Dispute over scope and cost of fire damage repairs and compensation for claims handling
Text of the determination
Determination
|
Case number
|
12-25-303906
|
Financial firm
|
Youi Pty Ltd
Case number: 12-25-303906 13 May 2026
1 Determination overview
1.1 Complaint
The complainant holds a home building insurance policy with the financial firm (insurer) and lodged a claim for fire damage at the insured property. The insurer accepted the claim. The parties disagree about the fair scope and cost of repairs, and whether the complainant is entitled to additional compensation for the insurer’s handling of the claim.
1.2 Issues and key findings
What is the fair and reasonable cost of repairs?
Neither party’s current repair figure is a reliable basis for a cash settlement. The insurer must pay for a further joint assessment using an agreed independent building consultant to set the repair scope and cost.
Is the complainant entitled to compensation for the insurer’s claims handling?
Yes. $3,500 in non-financial loss compensation is fair in the circumstances. Financial losses are not established.
Why is the outcome fair?
The assessment process is balanced and independent. It gives both parties the chance to participate in establishing a proper scope of works. Regarding claims handling, the information supports more compensation than that offered by the insurer.
1.3 Determination
This determination is mostly in favour of the insurer.
If the complainant accepts this determination, then within 14 days of being notified:
· the parties are to take the steps outlined in section 2.1 below
· the insurer is to pay the complainant $3,500 in compensation for non-financial loss (to the extent not already paid).
2 Reasons for determination
2.1 What is the fair and reasonable cost of repairs?
Neither party’s current repair figure is a reliable basis for a cash settlement. The insurer must pay for a further joint assessment using an agreed independent building consultant to set the repair scope and cost.
Scope of works and cost of repairs in dispute
A fire started in the wall behind a fireplace at the insured property. The complainant lodged a claim for damage on 14 July 2025, which the insurer accepted. There is no dispute about coverage. The dispute is about the cost of repairing the damage.
The insurer appointed several contractors to conduct make-safes, assess and scope the damage. The insurer offered a cash settlement of about $10,707. The complainant obtained two builder quotes: one for about $87,714, and another for about $121,772. The complainant seeks a cash settlement of $98,200. The gap between the insurer’s offer and the complainant’s position is about $87,000 to $111,000.
The insurer’s position is based on a scope limited mainly to internal wall lining, tile removal and replacement, and carpentry for the firebox. The complainant’s independent builders have scoped a far more extensive range of works including demolition, scaffolding, external cladding restoration, electrical reinstatement, structural engineering, compliance certification, and supply of a new firebox and flue system.
In February 2026, the insurer arranged a desktop assessment by a structural engineering firm, SE. SE says that a further physical site assessment is required to produce an accurate scope of works.
The complainant disputes this and says that, given the history of this claim and his personal circumstances, the insurer should not be permitted to conduct a further assessment.
A further joint assessment is required
I consider the fairest course is to require a further joint assessment to establish a single, independent scope of works for the accepted damage. I have reached this view for the following reasons.
Insurer is entitled under policy and at law to verify damage
The insurer has a policy entitlement to assess the damage. While this right is not unfettered, I am satisfied the insurer is entitled to exercise it in the current circumstances. The complainant must allow this to occur as part of his duty to cooperate under the policy, and his duty of utmost good faith under section 13 of the Insurance Contracts Act 1984 (Cth) (Act).
Policy allows insurer to determine ‘reasonable cost’
Where the insurer cannot do the repairs or the complainant prefers a cash settlement, the policy says the insurer will pay:
an amount equal to the reasonable cost that you would incur to repair or rebuild the buildings. [The insurer will] undertake a search of the market to determine what this cost would be in your area, based on factors including scope of works and comparison quotes from repairers or builders.
I consider it fair that the insurer can rely on this provision to assess the damage fully before determining the settlement amount.
