Fairness of cash settlement offer for rectification of defective repairs to flooring and cabinetry
Text of the determination
Determination
|
Case number
|
12-25-296429
|
Financial firm
|
Youi Pty Ltd
Case number: 12-25-296429 12 August 2026
1 Determination overview
1.1 Complaint
The complainant holds a home insurance policy with the financial firm (insurer). In March 2025, AFCA determined an earlier complaint in his favour. The insurer was required to indemnify him for water damage to the concrete flooring and cabinetry at his property. The insurer then repaired the property through its network builder. The repairs were defective. The insurer accepts rectification is required.
The parties disagree about how the rectification should be delivered, what it must cover and what it should cost. The complainant seeks a cash settlement of $169,382.29. The insurer has offered $42,457.41 for the flooring (plus a 15% uplift), $27,096 for temporary accommodation and $6,300 in non-financial loss compensation. The complainant also raises concerns about the insurer's claim handling.
1.2 Issues and key findings
Is the insurer's rectification settlement offer fair?
No. The offer omits necessary work, is not based on an actionable quote, and is not fair. The settlement should be based on the network builder’s quote plus a 20% uplift.
Is further compensation for non-financial loss warranted?
No. The insurer made errors in its claim handling, but its compensation offer is fair.
Why is the outcome fair?
There is no dispute the insurer is liable for significant rectification repairs. Fairness requires that any cash settlement is sufficient for the complainant to carry out those repairs. The adjusted settlement is now fair in that sense. The uplift awarded is high, but there are good reasons for this, including the lack of an actionable quote and potential for significant repair variations.
1.3 Determination
This determination is partially in favour of the complainant.
If he accepts this determination, the claim is to be settled as set out in section 2.2 below.
2 Reasons for determination
2.1 Matters not in dispute
Following the original AFCA complaint and repair work, the complainant raised various rectification concerns. Some of those have been addressed, and some were added later as matters progressed. There are also aspects of the settlement which the parties agree on.
For clarity, the following matters are not in dispute:
· the insurer accepts the flooring repairs were defective and must be rectified
· it accepts liability for the damage its repairers caused, including the damaged door and the leaks from the reinstated pipework
· it has agreed to pay $27,096 for temporary accommodation during the rectification and $6,300 for non-financial loss
· the network builder has refused to carry out the flooring rectification.
The dispute is mainly about scope, cost of repairs, and claims handling.
2.2 Is the insurer's rectification settlement offer fair?
No. The offer omits necessary work, is not based on an actionable quote, and is not fair. The settlement should be based on the network builder’s quote plus a 20% uplift.
Complainant may choose a cash settlement
The complainant asked for a cash settlement, and the insurer offered one. Cash settlement is therefore an available pathway.
The complainant also has good reason to prefer this pathway. The insurer's repairs failed. Its builder denies the flooring defects and refuses to return (even though the insurer itself accepts liability for the defects). In September 2025, the insurer said it would appoint an alternative trade, but it did not do so for over ten weeks.
It was only in December 2025 that the insurer tried to send its network builder for another assessment. The insurer says the delay was because a cash settlement was under negotiation. That explains the more recent period, but not the earlier inaction. I also note the insurer has not taken steps to engage a new trade.
In these circumstances it is fair the insurer honours its offer to cash settle if the complainant elects this pathway.
Repair remains open if the complainant prefers it
The complainant says he has lost confidence in the insurer. I understand why. Even so, the available information does not establish the parties could not complete an insurer-managed rectification if the complainant chooses that course. The insurer remains willing to arrange repairs and to appoint a new trade.
Network builder's quote is the appropriate basis
The rectification requires the defective floor topping to be removed and the flooring reinstated across the affected open-plan area, together with the accepted cabinetry works. That is substantially the same scope the builder priced in its quote of 22 April 2025 at $64,072.80.
The following matters satisfy me this quote is the most reliable basis for the settlement:
· it was prepared by the insurer's builder after a site inspection, by a party with direct knowledge of the proprietary flooring system
· no better costing exists. The flooring system has a very small pool of certified installers. The complainant approached other contractors, who declined to quote because they were unfamiliar with the product. The insurer has not produced an alternative itemised costing
· both parties accept it is fair to settle on this quote for the most substantial rectification work, being the flooring; they only disagree on how much of the quote should be included.
