Cash settlement amount for building repairs, temporary accommodation and compensation for claim handling
Text of the determination
Determination
|
Case number
|
12-25-318416
|
Financial firm
|
AAI Limited
Case number: 12-25-318416 2 July 2026
1 Determination overview
1.1 Complaint
The complainant lodged a claim with the financial firm (insurer) under a home insurance policy. Water escaping from the shower and bath waste pipe had damaged the property on or around 8 January 2024.
The insurer accepted the claim and offered cash settlement based on the complainant’s builder MB’s revised quote. This is because its nominated repairer (MM) refused to complete repairs due to the property’s pre-existing condition.
The complainant seeks the insurer to increase the cash settlement for building repairs, pay his expert report costs, temporary accommodation and compensation for its claim handling.
1.2 Issues and key findings
Is the insurer’s settlement fair?
No. The insurer’s cash settlement for repairs based on MB’s revised quote, its offer to consider variations for repair of claim related damage and reimburse other additional expenses is fair. It should however increase the cash settlement for building repairs with an uplift of 10% for transfer of risk and guarantee on works.
The insurer should reimburse the complainant for temporary accommodation costs incurred from July 2025 until the completion of repairs. This is because the insurer’s:
· initial scope of works and cash settlement offer was incomplete and inadequate
· revised cash settlement offer was based on the complainant’s experts’ findings.
Is the insurer required to pay compensation?
Yes. The insurer’s claim handling caused significant stress, inconvenience and frustration to the complainant.
Why is the outcome fair?
The parties are bound by the policy terms and conditions. It is fair the insurer accepts liability for insured damage and pays compensation for its claim handling.
1.3 Determination
This determination is substantially in favour of the complainant.
Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required settle the claim as detailed in section 2.1 and pay $4,000 non-financial loss compensation.
The insurer should also assess the complainant’s request for any variations (additional claim related costs) and provide an outcome and/or payment in a timely manner.
2 Reasons for determination
2.1 Is the insurer’s settlement fair?
No. The insurer’s cash settlement for repairs based on MB’s revised quote, its offer to consider variations for repair of claim related damage and reimburse other additional expenses is fair. It should however increase the cash settlement for building repairs with an uplift of 10% for transfer of risk and guarantee on works.
The insurer should reimburse the complainant for temporary accommodation costs incurred from July 2025 until the completion of repairs. This is because the insurer’s:
· initial scope of works and cash settlement offer was incomplete and inadequate
· revised cash settlement offer was based on the complainant’s experts’ findings.
Insurer should increase the settlement for building damage
The complainant has established a claimable loss for escape of liquid damage under the policy. The insurer accepted the claim for damage caused by the claimed event. The complainant had purchased the optional benefit for complete replacement cover under the policy (see section 3.2).
Given the insurer’s builder (MM) refused to repair the property because of pre-existing issues, the insurer requested the complainant to provide his builder’s (MB) quote.
The complainant appointed an engineer (BC) to determine the cause and extent of damage to the property. BC concluded the property had sustained extensive damage from the escape of liquid event. BC agreed it was unclear if some of the damages were a result of long-term issues or from the claimed event. BC agreed with some of the findings of the insurer’s engineer MO that the property had suffered from long term issues. This includes:
· the dwelling has experienced some of the noted effects that have resulted in adverse building movement and resultant building damage:
> drying effects of trees in the vicinity of the building/footings
> removal of existing trees in the vicinity of the building/footings.
> failure to maintain appropriate site drainage.
· the building has suffered from long-term footing movement throughout the dwelling, and additionally recent short-term movements of the dwellings footing have occurred since the complainant’s occupancy of the dwelling.
I accept BC’s engineering inspection, mould assessment and complete flooring removal arranged by the complainant revealed extensive subfloor damage far beyond the insurer’s initial scope of works. I accept the insurer is liable for the damage caused by the claimed event pursuant to the policy terms and conditions.
I accept the insurer’s initial scope of works and settlement offer ($58,549.64) were incomplete and inadequate to repair and reinstate the property pursuant to the policy terms and conditions. It is however not obliged to cover unrelated damage including long-term issues. This includes drainage issues identified by the experts.
MB’s initial scope of works provided a summary of the works proposed to reinstate the property with a repair estimate of between $249,700 (excl GST) and $274,700 (excl GST).
Given the difference in the quotes arranged by the parties, a dual assessment was performed at the insured property with experts representing both parties. Based on the scope of works agreed at this meeting, MB presented a detailed revised quote amounting to $193,426.93.
The complainant remains dissatisfied with the above offer and says MB had informed him that while the revised amount was quoted, MB could not complete the repairs for the quoted value.
Given the property is over 100 years old, I am not satisfied the current building regulations referred to by the insurer apply. However, I accept repairs unrelated to the claimed event will be the complainant’s responsibility. These include:
· poor site drainage
· garden beds built up against external vents
· blocked and deteriorated external guttering.
