Dispute over the adequacy of the cash settlement and scope of works for cyclone damage, delay, temporary accommodation and non-financial loss
Text of the determination
Determination
|
Case number
|
12-25-288358
|
Financial firm
|
Allianz Australia Insurance Limited
Case number: 12-25-288358 31 August 2026
1 Determination overview
1.1 Complaint
On 9 March 2025, the complainants lodged a claim under their home and contents insurance policy (policy) with the financial firm (the insurer) after the insured property and contents sustained cyclone damage
The insurer accepted the claim and assessed the damage. The complainants say the insurer has not adequately scoped the work required to return the property to its pre-damaged state.
The complainants want the insurer to:
· cash settle them based on their quote for $388,301.24
· pay for the repair of additional items
· pay additional temporary accommodation costs
· pay professional costs for expert reports totalling $4,607.01
· pay non-financial loss compensation for the stress and inconvenience it has caused.
The complainants argue, in the alternative, they are entitled to the costs of a full rebuild because of the insurer’s delays.
1.2 Issues and key findings
Is the cash settlement offer fair and reasonable?
No. There is insufficient information to enable the panel to determine if either quote represents a fair and reasonable cash settlement offer. Further, the insurer is liable for further deterioration caused by the delay in the settlement of the claim.
The insurer must obtain an updated scope of works and quote.
Are the complainants entitled to additional temporary accommodation?
Yes. The insurer must pay an additional 18 weeks of temporary accommodation payments due to the insurer’s delays.
Are the complainants entitled to reimbursement of professional costs?
Yes. The complainants are entitled to reimbursement of $4,607.01 for expert reports.
Are the complainants entitled to compensation for non-financial loss?
Yes. The insurer’s claims handling caused the complainants an unusual degree of physical inconvenience and stress. The insurer must pay non-financial loss compensation of $5,000 for each complainant.
Why is the outcome fair?
The outcome is fair because it is based on the information exchanged and is consistent with the clear policy terms.
1.3 Determination
This determination is substantially in favour of the complainants.
Within 14 days of being notified of the complainants’ acceptance of this determination, the insurer is required to:
· pay the complainants $10,000 in non-financial loss compensation
· pay the complainants $4,607.01 for expert reports
· pay the complainants 18 weeks of temporary accommodation
· pay the complainants the difference between its initial cash settlement offer and amount already paid.
Within 21 days of being notified of the complainants’ acceptance of this determination, the insurer is required to:
· provide the complainants with the names of two engineers and two repairers, from which the complainant is to choose one engineer and one repairer
· then seek a scope of works from the engineer, based on all damage caused by the cyclone, including deterioration due to the insurer’s delays and the accepted additional items
· then seek actionable quotes from the repairer based on the engineer’s updated scope of works
· cash settle the complainants based on the highest of the two quotes (NXP’s quote and the fresh quote) within 14 days together with a further 15% for contingencies, less any amount already paid.
The total the insurer pays to the complainants for the repairs and the temporary accommodation because of this determination must not exceed $631,500.
2 Reasons for determination
2.1 Is the cash settlement offer fair and reasonable?
No. There is insufficient information to enable the panel to determine if either quote represents a fair and reasonable cash settlement offer. Further, the insurer is liable for further deterioration.
The insurer must obtain an updated scope of works and quote.
The policy covers the insured property against accidental loss or damage
The complainants’ home and contents insurance policy covers the complainants’ buildings and contents for any accidental loss or damage. The policy defines accidental damage as ‘damage caused by sudden, unforeseen and unintended events.’
The coverage provided by the policy is subject to conditions, limitations, and exclusions. This means that not all loss and damage is automatically covered. Rather, only loss and damage, subject to the conditions, limitations and exclusions, is covered.
The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement and Certificate of Insurance. Relevant provisions are set out below at section 3.2.
Cyclone caused extensive damage
In March 2025, the coastal area where the insured property is located was affected by a tropical cyclone. The insured property sustained significant damage, including water ingress through the roof which led to internal water damage.
The insurer attended to a make safe to reduce moisture and potential mould growth. Moisture readings reduced between 14 March 2025 and 1 April 2025. However, the property has not been remediated to date. The ongoing damp conditions have resulted in significant mould growth inside the house.
Insurer offered cash settlement
The insurer accepted the claim and appointed experts to assist it in assessing the damage. The experts included builders [NXP] and [NZC] and an engineer.