Insurer's figure cannot be verified and omits necessary work
The insurer bases its offer on $42,457.41, which it describes as the flooring component of the quote inclusive of a 19% builder's margin and GST. The figure is not itemised on the information before me, and the insurer has not explained which line items it removed or why.
I consider the ancillary items the insurer has excluded are needed to do the work. The quote includes demolition and disposal, furniture removal and storage, floor protection and dust walls. Flooring and cabinetry rectification cannot occur without these work items. The insurer has not explained why a fair settlement would leave them out.
Cabinetry allowance should be included in base figure
The insurer says adopting the full quote is excessive because it includes cabinetry that has already been repaired.
However, I do not accept this. The insurer's builder scoped and priced further cabinetry rectification in December 2025 at $9,903.43, and has acknowledged rectification is required. The cabinetry allowance in the April 2025 quote is broadly comparable to the December 2025 figure.
I therefore consider the April 2025 quote is a fair proxy for the combined flooring and cabinetry rectification now required. I do not treat it as proof that every original cabinetry line remains literally outstanding. Rather, it is the best available benchmark, and the later accepted cabinetry quote confirms a material cabinetry allowance is still needed.
Quote's limitations are addressed via the uplift
The quote is not perfect. The flooring line is a provisional sum pending confirmation of the product. The quote notes the substrate quality is unknown. I note the builder's December 2025 variation prices an identical plumbing line item about 30% lower than the April 2025 quote, without explanation.
These matters reduce the quote's precision. They do not undermine it as the best available costing. I have taken them into account in setting the uplift below.
Floor re-levelling is not established as a separate cost
The complainant claims $7,000 to restore the floor to its original height. He says the defective repair lowered the floor by 4 to 5 mm, exposing grout lines.
There is no expert evidence supporting the need for this work as a separate item, or its cost. His submission does not establish the work is required beyond what the quote already covers. But his photographs and description raise a real prospect that some height correction will be needed once the defective topping is removed and replaced. That risk is fairly dealt with through the uplift below.
Benchtop: complainant may seek reimbursement
The complainant seeks $22,057.95 for removal and replacement of the stone benchtop, based on the stone contractor's quote.
He treats the damage as certain, but it is not. The benchtop is currently undamaged, and it survived the original repairs intact. Even if it cracks during the cabinetry work, the evidence does not establish full replacement is the only viable remedy.
However, I acknowledge the risk is real, and the insurer understates it. The insurer says there is no evidence the benchtop will be damaged. But its builder's December 2025 quote warns the benchtop is likely to crack and break on removal, says the same of the splashback tiles, and notes a variation is likely.
I also acknowledge the significant cost of full benchtop replacement.
So even though the benchtop replacement cost is not established now, this is a significant contingency – and it is too significant to be absorbed fairly by the uplift I award below.
In these circumstances, I consider this is fair: If the benchtop is damaged during the accepted cabinetry rectification works, the insurer must consider that damage as part of the claim. The complainant may provide photographs, a trade report and a quote for the reasonable cost of repair. If the damage was caused by the rectification works, the insurer must pay the reasonable cost of remedying it.
Splashback tiles: the uplift accounts for this
The complainant has flagged about $1,000 for the splashback tiles, which will likely be damaged during the cabinetry rectification process. He has not provided detailed costings for the tiles, but the network builder’s quotes support his position on the likelihood of damage. This item is fairly accounted for by the uplift below.
Concealed cabinetry damage is not established
The complainant says during the original repairs there was another leak in the sink area. He says water from the leak likely entered the join between the bottom shelf and the back panel of the under-sink cabinet, and that only removal of the back panel can confirm this. He reasons from the visible swelling pattern on the back panel and the damage to the removed middle shelf.
The insurer says this is excessive and not needed. It relies on the builder's thermal imaging and moisture testing, which found no moisture, and proposes a camera inspection first.
The complainant's reasoning from the damage pattern is careful, but it is not supported by expert evidence, and the testing that has been done found nothing. On balance, concealed damage is not established.