‘Reasonable cost’ is not clear on the current evidence
The insurer’s builder’s quote appears to be a liability quote only. It is also incomplete. SE’s table shows the insurer scope omits many categories that appear in the independent quotes.
SE’s desktop review compares the insurer scope with the complainant’s quotes. SE did not review quantum, but it flagged several items as excessive, not required or needing clarification, and said the reviewed scopes were not compliant.
Fire restoration work involving structural elements, compliance certification, and specialist installation typically requires an independent engineering scope to be definitive. The complainant’s builders are qualified and experienced, and their quotes are detailed. But they are repair quotes prepared for pricing purposes, not engineering assessments of the type needed to resolve the disputed scope items with finality. This point is underscored by the gap between the two quotes, being about $34,000.
Given the complexity of fire restoration work, the disputed scope items and the time that has passed, a further assessment is needed. Without one, the insurer cannot accurately determine the reasonable cost of repairs, and this undermines its policy entitlement.
I have considered the complainant’s criticisms of the insurer’s scope. They have merit. In my view this only adds weight to the need for an engineering reassessment.
Insurer has not had adequate chance to assess scope of works
The complainant says the insurer has conducted more than 14 site attendances and has had ample opportunity to get its assessment right.
I accept the complainant has had to tolerate a significant number of attendances. However, most of the attendances were make-safes, restoration or preliminary assessments. From the claim file notes, between July and October 2025, I counted about four substantive scope assessments. None involved an engineer. While the number of assessments still seems high, the complainant has not established it was entirely unjustified, given the nature of the damage.
The claim was lodged in July 2025. In October 2025, the insurer arranged for SE to conduct a site inspection. That inspection was booked for 29 October 2025. The complainant cancelled it because the insurer had not provided SE’s instructions beforehand. The insurer provided those instructions the following day, 30 October 2025.
The claim timeline and assessment history between July and October does not establish the insurer’s October proposal was unreasonable. I do not consider the insurer should be prevented from a further assessment on the basis it could, in theory, have arranged it earlier.
The insurer arranged a desktop assessment by SE in February 2026. SE said its assessment would be limited without a physical site inspection. The insurer acknowledged this at the time. The desktop assessment was a reasonable interim step, but it is not a substitute for a site inspection.
Complainant’s quotes are not a fair basis for settlement
Both parties have made legitimate criticisms of the other’s scope and costings. There is real uncertainty about the scope and quantum, and the complainant’s quotes are not a reasonable basis for cash settlement on their own.
SE’s desktop assessment noted concerns with the complainant’s quotes. These included:
· certain internal structural, electrical, tiling and finishing works may be over-scoped / not required
· parts of the external envelope scope are unclear or may not match the existing materials
· key installation details remain unknown, including how the suspension bracket and flue were installed and the roof-to-chimney flashing detail.
SE is a qualified structural and civil engineering firm and provides reasons in support of its views. I place weight on those views, while noting the limitations of a desktop review.
The complainant argues that SE’s opinions should be given no weight because SE did not inspect the property, was not provided with all the complainant’s evidence, and is not a fire restoration specialist. These are not unreasonable points, but they do not establish that the complainant’s quotes should be accepted without independent verification. If anything, they reinforce the need for a proper on-site assessment where the expert has access to all relevant material.
I also note the complainant has not provided an independent engineer’s report to validate the scopes prepared by his builders. In the absence of this, it means I cannot be satisfied his figures are the right basis for settlement.
Gap between parties’ positions favours further assessment
The gap between the parties is about $87,000 to $111,000. A gap of that size reinforces the need for an independent assessment rather than adopting either party’s figure.
Complainant’s arguments are not sufficient
The complainant raises several arguments against a further assessment, some of which I have addressed above. I deal with his other most substantive points here.
The complainant says his mental health would be further compromised by another assessment. I accept the process has taken a toll on the complainant’s wellbeing, and that the insurer is funding counselling for the complainant and his wife. I also accept the complaint was expedited under AFCA’s processes because of the complainant’s personal circumstances.