The insurer made cash settlement payments for contents, electricity consumption, fencing, and temporary accommodation. These aspects are not in dispute (save for temporary accommodation addressed below).
The insurer made a cash settlement offer of $216,172.97 to repair the property, based on NXP’s quote. The insurer also offered to undertake the repairs. The complainants say they cannot allow the insurer to repair the property because they must rebuild it to ensure it is insurable into the future.
In early March 2026, the insurer made partial payment of $50,000 to the complainants to assist with financial hardship. Then, in July 2026, following AFCA’s suggestion, the insurer paid the complainant a further $50,000. It has still not paid the complainants the amount it offered, despite having receive the quote over 12 months ago.
Complainants say cash settlement is inadequate
The insurer offered to cash settle the complainants based on a scope of works and repair quote from NXP dated 8 July 2025 in the amount of $216,172.97. The insurer also obtained another quote from NZC for $224,999.28.
The complainants rely on their builder’s revised quote dated 29 October 2025 for $388,301.24, which is also based on the insurer’s engineer’s scope of works.
The complainants say the insurer’s scope of works is incomplete. They say that it should also include further items, including:
· increased cost to remove and replace downlights, fans and smoke alarms
· underscoped replacement of skirting, architraves, cornices, wall plaster, ceiling lining and subsequent painting
· increased cost for floor preparation and vinyl flooring replacement
· increased internal door replacement cost and inclusion of door jambs to all locations
· increased cost to disconnect and reconnect appliances, install new dishwasher, and higher allowances for kitchen base cabinetry, pantry unit and splashback tiles
· incorrect tiling height to ensuite and bathroom shower alcoves
· increased cost to replace air conditioners to match existing.
The insurer says its quote is sufficient and the amounts in the complainant’s builder’s quote is excessive.
NZC’s quote dated 9 October 2025 does not include a breakdown of costings, and is a desktop report based on NXP’s scope of works and quote. The panel is accordingly not satisfied this reflects a fair settlement amount.
Policy requires insurer to pay the complainant the ‘reasonable cost’
The policy wording requires the insurer to pay the complainants the ‘reasonable cost’ to repair their home. This means it must reasonably enable them to repair the covered damage.
The insurer’s engineer reviewed the quotes and said NXP’s quote ‘is fair and reasonable and the most competitive for the works listed’. It also provided a summary of the main differences between the insurer’s and the complainant’s quote costings. He said the items in each quote are consistent with the scope of works, but costings in the complainant’s builder’s quote are more expensive. There is no information to support the view the complainant’s builder’s costings are excessive.
The panel is not satisfied the insurer’s quote genuinely reflects the cost to enable the complainant to undertake the required works because:
· the complainants may not have access to the rates appearing in the insurer’s quote
· whilst the complainants’ quote has significantly higher rates, the insurer has not shown they are excessive
· NXP did not measure the wall tile heights in the ensuite and bathroom shower alcoves correctly and accepted the height should be adjusted to 2100mm and subsequent waterproofing, which indicates there may be other measurement discrepancies in NPG’s quote.
However, the panel is also not persuaded the complainant’s builder’s quote is an accurate reflection of the reasonable cost to repair. This is mostly due to the large difference between the two quotes. There also appear to be some discrepancies in the quote, for example the plasterboard price for the living area is significantly higher per metre than other areas.
The panel is also concerned the insurer did not pay the complainants the amount it says they were entitled to, which has meant the complainants have not been able to commence works. This has of course meant the damage has worsened. The insurer says it did not pay the complainants because they did not accept the cash settlement offer. The panel does not consider this acceptable.
The complainants have shown damage that triggers cover under the policy
The complainants are first required to show it is more likely than not, that the loss or damage claimed triggers cover under the policy. Only if the complainants can do this, will the duty shift to the insurer to show, on balance, it is entitled to decline cover in line with the policy wording or otherwise.
In March 2025, the coastal area where the insured property is located was affected by a tropical cyclone. The insured property sustained significant damage, including water ingress through the roof which led to internal water damage.
There is no dispute the insured property (building and contents) have suffered significant damage because of a cyclone. The panel accepts this incident meets the policy definition of ‘accidental’, and therefore, the resultant loss or damage triggers cover under the policy.
Given this, the onus rests with the insurer to show, on the balance the probabilities, an entitlement to limit or decline cover for the claimed loss or damage in line with the policy provisions or otherwise.