The insurer’s building coordinator’s report dated 29 July 2025 states:
There was apparent heave in the very poorly laid concrete slab which will now require removal and replacement. Given the above, the lack of subfloor space to comply with current building regulations means the Toilet, laundry and bathroom will require an in-fill slab as well… The BC outlined to the IA that with what will be required to repair the residence, I felt that even the insureds private estimate was optimistic. Given the above advice, the IA may give consideration to accepting the IO’S estimate and settling the claim as a warrantable repair by any panel builder may not be possible.
On 31 July 2025, the insurer agreed to cash settle the loss based on MB’s revised quote.
I have reviewed the various submissions presented by both parties on the accepted scope of works and repair quotes(s). Given the above comments from the insurer’s building coordinator, I accept it is highly likely there will be requests for variations arising for the repair of claim related damage, after MB starts repairs to the property.
I acknowledge the complainant seeks an additional $100,000 in settlement of the claim. MB has recently explained the reasons why the revised quote differed from its initial quote. This included the following:
The revised Q‑Tech estimate (20 June 2025) was prepared at the insurer’s request in a standardised, itemised format for comparative assessment purposes, and is therefore limited to works that could be clearly identified and measured at the time, with remaining items to be addressed as variations during construction…
· The March 2025 proposal reflects a complete, outcome-based rectification approach
· The Q‑Tech estimate (June 2025) reflects a partial, measurable scope prepared for comparison purposes at the insurer’s direction
For the purposes of achieving a compliant and complete rehabilitation of the property, we consider the original proposal to be the more accurate indication of the required works and associated cost.
As explained above, parties accept the current cash settlement is for repairs based on the damage that can be seen and more works could be required once MB starts repairs to the property.
I accept the property’s mould impacted sections may be replaced as part of the repairs. However, the property may still require further mould assessment and treatment. This is because of the extent of damage to the subfloor, smell at the property and the insurer’s mould assessment confirming fungal growth in the subfloor and on the ground. Given measures were not taken to make safe and prevent mould contamination and the delays experienced so far, it is plausible the property may require further mould assessment and treatment.
While I acknowledge the complainant’s and MB’s reasoning why the claim settlement should be increased, I agree the insurer is liable for claim related repairs only. This liability does not extend to repairs unrelated to the claimed damage and property improvement costs.
Given the above, I consider the insurer’s offer to consider additional claimed event related repair costs as variations to be fair in the circumstances. This may also include additional expert costs, safe removal of hazardous waste, mould assessment and treatment, etc.
MB’s quote was initially priced in March 2025 and revised in June 2025. MB says the pricing has since increased by 8-10%. Given this and because the insurer is transferring the risk and guarantee on the works to the complainant, it is fair in all the circumstances the insurer increases the settlement ($193,426.93) with an uplift of 10%.
I also consider it fair the insurer agreed to reimburse the complainant for the following and it should arrange settlement in a timely manner if it has not already done so:
· $1,001 for mould remediation
· $550 for skip bin
· $993.06 for removalist costs.
The insurer should also reimburse BC’s report cost ($3,520) if it has not already done so, given I have relied on its findings in finalising this determination.
AFCA encourages the parties to work together in bringing resolution to this claim and complaint. If the complainant and MB submit requests for variations, the insurer should review these and issue a decision and/or process the payment in a timely manner. If the parties are unable to agree on the additional costs of repair including the variations, the complainant is free to lodge a new complaint with AFCA for its consideration of the new issues in dispute.
Insurer should pay additional temporary accommodation
The insurer says the complainant exhausted the policy limit applicable for temporary accommodation and says it has paid:
· a total of 4 weeks of short-term temporary accommodation costs from 13 February 2024 to 26 March 2024; and
· an additional 48 weeks of residential accommodation from 26 March 2024 to 15 February 2025.
It has since considered the complainant’s circumstances and offered to settle the cost of temporary accommodation until July 2025.
The complainant says that even though the insurer had ceased reimbursing rental payments, the insured property remains uninhabitable. I accept the insurer was responsible for the initial claim delays. The complainant would not have had to arrange BC and MB to assess the property and provide supporting information had the insurer’s initial scope of works and settlement offer been complete and adequate.
Given the insurer’s revised cash settlement offer made by end July 2025 is reasonably fair for the reasons explained above, I am satisfied the insurer is not obliged to reimburse the temporary accommodation costs incurred after July 2025 until the cash settlement for building repairs is issued.
However, given the insurer’s initial claim delays between July 2024 and July 2025, it is fair the insurer reimburses the complainant the temporary accommodation costs incurred for the period of repairs, to a maximum of nine months from the date it issues the cash settlement for building repairs (Period of repairs was estimated by MM to be six to eight months. An additional one month has been allowed in lieu of variations and contingencies to MM’s estimated repair period).