However, I consider the point is probably less significant than the parties believe. This is because the accepted cabinetry rectification already involves removing cabinetry components, and the builder doing that work will be well placed to inspect the area. Any residual risk is fairly covered by the uplift.
Additional internal repair items must be assessed
During this complaint the complainant claimed further items. These include:
· wall and possibly ceiling fascia damage
· skirting damage
· scratching to the powder-coated rails and door tracks
· concrete slurry staining
· gaps at the kickboard and bench back panel, and
· a damaged smoke alarm.
The insurer says the complainant raised several of these items for the first time during the AFCA process. However, the claim file shows otherwise.
Either way, the insurer has not assessed any of these items, and it is entitled to do so before paying. It is fair the insurer conducts an assessment, produces a scope and actionable quote for the verified items, and factors this into the settlement.
Temporary accommodation is agreed at $27,096, complainant may seek further reimbursement
The parties agree on $27,096 for eight weeks of temporary accommodation.
I consider it fair that, if the works run over because of repair contingencies, the complainant may seek reimbursement of additional temporary accommodation amounts from the insurer. This is subject to proof that:
· neither he nor his agents (such as repairers) were responsible for unreasonable delays leading to the expenses
· expenses were actually incurred
· the amount claimed is fair and reasonable.
A 20% uplift on the builder’s quote is fair
AFCA often applies an uplift to cash settlements to account for the transfer of risk to the complainant, the loss of the insurer's repair guarantee and the prospect of unforeseen costs. Uplifts are usually in the range of 5% to 20%. I consider it fair in the circumstances that the insurer includes an uplift of 20% on the network builder’s quote. In reaching this view, I have placed weight on the following matters:
· several identified contingencies carry a real prospect of extra cost: splashback cracking, possible floor height correction, possible concealed cabinetry damage
· the insurer's quote is not actionable. The network builder denies the flooring defects and refuses to do the work, so the complainant cannot engage it at the quoted price. Yet the insurer offered to cash settle for the flooring component of the builder’s quote rather than engaging a different trade to assess rectification costs afresh
· the pool of certified installers for the proprietary floor system is small, and the complainant's attempts to obtain other quotes failed
· as a retail customer, the complainant cannot access the trade rates and volume discounts available to the insurer. However, I also acknowledge the complainant has not definitively and precisely established that the insurer’s builder’s quote is heavily discounted
· a cash settlement transfers the whole project and its risks to the complainant, without the insurer’s repair warranty
· the complainant seeks additional loading amounts which are not fair.
For clarity, the base quote already includes the builder's margin and GST. The 20% uplift applies on top of the GST-inclusive rectification amounts. In addition, the uplift only applies to the network builder’s quote, not to any additional validated internal rectification items.
Interest applies to builder’s quote, but not additional internal items
If the claim is cash settled, the insurer must pay interest under section 57 of the Insurance Contracts Act 1984 (Cth) on the base rectification amount (that is, the network builder’s quote) and the uplift from 13 November 2025 until the date of payment. Interest maintains the real value of the settlement.
I have chosen 13 November 2025 because that is the date the insurer elected to quantify a cash settlement. By then it had accepted the flooring rectification was required, it had known for several weeks that its builder refused to do the works, and it had not appointed a replacement.
No interest applies to any additional validated internal items, as the quote for those will be current.
Claim to be settled like this
If the complainant accepts this determination, the parties must take the following steps.
Within 14 days of being notified of his acceptance, the insurer must arrange an assessment of the additional internal repair items. These are the wall and ceiling fascia damage, skirting damage, scratching to the powder-coated rails and door tracks, kickboard and long back panel, the concrete slurry staining and the smoke alarm. For any verified rectification items, the insurer must produce a scope of works and actionable quote for their repair.
The kickboard and long back panel issues should not be double counted if they are already addressed by the April 2025 quote or the accepted cabinetry variation. However, if the assessment identifies separate damage or rectification work for those items that is not covered by those amounts, the insurer must include that work in the scope and quote.
Within 14 days of receiving that quote, the complainant is to tell the insurer whether he elects a cash settlement or rectification by the insurer.