Insurer’s position
During the claim, the insurer arranged multiple inspections. On 14 March 2025, the restorer attended the property to undertake an inspection, commence a make safe and prepare a proposed scope or works.
The restorer observed:
· flooring in all rooms has been significantly contaminated and there is non-restorable vinyl and carpet
· elevated moisture readings in all floors and walls significantly exceeding standard benchmarks
· visible black mould to living room, living room 2 and walk in robe.
The restorer completed the following make safe works:
· applied anti-microbial treatment to affected area
· carpet and underlay in bedroom 1, 2, 3, walk in robe and bedroom 4 were removed and later disposed on 1 April 2025
· non-restorable contents photographed and later disposed on 3 April 2025
· mould inhibitor used to fog property on 14 March 2025 and 1 April 2025
· installed three dehumidifiers to dry the property and one air scrubber to reduce contamination
· moisture readings reduced upon re-attendance on 1 April 2025.
On 19 May 2025, the insurer’s builder, NXP, attended the property and prepared an initial scope of works dated 19 May 2025. NXP revised the scope to include remediation works and costings dated 8 July 2025 for the sum of $216,172.97.
On 23 May 2025, the insurer’s engineer inspected the external render and found:
· there was some uneven settling of the house, especially at the front left corner
· cracks observed to either side and below the front lounge window with evident filler repairs
· external walls of the property were built with rigid joins and over time when the property moves the joins struggle and crack to relieve stress
· the house was built on reactive soil which expands when wet and shrinks when dry, causing ground movement over time resulting in stress on the building
· a large hoop pine tree very close to the house draws moisture from the soil, causes the soil to shrink and leads to settlement at that corner
· floodwater forces would normally cause diagonal cracks, and the house shows vertical cracks in the external wall cladding, around windows and doors and along sheet joints, which indicates progressive ground movement over time.
The engineer re-attended the property on 29 December 2025 to inspect the internal cracking, external cracking and fencing and noted the following damage:
· wall lining detached from framing in lounge
· sagging/draping ceiling in rumpus
· cracking to the concrete apron slab at the front porch with maximum 2mm wide rounded edges
· localised popping of external render in several areas
· corrosion visible and discolouration to nail heads in render
· further drop in floor level to the front lounge sitting at 43mm in lieu of 42mm previously recorded in May 2025.
He attributed the damage to high ambient humidity and corrosive marine conditions, which accelerated corrosion of fixings. He said these conditions developed after the insured event, particularly with the property being closed up, and were not observed at the initial inspection.
He also found:
· the external render popping is caused by long-term corrosion of galvanised fixings, leading to expansion and surface failure of the render
· corrosion is consistent with ongoing exposure to a marine environment, rather than a sudden event
· the concrete apron slab is generally constructed in accordance with relevant standards, aside from having insufficient control joints
· cracking to the concrete apron slab is consistent with typical shrinkage cracking during curing, rather than sudden impact damage
· cracking exhibits rounded edges and weathering, indicating it developed gradually over time
· slab has insufficient control joints, resulting in cracking occurring at random locations where internal stresses exceeded capacity
· pattern and condition of the cracking indicate age-related deterioration and environmental exposure
· overall, the damage is consistent with pre-existing structural behaviour and construction factors, rather than the insured flood event.
The insurer says the proposed scope of works appropriately reflects the cyclone‑related damage it accepts under the policy. It says the scope was developed following multiple attendances and assessments and is limited to damage it considers was caused by the insured event and is covered under the policy.
The insurer says some damage identified in the independent reports was reasonably excluded from the scope because it was assessed as not caused by the cyclone, pre‑existing, non‑structural, cosmetic, or otherwise not substantiated as insured damage. It says that where there were differences between earlier internal findings, independent reports, and later assessments, it was reasonable to request further inspections or reviews to clarify causation and extent of damage.
Complainants dispute the scope of works and quote
The complainants say that before the cyclone event the property was in good condition for a property built circa. 1970s with no external, internal or structural issues. They say the insurer’s scope of works does not reflect the damage caused by the cyclone event, including concerns about:
· external wall cracking
· concrete slab damage
· ceilings, roofing and internal damage.
The complainants’ builder considers all the observed damage was due to the cyclone event.