2.2 Is the insurer required to pay compensation?
Yes. The insurer’s claim handling caused significant stress, inconvenience and frustration to the complainant.
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss where the insurer’s actions have caused an unusual amount of:
· physical inconvenience
· time taken to resolve the situation
· interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. When considering non-financial loss compensation, AFCA looks at what is reasonable and fair in all the circumstances. In considering what is fair in all the circumstances, it is appropriate to factor the overall claims experience, rather than focusing on specific individual events.
Insurer should pay non-financial loss compensation
The complainant says the insurer’s refusal to consider the temporary accommodation costs had caused significant stress and inconvenience. He says the claim has spanned so far over 2.5 years, with multiple changes in claim officers, each requiring re-explanation causing delays. The new staff did not have a full grasp of the file, and he felt they had not read the claim file.
The complainant says communications were missed because the insurer had sent emails to an incorrect address, to the wrong party, delaying progress by two weeks. He holds the insurer responsible for the claim delays including extended drying process, delayed scope of works and soil testing.
The complainant explains his wife has struggled with mental health stress and he has struggled having to manage his young family, away from their home, during the claims period.
I accept the overall claim delays and claim process has caused significant emotional distress and financial strain on the complainant. The complainant has been displaced for nearly two years and has had to self-fund investigations and accommodation due to the insurer’s refusal to reimburse these costs in a timely manner.
While the insurer apologised for the delays, it says the complainant was responsible for the delay between 27 September 2024 to 19 March 2025 as it awaited his expert report(s) and quote. The insurer says
· its claim assessment has been reasonable considering the level of specialist input required to develop a repair solution
· it was entitled to undertake reasonable enquiries through its assessment of the claim and maintains that its enquiries are necessary
· its staff have maintained regular contact with the complainant throughout the claim.
I acknowledge extensive investigations were required to determine the extent of claim related repairs required to reinstate the property. However, the claim notes show the complainant’s call back requests were not returned and his emails were not responded to in a timely manner on many occasions. Most importantly the insurer did not complete comprehensive investigations to determine the extent of the claim related damage at the initial stages resulting in the complainant having to organise additional investigations and assessments.
Given the above, I am satisfied the insurer’s overall claim handling caused significant stress, inconvenience and frustration to the complainant. It is therefore fair the insurer pays $4,000 non-financial loss compensation.
2.3 Why is the outcome fair?
The parties are bound by the policy terms and conditions. It is fair the insurer accepts liability for insured damage and pays compensation for its claim handling.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Product Disclosure Statement
When a member of our supplier network is unable to complete the repair or rebuild and you have Complete Replacement Cover ®
When your claim for loss or damage to the building is covered and a member of our supplier network is unable to complete the repair or rebuild, we will ask you to engage a builder to provide a scope of works and provide a quote on the cost to repair or rebuild the building on a ‘new for old’ basis.
Once the scope of works and quote is provided to us, we will arrange for it to be assessed. This will involve reviewing the quote to determine it is appropriate and reasonable for the scope of works. This includes a consideration of the appropriateness of materials, repair method, labour and material costs and overall cost.
If the quote is appropriate and reasonable for the scope of works, we will then pay you the assessed amount. If it is not, the quote may be adjusted. This may include, adjusting the scope of works or the quote. We will then pay you the adjusted amount of the quote.
If we pay you for the repair or rebuild, the Lifetime guarantee for building repairs does not apply see page 84.
When you have Complete Replacement Cover and we settle the building claim we will not:
• pay extra because you paid more for an item when it was originally purchased;
• pay extra to repair or rebuild the building to a better standard, specification or quality than it was before the loss or damage occurred except as stated in the meaning of ‘new for old’ (see page 77) or unless stated otherwise in your policy;
• fix inherent defects, structural defect, structural fault and/or faulty/poor workmanship that are not covered by your policy (see section 3 ‘Things we don’t cover’ on page 31), other than a defect or fault that we guarantee under this policy;
• fix or pay to fix pre-existing damage (unless your policy provides otherwise).
‘New for old’ means:
• rebuild or repair with new items or new materials that are reasonably or readily available at the time of replacement or repair from Australian suppliers;
• rebuild or repair regardless of age, with no allowance for depreciation.
Same type, standard and specification as when new
We will rebuild or repair to the same type, standard and specification (but not brand) to the damaged items as when new. If the same is not reasonably available from an Australian supplier, we will rebuild or repair with items or materials of a similar type, standard and specification when new. We can replace with a different brand.
‘New for old’ does not:
• include paying the extra cost of replacing or purchasing an extended warranty on any item;
• mean of a better standard, specification or quality than when new.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.