If he elects a cash settlement, the insurer must pay him:
· $76,887.36, being the amount of the network builder's quote of 22 April 2025 ($64,072.80), plus a 20% uplift ($12,814.56)
· interest on this amount under section 57 of the Insurance Contracts Act 1984 (Cth) from 13 November 2025 until the date of payment
· the cost of any validated additional internal repair items (with no uplift and no interest)
· $27,096 for temporary accommodation, to the extent not already paid
· $6,300 for non-financial loss, to the extent not already paid.
If he elects rectification, the insurer must carry out the rectification works, including any verified additional internal repair items. It must also pay the temporary accommodation and non-financial loss amounts above.
If the benchtop is damaged during the accepted cabinetry rectification works (whether by the complainant’s contractors or the insurer’s), the insurer must consider that damage as part of the claim. The complainant may provide photographs, a trade report and a quote for the reasonable cost of repair. If the damage was caused by the rectification works, the insurer must pay the reasonable cost of remedying it.
If the works run over because of repair contingencies and this leads to additional temporary accommodation costs, the complainant may seek reimbursement of these amounts from the insurer. This is subject to proof that:
· neither he nor his agents (such as repairers) were responsible for unreasonable delays leading to the expenses
· expenses were actually incurred
· the amount claimed is fair and reasonable.
2.3 Is further compensation for non-financial loss warranted?
No. The insurer made errors in its claim handling, but its compensation offer is fair.
AFCA’s non-financial loss jurisdiction is limited
Under AFCA Rules, we can award up to $6,300 compensation for non-financial loss caused by poor claims handling.
Apart from this monetary cap, it is important to understand what this kind of assessment entails.
In this regard, I note AFCA’s role is principally to award compensation for loss; it is not to punish a financial firm for wrongdoing.
In addition, while a non-financial loss assessment considers the financial firm’s conduct, AFCA is not bound to make findings about breaches of legislation, industry codes or regulatory guides.
Further, it is not my role in this dispute to consider systemic issues or to audit the insurer's processes generally.
The insurer made errors
The claim history spans more than two years, including a declined claim that AFCA overturned and repairs that failed.
Within this complaint, a few matters stand out:
· on 24 September 2025, the insurer's dispute resolution specialist told the complainant the policy contractually required him to accept the network builder's continued involvement. However, the policy contains no such term
· the complainant asked three times in August 2025 for his complaint to be escalated to internal dispute resolution, after the insurer told him of that right. The complaint was escalated and then moved back to customer relations without telling him. Whatever the insurer's process allows, the complainant was left believing an escalation was on foot when it was not
· in late September 2025 the insurer said it would appoint an alternative trade and did not do so.
These errors caused the complainant undue stress and inconvenience on top of a long and difficult claim.
Insurer has offered $6,300 in compensation
The insurer has offered $6,300 for non-financial loss. This is in line with AFCA’s maximum cap, and the complainant accepts that amount. Nothing therefore turns on making individual findings about each of the complainant's remaining claim handling allegations.
Other matters
The complainant seeks orders about other matters. I have considered them but in my view they do not warrant further remedial action.
First, the non-renewal flag. The claim file shows the instruction to flag the policy for non-renewal was recorded within about 40 minutes of the complainant’s complaint being loaded. It also shows the related underwriting task referred to the AFCA claim. The complainant has complained about this. This is a new issue and I make no findings on it.
Secondly, access to / correction of his personal information. The complainant says the insurer refused access to file notes, emails and call recordings in breach of the Australian Privacy Principles (APP).
This issue did not form part of the original complaint; it is not mentioned in the AFCA complaint form. It also seems the parties were arguing at cross purposes about the matter. This is appropriately the subject of a new AFCA complaint if the parties cannot resolve it.
Thirdly, the complainant raises potential systemic issues. AFCA has a separate team and process for this, which is outside this determination.
2.4 Why is the outcome fair?
There is no dispute the insurer is liable for significant rectification repairs. Fairness requires that any cash settlement is sufficient for the complainant to carry out those repairs. The adjusted settlement is now fair in that sense. The uplift awarded is high, but there are good reasons for this, including the lack of an actionable quote and potential for significant repair variations.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues and arguments in their submissions, we have restricted this determination to the issues and arguments that are most relevant to the outcome.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.