The complainants’ builder inspected the external cladding and prepared a report dated 28 January 2026 concluding:
· external cladding cracking was caused by flooding associated with the cyclone
· damage was caused by ground movement and movement in the timber framing, including expansion and contraction occurring around the time of the event
· delays in commencing internal strip‑out works, particularly not completing these within seven days, contributed to additional deterioration.
Overall, the complainant says the scope omits identified internal and external damage and would not restore the property to its pre‑loss condition or adequately address safety risks.
Insurer declined some damage
The insurer accepted damage it says was caused by the cyclone event. However, it declined the external render cracks and porch slab cracks. It says this was caused by ground movement over time and is not covered under the policy.
The insurer disagrees with the complainant’s builders’ quote and says a number of items were not damaged by the cyclone event.
I have carefully reviewed both quotes.
External rendering
The complainants say the property’s external rendering requires repair, repainting and expansion joint installation above window and door openings. Their builder assessed the damage and concluded it was the result of ‘the expansion and contraction of the ground and timber frame of the dwelling during and after the event’.
They have provided a quote totalling $16,957.25 for these works. The complainants say before moving into the insured property, on or about September 2023 they obtained a building inspection report. This identified minor hairline cracking to the external rendered walls, described as superficial, less than 1mm in width, and consistent with normal building movement. This cracking was considered cosmetic and did not require repair at that time.
They provided photos of the damage showing cracking to the external walls. The property inspection report identified some pre-existing cracking, particularly near windows and doors.
The insurer’s engineer identified multiple long-term contributing factors, including reactive soils, tree-related ground movement, and construction characteristics, which are consistent with progressive deterioration rather than damage arising from a single insured event. He relies on observed cracking patterns, evidence of prior repairs, the level survey confirming settlement at the front portion of the property.
Their findings identify multiple long-term contributing factors, including reactive soils, tree-related ground movement, and construction characteristics, which are consistent with progressive deterioration rather than damage arising from a single insured event. The panel is accordingly not satisfied the information currently shows this damage was caused by the insured event.
Porch slab
The complainants first observed damage to the porch slab around 14 August 2025.
The complainants provided further video evidence of the cracking.
The property inspection report does not identify any damage to the porch slab on or about September 2023, indicating it occurred after that date.
The slab adjoins the lounge, which has experienced progressive settlement and has dropped up to 42mm from floor level due to ground movement. Ongoing moisture variation in reactive soils, through repeated wetting and drying, has likely contributed to uneven slab movement and cracking. This is supported by the crack pattern, which is wider at the slab edge and tapers to approximately 2 mm further in, consistent with long-term ground movement rather than a sudden event.
The panel is not satisfied the information currently shows this damage was caused by the insured event.
Carport timber screening
The insurer says damage to the carport timber screening is excluded from cover because it is the result of gradual deterioration of the timber screening over time, rather than damage caused by an insured event.
The complainants say the timber slats may have been impacted during the flood event and seek replacement and repainting of the timber slats to the first panel adjoining the door.
However, the pre‑purchase inspection report identifies damage in this same location, including bowed and broken slats within the first panel. The image from that report shows deformation and distress to the slats in the identical area now in dispute, indicating the condition was already present prior to the cyclone event.
The panel acknowledges the complainants consider that debris or unknown objects during the flood may have caused or contributed to the damage. However, there is no clear evidence of new or distinct impact damage to this section that is separate from the deterioration previously recorded. The current condition is consistent with a continuation or progression of the earlier identified issues. Therefore, the insurer is not required to pay for the pre-existing damage.
Air conditioner
The complainants’ builder’s quote includes a prime cost allowance of $1,200 per unit for air conditioning, and notes the new units are to match existing. In contrast, the NXP quotation allows $1,900 per unit for supply.
The complainants’ quote includes four Mitsubishi DXC09ZSA-W units. In contrast, the NXP quote includes two Mitsubishi DXC09ZSA-W units and two Mitsubishi DXC09ZRA-W units. The complainants’ builder’s second quote dated 29 October 2025 includes the two different models.
The panel acknowledges neither quotation nor the supporting expert reports identify the original air conditioning systems installed at the property. However, the engineer also inspected the property and noted the same units as NXP.
Therefore, based on the engineer’s and NXP’s reports, it is reasonable to determine that there were two Mitsubishi DXC09ZSA-W units and two Mitsubishi DXC09ZRA-W units at the property that require replacement.