However, a single further assessment conducted with appropriate support measures is a proportionate step. Adopting an unverified figure would not be fair to either party. The insurer has offered to work with the complainant to ensure he feels supported during any further attendance.
The complainant also says the insurer has had every chance to get its assessment right and should not benefit from its own failures. I acknowledge the insurer’s claims handling has not been without fault. The initial scoping was inadequate. The insurer engaged four assessment firms, none of which produced a comprehensive scope, and it did not provide SE with the complainant’s full evidence.
But the question here is whether, given the current evidence, a further assessment is needed to reach a fair outcome. I consider it is.
The claims handling shortcomings do not mean the complainant is entitled to a cash settlement based on figures that have not been independently verified. The fair remedy for those shortcomings (if established) is compensation for non-financial loss, not the blocking of a comprehensive assessment process.
The complainant suggests the desktop assessment, together with his two builder quotes, provides enough information to determine the claim. I disagree. SE says the extent of damage is difficult to determine without a site inspection. A desktop reviewer who cannot determine the extent of damage is not in a position to conclusively validate or reject either party’s scope.
Finally, in an extensive summary document, the complainant provides what he describes as comprehensive market research and analysis which supports his quote values. Although he lists the sources, not all of them are publicly accessible, and he does not provide the sources. He also does not provide verification of the analysis by a qualified expert (such as a quantity surveyor). This limits the weight I can give to it. However, the research summary seems, on its face, coherent and the insurer has not refuted it. Regardless, scope items would still need to be clarified / verified, and the insurer has an entitlement to do so. Arguments about market value do not negate this entitlement.
Defective installation does not reduce insurer’s liability
The insurer has raised the question of whether the fireplace may have been installed in a non-compliant way, and whether this affects the scope of works. The insurer refers to general exclusions in the policy which relate to additional costs arising from non-compliance with building codes or regulations.
I note the following. First, the claim has been accepted. The insurer has not sought to decline liability on the basis of defective installation.
Secondly, the evidence on installation compliance is contested. The fireplace assessor’s report attributed statements to the complainant which the complainant says are untrue. Also, SE’s installation findings are based on that report.
Thirdly, the insurer’s contractor removed the firebox from the property in October 2025, limiting the ability to independently verify the installation details.
I also note one of the general exclusions excludes loss caused by poor or faulty workmanship or by a defect, “unless you were not and could not reasonably have been aware of the problem prior to the incident.” The fireplace was professionally installed in 2021, received building approvals, and apparently worked fine for about four years. On the available evidence, the complainant was not aware of any installation deficiency.
I do not consider the defective installation issue reduces the insurer’s liability on the current evidence. However, the insurer should be entitled to consider the application of relevant policy terms as part of the further assessment process I am directing.
Firebox must be replaced, not reinstalled
The insurer has given mixed messages about the scope for the firebox. Initially it said the scope was for reinstallation only, but now it concedes its contractor removed the firebox and has agreed to replace it. The replacement cost must be included in whatever settlement figure is ultimately determined.
Assessment should follow this process
If the complainant accepts this determination, then within 14 days of the insurer being notified, the parties are to take the following steps.
The parties should agree on an independent engineer or suitably qualified building consultant. To facilitate this, the insurer should provide a list of three candidates, and the complainant should choose one from that list. SE may be included on the list.
The expert should inspect the property with both parties or their representatives present and prepare a written scope of works describing the repairs required to address the fire damage, having regard to the previous reports and scopes already obtained. The expert must be provided with all relevant information from both parties, including the complainant’s photographic and video evidence, the Fire & Rescue NSW incident report, the complainant’s two independent builder quotes, and all prior assessment reports.
Once the scope is available, each party may obtain up to two actionable building quotes based on that scope. An actionable quote is one where the builder confirms it is prepared to perform the works for the complainant at the quoted price.
