispute, the insurer accepted the further claimed damage (except for the roof and window defects themselves, which are not in dispute). It cash-settled the complainant for the building repairs, mould remediation and testing, damaged carpet and contents, temporary accommodation, restoration services and HVAC cleaning. The complainant says the insurer has still not cash-settled her for the removal and replacement of the built-in bedhead in the master bedroom and associated works. She also seeks payment of a further mould inspection invoice and non-financial loss compensation. 1.2 Issues and key findings Has the insurer correctly and fairly settled the building damage? No. The insurer is still required to pay the complainant: · the costs for the removal and replacement of the built-in bedhead and associated works · an additional amount of $6,480.38 for the other building repairs. Should the insurer pay other compensation? Yes. The insurer is required to contribute to the costs of the complainant’s expert reports. Non-financial loss compensation of $6,300 is also warranted and fair in the circumstances. Why is the outcome fair? The outcome is fair because the insurer is required to cover the complainant for the damage caused by the cyclone. It is also fair for $6,300 in non-financial loss compensation to be paid. 1.3 Determination This determination is in favour of the complainant. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to settle the claim by: · cash-settling the complainant for the remaining building repairs (being the removal and replacement of the built-in bedhead in the master bedroom and associated works), by paying the complainant the reasonable amount of an itemised quote she obtains, prepared by a suitably qualified professional, within 14 days of being provided with the quote · paying the complainant a further $6,480.38 for the building repairs, representing the difference between the complainant’s quote from SN and the insurer’s quote from AC · paying the complainant $176.00 for SR’s mould inspection invoice · paying the complainant non-financial loss compensation of $6,300. 2 Reasons for determination 2.1 Has the insurer correctly and fairly settled the building damage? No. The insurer is still required to pay the complainant: · the costs for the removal and replacement of the built-in bedhead and associated works · an additional amount of $6,480.38 for the other building repairs. Insurer has now accepted most of the claimed damage The complainant’s home is a two-storey residential house, which was built in around 2023. During Cyclone Alfred in March 2025, water entered the house. The complainant initially claimed for damage to the guest bedroom and another bedroom (bedroom 2). She later found damage in the master bedroom and also claimed for this. The insurer partly accepted the claim, and agreed that the cyclone caused damage to the three bedrooms and some of their contents. The insurer initially: · arranged mould inspections, mould remediation and make-safe works · appointed builders and consultants to investigate the cause of the water ingress and scope the repairs. It found that the water entered the home through the roof, flashing, gutter and windows. The insurer said these were non-claim related building defects which the complainant was responsible for fixing before the insured repairs could proceed · accepted an initial repair scope for the building damage valued at $7,463.89, which was later increased to $21,819.32, which it paid as a cash settlement to the complainant · paid the complainant a cash settlement of $15,300.99 for damaged contents in the guest bedroom. During the course of this complaint, the insurer accepted most of the claim (except the window and roof defects themselves which are not in dispute) and paid the complainant: · $6,653.58 for the damaged carpet, based on the complainant’s quote · $21,630.40 for further mould remediation and works based on the complainant’s quote · $85,555.73 for temporary accommodation, based on the period of the building repairs and mould remediation and restoration works · $1,760.44 for the mould restoration technician engaged by the complainant · $938 for the HVAC system clean · a further amount of $62,657.13 for the damaged contents · $6,330 for the mould testing and laboratory reports arranged by the complainant. The complainant says the insurer has still not settled her for the removal and replacement of the mould-affected built-in bedhead in the master bedroom and associated works. The insurer says it is waiting on the complainant to provide it with a quote to settle this. The complainant also submitted her own quote for the building repairs, which was for $28,299.70 (around $6,480 higher than AC’s quote that the insurer based its cash settlement on). Insurer required to pay more of the building damage claim I am satisfied the insurer's cash settlement for the building damage repairs needs to be increased further. The cash settlement amount for the building repairs (apart from the mould related work) was based on the quote prepared by its appointed builder, AC. This was initially valued at $7,463.89, which was later increased to $21,819.32, which the insurer paid the complainant as a cash settlement. The complainant obtained a SOW and repair quote from her own builder, SN, for the same work, for an amount of $28,299.70 (around $6,480 higher than the amount paid by the insurer). Having reviewed the material before me, I consider the complainant's quote reflects the