Internal and external door jambs
Water ingress to approximately 170mm high indicates the lower portions of the door jambs were subjected to standing water, leading to moisture retention and loss of structural integrity. Given the insurer has accepted replacement of adjoining elements such as skirting and architraves, the panel considers all accepted external and internal door jambs should also be replaced. This should be included in the scope of works and quote.
Flyscreens
The complainants’ builder’s quote includes the replacement of the flyscreens in the entry, dining, bedroom one and rumpus. The flyscreens listed are 2100mm x 900mm indicating they are for the sliding doors in these locations. The complainants have provided photographs of the sliding doors showing debris ingrained in the mesh flyscreens up to the floodwater line. The frame and mesh are otherwise intact and show no signs of visible damage.
On balance, the panel considers flood water has likely contaminated the flyscreens and they should be replaced. The insurer should pay for the replacement of the flyscreens in these rooms.
Tiling
The complainants’ quote includes replacement of floor to ceiling wall tiles up to 2100mm height to the bathroom and ensuite. However, the insurer’s quote includes wall tile replacement to the shower alcove up to 1800mm height. The ensuite and bathroom currently have shower alcove wall tiles up to 2100mm height.
The panel notes the insurer has acknowledged the discrepancy in the scope, which provides tiling to 1800mm only. The information shows the complainants are entitled to additional tile supply, labour and waterproofing to accommodate the additional 300mm tile height.
Roof
The complainants say there were no prior issues with the roof, and cyclone‑driven wind and rain caused roof failure leading to internal water ingress and ceiling damage. They dispute the insurer’s finding the damage was due to pre‑existing roof defects.
NZC’s report says water ingress to the ceilings occurred following heavy rainfall during the March 2025 storm event. There is no clear evidence of significant or direct physical damage to the roof coverings attributable to the cyclone itself. Rather, the roof was generally in good condition, and a mix of maintenance and design issues have caused water entry.
NZC’s report identifies several pre‑existing deficiencies in the roof, including inadequate ridge capping coverage, poorly installed or deteriorated roof screws, and construction issues associated with the low roof pitch. Additionally, there was one loose roof batten near the skylight. These conditions would have made the roof more susceptible to water ingress during significant rainfall events.
While the panel accepts the cyclone involved heavy rainfall and may have contributed to water ingress into the property, there was no observable cyclone-created damage to the roof coverings during inspection. In the circumstances, the panel is satisfied the roof issues were predominantly pre-existing in nature rather than caused by the cyclone. Accordingly, the panel is not satisfied the insurer is required to indemnify the insured for full roof replacement costs.
Internal ceilings
The complainants’ builder’s quote includes replacement of ceiling lining to the dining, bathroom, ensuite and rumpus. The pre purchase inspection report does not list any damage to the internal ceilings in these rooms.
The complainants’ builder’s quote includes 8m² plaster replacement in the dining, in comparison to 4m² noted in NXP’s quote. The engineer includes 8m² of plaster replacement to this room which aligns with the complainants’ builder’s quote based on on-site inspections. The panel is satisfied the insurer should increase the plaster ceiling repairs quantity to 8m² for the dining in the scope of works.
There is no available information to substantiate the ceiling damage in the bathroom and ensuite listed in complainants’ builder’s quote, which are not listed in the insurer’s quotes.
The insurer provided photographs dated 13 March 2025 which it says shows long-term water ingress, mould and plaster damage to the rumpus ceiling. However, the photographs are unclear and do not satisfactorily establish the presence of pre-existing damage to the rumpus ceiling.
The engineer later identified ceiling damage to the rumpus and included replacement of the ceiling linings and cove cornice within its scope of works. It attributed it to subsequent deterioration due to humidity and closure of the property. The panel considers the insurer should pay for this because it has worsened as a result of the insurer’s claims handling.
The panel is satisfied the rumpus ceiling sustained water ingress damage during the cyclone event, and the insurer has not established the damage was pre-existing as opposed to progressive deterioration following the insured event. The panel also notes the complainants sought a cash settlement and the insurer’s engineer did not assess the complainants’ builder’s quotation until October 2025. Accordingly, the panel is satisfied the insurer is required to indemnify the complainants for replacement of 43m² of plasterboard ceiling lining and associated cove cornice within the rumpus, consistent with the engineer’s scope of works.