If only one actionable quote is obtained, the insurer should cash settle the building claim using that quote plus a 15% contingency. If more than one actionable quote is obtained, the insurer should cash settle using the average of those quotes plus a 15% contingency. The contingency addresses the likely variances in fire restoration work and the fact that the risk of the works passes to the complainant in a cash settlement.
Any amount payable is limited by the building sum insured. No interest is payable, because the settlement will be based on current market rates at the time of quoting.
In the context of the further assessment, the insurer is also to consider the application of any policy benefits and any terms relevant to determining the extent of its liability, including the firebox replacement.
If the complainant is required to take unpaid leave to attend the further assessment, and he provides evidence of this to the insurer, the insurer should reimburse his lost income for the duration of that attendance.
If the parties are unable to agree on the final quantum after completing this process, they may return to AFCA for a decision on that point. However, this will be a new AFCA complaint, subject to our usual process, including information gathering and exchange.
2.2 Is the complainant entitled to compensation for the insurer’s claims handling?
Yes. $3,500 in non-financial loss compensation is fair in the circumstances. Financial losses are not established.
AFCA’s approach to non-financial loss compensation
AFCA can award up to $6,300 compensation for non-financial loss. We will only award this where a complainant suffered an unusual degree of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind, because of an insurer’s conduct. We take a conservative approach and expect customers to bear the normal degree of inconvenience involved in making a claim.
Complainant says the insurer’s conduct caused severe harm
The complainant says the insurer’s claims handling was deficient in several respects. He points to extended delays, the initial under-scoping of damage, the removal of the firebox by the insurer’s contractor, two admitted errors in the insurer’s statements to AFCA about the firebox, multiple site attendances, and the impact on his mental health. He says the insurer is funding counselling for both himself and his wife.
The complainant also says the insurer breached section 13 of the Act (duty of utmost good faith), the General Insurance Code of Practice, and the Australian Consumer Law. He also points to a Federal Court case involving this insurer, and says the pattern of misconduct here is the same as in that case.
Insurer concedes it mishandled claim
The insurer has acknowledged its claims handling fell short. It waived the $1,250 excess and offered a further $1,250 in non-financial loss compensation, for a total of $2,500. The insurer says it is willing to consider a higher amount once the claim quantum is confirmed.
The insurer says the counselling was offered as a standard benefit under the policy (which provides reimbursement of out-of-pocket counselling costs up to $1,500 per person). However, from the correspondence it seems the insurer offered counselling “as a gesture of support and in consideration of their vulnerabilities which have been communicated.” I do not treat the provision of counselling as an admission of fault, but I note this goes beyond a routine policy benefit.
Additional compensation is warranted
I accept the complainant experienced significant stress and inconvenience during the claims process. I also accept the insurer mismanaged the claim to an extent. The insurer concedes this.
However, I consider the available information establishes the parties genuinely disagreed about the assessment process and scope of works. The disagreement was significant and legitimate on both sides. The insurer’s position was not unreasonable.
I distinguish between the insurer’s specific conduct errors and the broader dispute about scope.
Regarding the firebox, the insurer made incorrect statements. These were errors, and the insurer has acknowledged them. But they were corrected within a short time and did not ultimately affect the outcome.
In relation to the removal of the firebox, this was a significant error, and I accept it caused the complainant distress and complicated the assessment process. I also note the insurer accepted responsibility for replacing the unit, which was appropriate.
On the evidence withholding from SE, this failure was not ideal. I also note the insurer has consistently said a site inspection is needed, and the further assessment I am directing will address this gap.
On the delays: the claim was lodged in July 2025. By October 2025, the insurer had engaged SE for a site inspection. The complainant cancelled that inspection. The desktop assessment followed in February 2026. While there were delays, I do not consider they were primarily caused by the insurer’s bad faith. The complexity of the damage, the disagreement about scope, and the complainant’s cancellation of the October 2025 inspection all contributed.