reasonable cost of completing those required building repairs. In particular, the insurer’s cash settlement based on AC’s quote did not include an uplift to allow for contingencies and the risk of the work passing to the complainant. I am satisfied this is reasonably and fairly required and the complainant should therefore be paid the difference between AC’s and SN’s quote to address this. I also note that the complainant seeks payment for the removal and replacement of the built-in bedhead in the master bedroom and associated works. During this dispute, the insurer indicated it accepts these works should be included in its cash settlement. However, it says it requires a quote from the complainant for the works before it can determine the amount payable. I consider that position reasonable. Therefore, within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to: · cash-settle the complainant for the remaining building repairs (being the removal and replacement of the built-in bedhead in the master bedroom and associated works), by paying the complainant the reasonable amount of an itemised quote she obtains, prepared by a suitably qualified professional, within 14 days of being provided with the quote · pay the complainant a further $6,480.38 for the building repairs, representing the difference between the complainant’s quote from SN and the insurer’s quote from AC. 2.2 Should the insurer pay other compensation? Yes. The insurer is required to contribute to the costs of the complainant’s expert reports. Non-financial loss compensation of $6,300 is also warranted and fair in the circumstances. AFCA can require contribution towards professional costs Under the AFCA Rules, we can require an insurer contribute up to $5,000 in professional costs reasonably incurred by a complainant(s) in the course of a complaint. During the course of this complaint, the insurer reimbursed the complainant for most of the professional costs and reports she obtained. However, the complainant says the insurer has still not paid two of the mould testing and inspection invoices (one is for $176 and the other is for $3,630). Insurer required to pay one of the further invoices The two invoices the complainant says the insurer has not yet reimbursed her for are: · mould inspection invoice dated 10 April 2026 from SR for $176 · mould testing invoice dated 16 February 2026 from OC for $3,630.00 Having reviewed the material before me, I am satisfied the insurer has shown that it has already reimbursed the complainant for OC’s invoice. However, I am not satisfied the insurer has shown that it has reimbursed the complainant for SR’s invoice. The insurer has not identified any payment corresponding to that invoice in the materials it has provided. Within 14 days of being notified of the complainant accepting this determination, I am satisfied it is fair that the insurer reimburse the complainant $176 for SR’s invoice. AFCA can award compensation for non-financial loss Under the AFCA rules, non-financial loss compensation (capped at $6,300) may be awarded in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. Compensation for non-financial loss is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer. Compensation for non-financial loss is warranted In this case, I am satisfied that the insurer's handling of the claim caused the complainant substantial inconvenience, frustration and distress beyond that which would ordinarily arise from making an insurance claim. In reaching this conclusion, I have considered that: · the complainant lodged her claim shortly after Cyclone Alfred in March 2025, yet the building claim is still not fully resolved · although the insurer has now ultimately accepted and cash settled most of the damage and losses claimed by the complainant during the course of this dispute, this occurred progressively over a much longer period than it should have taken · throughout the claim, the complainant repeatedly raised concerns about ongoing moisture, mould growth and additional damage. The material before me shows she was required to continually pursue the insurer, seek reassessment of the damage and challenge aspects of its claim assessment before the further items were correctly accepted · as a result, the complainant was left dealing with unresolved moisture and mould issues within her home for an extended period. I accept this would have caused significant inconvenience and distress, particularly where further investigations, remediation and repairs remained outstanding · while the insurer was entitled to investigate the claim and obtain expert opinions, this does not adequately explain the delay in resolving the claim or why the complainant had to repeatedly follow up and seek reassessment before further damage and losses were accepted · even now, I have found that the insurer's cash settlement does not fully reflect the reasonable cost of the building repairs and that further amounts remain payable. Having regard to the nature and extent of this impact on the complainant, I am satisfied that the maximum compensation AFCA can award for non-financial loss is appropriate in this case. Accordingly, I consider it fair and reasonable that the insurer pays the complainant $6,300 for non-financial loss. 2.3 Why is the outcome fair? The outcome is fair because the insurer is required to cover the complainant for the damage caused by the cyclone. It is also fair for $6,300 in non-financial loss compensation to be paid. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.