Tile insert drains
The insurer’s scopes of works do not include replacement of the tile insert drains, including the tile insert components, within the ensuite and bathroom shower areas. The complainants’ builder includes these items for $1,387.
While the SOW includes removal and replacement of the shower floor tiles, together with new bedding and falls to the shower areas, the replacement of the tile insert drain assemblies themselves does not appear to have been specifically allowed for within NXP’s quote.
The panel is satisfied the additional work associated with the purchase and replacement of the wall-to-wall tile insert drain and square tile insert drains has not been included within NXP’s scope of works and is reasonably related to the insured repairs. Accordingly, these items should be covered by the insurer.
Additional plastering works
The complainants’ quotes include additional plastering works to grind out existing joint tape and replace external metal angles to square set corners throughout the dwelling.
While these items are not expressly identified within the insurer’s scopes, both scopes already include extensive partial plasterboard replacement, setting and sanding works, together with repairs to square set openings and transitions throughout the property.
In the panel’s view, the nature of the wall lining repairs would reasonably require some degree of joint preparation and corner angle remediation. Accordingly, the insurer should allow for these works within their scope of works.
Insurer must include additional items in the scope of works
The insurer must ensure the new scope of works includes replacement of the internal and external door jambs, flyscreens, additional tiles, tile inserts, drains and subsequent waterproofing in the bathroom and ensuite, rumpus ceiling, additional plastering and plumbing works (additional items).
Insurer is entitled to exclude some items from the scope of works
For clarification the new scope of works is not required to include the following items: full replacement of the roof, carport timber screening, porch slab and external rendering, unless the new engineer considers this damage was caused by the cyclone.
Complainants say additional damage occurred due to insurer’s delay in finalising the claim
The complainants say the property stayed in a damaged condition for an extended period after the cyclone event. The property was not repaired in a reasonable timeframe, and this has caused the ongoing deterioration of the property since it was inspected after the insured event. The complainants state this damage was outside of their control and was caused by the insurer’s delay in assessing the claim and providing a reasonable cash settlement offer that reflected the damage.
The complainants’ builder’s second quotation includes increased restoration costs of $42,172.
On 27 March 2026, the complainants engaged hygienists, to assess the ongoing deterioration at the property. They prepared a report and concluded that:
· The property was impacted by approximately 300mm category 3 floodwater with a visible tideline throughout and minimal remediation undertaken since the event
· The property remains unremedied, unoccupied and subject to ongoing roof leaks, with debris, silt and moisture still present
· There is widespread elevated moisture levels recorded across the property, with some areas at or near saturation
· Indoor humidity levels exceeded recommended thresholds, creating conditions conducive to continued mould growth
· Airborne mould concentrations inside wall cavities exceeded outdoor control levels, indicating active indoor contamination
· Sampling identified dominant mould species
· Surface sampling confirmed condition two to three contamination, indicating both settled spores and active growth
· Mould contamination was found to extend above 1200mm wall height, beyond the typical strip‑out level
· Ongoing moisture ingress and environmental conditions were contributing to continued microbial amplification
· Full removal of all porous materials within affected areas to achieve a safe condition of the indoor environment.
Overall, the complainants say the delays in finalising the claim have caused significant additional damage to the property. This has resulted in extensive mould and deterioration that according to the hygienist requires a full internal strip out of wall linings and ceilings of affected areas to restore the property to pre-loss condition.
Insurer says it assessed the claim promptly
The insurer disagrees with the complainants and says it promptly attended the property to complete a make safe, and subsequent assessments. Further, the insurer’s builder prepared a SOW and offered to do the repairs. As per the exchanged information, the complainants requested a cash settlement.
While the complainants prefers a cash settlement, the insurer retains discretion under the policy as to the method of settlement. However, having agreed to pay a cash settlement, the insurer must pay the ‘reasonable cost’ to repair. Further, the complainants wish to rebuild their home in order to reduce the impact of future disasters and ensure their home is insurable into the future.
Complainants have shown insurer is liable for further delay
The restoration contractor identified significant water ingress and implemented make‑safe measures directly after the incident. This included removal of non‑restorable materials, antimicrobial treatment, and installation of drying equipment to stabilise the property following the event and mitigate ongoing moisture and mould growth. These initial actions were consistent with accepted industry practice.
The complainants did not accept the cash settlement and continued to dispute the SOW with the insurer. I acknowledge the complainants have not taken any steps to mitigate the ongoing damage to the property.