On the number of attendances, I have partially addressed this above. Some degree of multiple attendance is to be expected in a fire damage claim, though I accept the number here was high.
The assessment process could have been more streamlined and accurate. The initial scopes were incomplete, which led to additional time and stress. The complainant’s market research and SE’s desktop review suggest the insurer’s panel builders’ quotes were unreasonably low. Also, there were delays in making the property safe, which the insurer acknowledged.
Regarding the court case, AFCA is not bound by this. Each case turns on its own facts. I am not satisfied the insurer’s conduct in this case amounts to a breach of the duty of utmost good faith. The insurer’s handling had shortcomings, but these fall short of the conduct found in that case.
Regarding the Code of Practice, I acknowledge the overall claim timeline has been lengthy and the insurer’s communication may not have always met Code standards. However, my role is not to make findings about Code breaches.
The complainant also questions the independence of the insurer’s assessment process, saying the panel builders copied each other’s quotes. The information is insufficient to establish bias of this kind.
Overall, I do not consider it fair to attribute all of the complainant’s stress to misconduct by the insurer. The evidence establishes a legitimate disagreement about scope and quantum, not a pattern of bad faith conduct.
However, given the matters above in the context of the complainant’s documented vulnerability, I consider an increased award of compensation appropriate. $3,500 is fair in the circumstances.
For completeness, I note that, apart from the matters discussed above, the complainant has raised other claims handling allegations. I have considered them. They are either lack merit, are not made out with sufficient reliable evidence in support or, if they are, do not by themselves warrant compensation in the context of the overall picture of the claim.
Financial losses not established
The complainant claims several types of financial loss, including:
· lost earnings from unpaid leave to attend site visits (exceeding $11,666)
· professional assistance costs through a claims support firm (about $9,983)
· costs of preparing the complaint (about $9,980 for time and expenses).
These claims are not established. The complainant has not shown that unreasonable conduct by the insurer caused him to incur these losses. The claimed amounts are insufficiently supported by adequate evidence of causation and quantum. AFCA does not normally award compensation for time spent dealing with a dispute. Also, to the extent some of the fees claimed are “future fees”, these are not compensable losses.
Regarding the professional assistance costs in particular, I note the complainant engaged the claims support firm from the outset of the claim. I am not satisfied this was necessary or that it materially advanced the complainant’s position in this AFCA complaint.
I note the insurer has indicated willingness to reimburse engineering advice costs obtained by the complainant if that advice assists in resolving the scope of works. If the complainant has incurred engineering costs of that nature, this is a matter the insurer should consider as part of the further assessment process.
2.3 Why is the outcome fair?
The assessment process is balanced and independent. It gives both parties the chance to participate in establishing a proper scope of works. Regarding claims handling, the information supports more compensation than that offered by the insurer.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Policy extracts
Insured’s responsibilities when making a claim
These responsibilities must be fulfilled when a claim is made; if they are not, we can reduce or refuse your claim.
Allow us to view any damaged property (buildings and/or contents) that you are claiming for. Do not repair, sell or dispose of any damaged property prior to advising us of the damage and allowing us the opportunity to assess the damage. This includes providing us the opportunity to assess unsatisfactory repairs that need to be rectified, unless emergency repairs are required to prevent further loss or damage to the insured property.
...
You and any authorised person must give us full co-operation and comply with all our requests in relation to your claim …
Settlement provisions
How we settle your claim
If you are claiming for buildings
If we cannot repair or rebuild the damaged part of your buildings, we will pay you an amount equal to the reasonable cost that you would incur to repair or rebuild the buildings up to the limits noted in your policy.
We will undertake a search of the market to determine what this cost would be in your area, based on factors including scope of works and comparison quotes from repairers or builders.
We can use a combination of the above settlement methods if we are able to partially repair or rebuild the damaged part of your buildings.