However, the insurer did not pay the complainants what it said they were entitled to, even when it knew the complainants were in significant financial hardship. This meant the complainants were unable to take any steps to mitigate the damage. The insurer was aware the complainants were in financial hardship. The panel considers the complainants’ decision to dispute the offer was reasonable.
The insurer is accordingly liable for deterioration of damage initially caused by the cyclone and this should be included in the new scope of works.
Insurer to settle based on new quote and scope of works
A cash settlement must be based on a reasonable quotation for repairs, actionable by a retail customer. It is fair for to also apply an uplift to allow for contingencies and the loss of the lifetime guarantee.
The panel is not satisfied the insurer has shown its quote costings would have been available to the complainants. The panel is further not satisfied the complainants’ quote is a true reflection of the costs to rectify the property. The insurer must therefore obtain a new quote, based on an updated scope of works.
The insurer is entitled to deduct any cash settlement already paid from any future claim settlement as well as any applicable policy deductions.
Insurer is to settle the complainant’s building damage claim as set out below
Within 21 days of receiving notice of the complainants’ acceptance of this determination, the insurer:
· must provide the complainants with the names of two engineers, two repairers, from which the complainant is to choose one engineer and one repairer
· must then seek a scope of works from the engineer, based on all damage caused by the cyclone, including deterioration due to the insurer’s delays and the accepted additional items
· must then seek actionable quotes from the repairer based on the engineer’s updated scope of works
· must cash settle the complainant based on the highest of the two quotes (NXP’s quote and new quote) within 14 days
· must pay a further 15% to allow for contingencies.
2.2 Are the complainants entitled to additional temporary accommodation?
Yes. The complainants are entitled to additional temporary accommodation costs beyond the policy limit, for an additional 18 weeks, due to the insurer’s delays and their decision not to pay the complainants the cash settlement offer.
Policy provides temporary accommodation
The policy provides:
Alternative accommodation for You and Your pets
We cover
If Your home building is damaged by an insured event during the period of insurance to such an extent that You can’t live in it, We’ll pay the rental costs for accommodation for You and Your pets for the period it reasonably takes, to repair or rebuild Your home building. This is an extra amount, paid in addition to Your buildings sum insured. No excess applies to this benefit.
…
When We pay
We will pay this benefit when:
* You were living in the buildings when the insured event took place, and
* the loss or damage means Your home buildings are unable to be lived in.
How much We will pay
We will pay:
* the weekly rent equivalent to Your building’s rentable value prior to the damage, up to 20% of Your buildings sim insured in total, and
…
What’s covered?
For the time necessary, up to a maximum of 12 months.
The insurer has paid the complainants up to the policy limit. However, the complainants say they are entitled to additional temporary accommodation because the property remained uninhabitable for an extended period due to delays in finalising an appropriate scope of repairs. They say those delays contributed to prolonged displacement and the exhaustion of the accommodation limit.
The insurer says it was entitled to apply the policy limit and that it has no obligation to pay more.
Complainants are entitled to additional temporary accommodation
The policy provides cover for reasonable and necessary temporary accommodation costs when the insured property cannot be lived in, subject to a stated monetary limit.
However, AFCA may determine what is fair in all the circumstances. In this case, the panel is satisfied the complainants remained displaced for longer than would reasonably have been necessarily had the insurer progressed the complainants’ claim in a timely manner. The uninhabitable condition of the property continued not because of the nature of the damage alone, but because of delays.
The insurer received the complainants’ builder’s quote in around July 2025 and engaged the engineer to review the quote and SOW. It did not receive the engineer’s SOW and subsequent report until 8 October 2025. During this period, the job was sent to the wrong expert. The engineer did not progress the request and the insurer followed this up.
As set out above, the panel is also concerned about the impact of the insurer not having paid, or at least attempted to pay, the cash settlement offer.
In these circumstances, it would be unfair to apply the policy limit strictly without regard to the insurer’s contribution to delays.
The panel acknowledges the insurer initially paid a higher rate per week of $2,200, over what the insurer says the expected rental income of the property was, being $800 per week.
The panel is satisfied the insurer should pay for a further 18 weeks to fairly reflect the delay at the rate of $800 per week.
2.3 Are the complainants entitled to reimbursement of professional costs?
Yes. The complainants are entitled to reimbursement of reasonable professional or expert costs incurred in connection with the claim.
AFCA may require insurer to contribute to the complainants’ professional costs
The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs incurred by the complainants. These costs are, however, usually capped at a total of $5,000, unless special circumstances apply.
When considering whether to require an insurer to make a costs contribution, AFCA takes into account the complexity of the complaint and whether the complainants needed to incur costs to understand or establish their claim.
Complainants seek reimbursement of professional costs
The complainants seek reimbursement of the costs they incurred in obtaining professional reports, including independent building, and hygienist assessments. They say those reports were necessary to progress the claim and properly establish the extent and cause of cyclone‑related damage. The reports were also obtained to understand the extent of ongoing deterioration to the property approximately 12-months post-event due to the insurer’s incomplete scoping of works to remediate the property.
The complainants are seeking the insurer to pay for their builder’s and quote in the amount of $528 and the restorer’s report in the amount of $3,542.
Complainants are entitled to reimbursement of professional costs
The panel acknowledges the policy contains an exclusion for professional and expert costs unless prior authority is obtained. However, it considers these reports materially assisted in the resolution of the complaint. The insurer must accordingly reimburse the complainants the cost of these reports.
2.4 Are the complainants entitled to compensation for non-financial loss?
Yes. The insurer’s claims handling caused the complainants an unusual degree of physical inconvenience and stress. The insurer must pay non-financial loss compensation of $5,000 for each complainant.
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss (capped at $6,300) where the insurer’s actions have caused an unusual amount of:
· physical inconvenience
· time taken to resolve the situation
· interference with the complainant’s expectation of enjoyment or peace of mind.
However, AFCA adopts a conservative approach and expects complainants to be moderately robust, bear the normal degree of inconvenience experienced when a problem occurs, and take reasonable steps to minimise the inconvenience suffered.
Complainants are entitled to compensation
The complainants say the insurer’s delays in progressing the claim, and finalising an appropriate scope of repairs caused prolonged displacement, uncertainty and distress. They say these impacts go beyond the normal inconvenience associated with an insurance claim and justify compensation. The delays have had a significant impact on the complainants and their family. They are living in a shed on their property and the delays have impacted their business.
While I appreciate the complexity of the claim, and the requirement for different reports and experts, there was a significant period of delay by the insurer.
The panel also consider the insurer’s failure to pay the cash settlement offer, or at least attempt to, in circumstances where it knew the complainants were in significant financial hardship materially impacted the complainants.
The insurer acknowledges the stress, inconvenience and delays the complainants have experienced and offered $2,000 non-financial loss compensation.
The panel is satisfied the insurer’s claims handling caused the complainants significant stress.
The panel accordingly consider the complainants are entitled to compensation for non‑financial loss totalling $10,000 (ie $5,000 each).
2.5 Why is the outcome fair?
The outcome is fair because it is based on the information exchanged and is consistent with the clear policy terms.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:
· an ombudsman
· a member with significant experience in consumer and small business advocacy
· a member with extensive industry experience.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Relevant Policy Provisions
|
Product Disclosure Statement
|
Page 43
Accidental damage cover
Available for both Buildings and Contents cover.
The accidental damage cover option helps protect You in the event of accidental unexpected mishaps that are caused unintentionally – giving You greater coverage for Your home building and/or contents.
What’s covered?
✔The insured events covered on pages 16 - 23
✔If You’ve insured Your buildings, We’ll cover any accidental damage or loss to them
|
Page 54
Always excluded
Loss, damage, injury (unless You have chosen the Domestic workers’ compensation option (see page 46) and cover is provided under that option) or legal liability as a result or, caused by or arising from:
…
Wear and tear Including depreciation, gradual deterioration, wear and tear or lack of maintenance.
…
Inherent defects Including faulty design or materials, structural defects or poor workmanship.
Soil movement Including erosion, landslide, mudslide or subsidence unless it is directly caused by and occurs within 72 hours of an explosion, earthquake, tsunami, storm or flood (where Your policy schedule shows You have optional cover for flood).
|
Page 61
How We settle Your claims
Buildings claims
If We agree to cover Your claim for loss of or damage to Your buildings, We will pay the reasonable cost of repairing or rebuilding the damaged part of Your buildings to the same condition as when it was new. At Our discretion (acting reasonably), We may:
• enter into a contract with a builder to repair or rebuild Your home, or
• pay You the reasonable cost of repairing or rebuilding Your home in cash or cash equivalent.