Denial of bathroom damage and inadequate assessment of escape of water claim, with delays and mould damage
Text of the determination
Determination
|
Case number
|
12-25-286986
|
Financial firm
|
Auto & General Services Pty Ltd
Case number: 12-25-286986 7 July 2026
1 Determination overview
1.1 Complaint
The complainant held a home building and contents insurance policy for his home in Queensland with the financial firm (insurer). The policy period was from 26 June 2024 to 26 June 2025. The home building cover was $660,000 with an excess of $750.
The complainant made a claim for damage to his home caused by the escape of water from the connector pipe of the fridge on 4 March 2025.
The insurer accepted the complainant’s claim for contents damage. The insurer partially accepted the claim for building damage but denied claimed damage to the bathroom.
The complainant disputed the insurer’s denial of the damage to the bathroom and said that the insurer’s removal of dryers and its delays had caused structural and mould damage. The complainant sought independent assessments of the damage and the appointment of independent repairers.
1.2 Issues and key findings
Has the insurer correctly assessed the claim?
No. The insurer has not correctly assessed the claim. An independent mould remediation specialist and an independent builder should be appointed.
Is the complainant entitled to non-financial loss compensation?
Yes. It is fair for there to be an award of non-financial loss compensation.
Why is the outcome fair?
The outcome is fair because the complainant should have the option to choose whether the insurer repairs the property or pays him a cash settlement together with an uplift. An award of non-financial loss is also fair.
1.3 Determination
The determination is in favour of the complainant.
Within 28 days of receiving notice of the complainant’s acceptance of the determination, the insurer shall:
· comply with the terms of the determination as set out in Section 2.1
· pay the complainant $4,000 for non-financial loss compensation.
The complainant shall provide access to his property to the insurer’s representatives, the independent mould remediation specialist, and the independent builder to conduct the necessary inspections, testing, and repair and rebuilding works until their completion.
2 Reasons for determination
2.1 Has the insurer correctly assessed the claim?
No. The insurer has not correctly assessed the claim. An independent mould remediation specialist and an independent builder should be appointed.
Coverage of the policy
The complainant’s home insurance policy provided cover for loss or damage caused by insured events during the period of insurance. The coverage provided by the policy is subject to conditions, limitations, and exclusions. This means that not all loss and damage is automatically covered. Rather, only loss and damage caused by an insured event, during the period of insurance and subject to the conditions, limitations and exclusions, is covered.
The full details of the policy coverage, conditions, limitations, and exclusions are contained within the Product Disclosure Statement (PDS) and Insurance Certificate (together referred to as the policy).
Based on the exchanged information, the policy has been provided to the complainant. Therefore, the insurer is obliged to comply with the terms of the policy, including its conditions, limitations, and exclusions, to determine its obligations to the complainant.
Complainant has initial onus to establish a valid claim
The initial onus is with the complainant to establish on the balance of probabilities (that is more likely than not) that the loss or damage claimed falls within the insuring provision of the policy. This is known as a ‘valid’ (or prima facie) claim.
Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline or limit the claim under the policy.
Proximate cause
When establishing the cause of the damage to the complainant’s property, it is the proximate cause that must be established. The proximate cause is not necessarily the first or the last or the sole cause of the damage. It is the dominant or effective or operative cause. The proximate cause of the loss is a question of fact to be determined based on the circumstances. Where there are several causes operating, each must be considered to determine its impact on the resultant damage or loss. If one cause results in the loss or damage in any case, and the other would not without the first, the first is the proximate cause. A common-sense approach is taken to determine proximate cause.
Policy covered damage caused by escape of liquid subject to exclusions and also provided a lifetime guarantee
The policy covered damage caused by an insured event during the period of insurance (page 28). The policy provided cover for damage caused by the sudden escape of liquid, including from appliances such as refrigerators (page 38). The escape of liquid cover under the policy was subject to an exclusion for damage caused by leaking shower floors, bases or recess walls (page 39). The policy also provided a gradual deterioration exclusion (page 63).
The policy provided (page 21) a guarantee of the quality of the work and the materials used for all authorised repairs. The policy provided an additional benefit for temporary accommodation costs (page 42).
No dispute the complainant has established a claimable loss for escape of liquid damage
On 5 March 2025 the complainant made a claim for an escape of liquid on 4 March 2025 due to the connector pipe of the fridge bursting and flooding the complainant’s home. The insurer accepted the claim but denied the claimed damage to the complainant’s bathroom. There is no dispute the complainant has established a claimable loss for some damage at the property. However, his onus extends to showing all damage claimed is due to the escape of liquid event.
Insurer engaged repairers and denied the claim for bathroom damage
On 7 March 2025 the insurer engaged its builder, PB, to assess the damage. PB reported ‘elevated moisture was observed to the bathroom vanity kickers’. PB recommended a leak detection test to the shower to determine if the moisture was due to pre-existing issues. PB also recommended a leak detection test to the bathroom to determine if the moisture to the vanity kicker was pre-existing or due to moisture barrier issues or rising damp in the walls.
On 6 March 2025 the insurer engaged its restorer, RR, to prepare a report. RR’s report recorded ‘the claimed event was consistent with all damage observed. The property [had] been affected by a fridge leak from the filter pipeline’. RR prepared a quote in the amount of $11,687.36 dated 7 March 2025 for repairs to the bathroom which included the removal and replacement of both the bathroom vanity and the kitchen.
On 10 March 2025 the insurer engaged its plumber, FP, to conduct a leak detection test. FP’s report recorded:
· high elevated moisture levels around the front of the main bathroom shower because there was water escaping under the shower door when in use
· a light spray test inside the shower showed water escaping under the shower door
· the main cause of the event was the split kitchen fridge nylon reducer on the stop tap which leaked and water had entered multiple rooms inside the home
· the external front lower rendered walls showed high elevated moisture levels due to insufficient stormwater surface drainage around the dwelling
· the leak had caused water damage affecting a number of internal rooms but there were pre-event high elevated moisture levels in the bathroom from the shower screen leaking.
On 9 June 2025 the insurer denied the claim for damage to the bathroom on the basis that the damage was caused by a long-term leak from the shower screen and possible moisture barrier issues and rising damp.
Based on the exchanged information, the insurer’s denial of the bathroom damage was contrary to the insurer’s own experts’ reports, RR’s report concluded that the claim was consistent with all damage and FP’s report concluded that the main cause of the bathroom damage was the split kitchen fridge nylon reducer. Based on the insurer’s own experts’ conclusions, the proximate cause of the bathroom damage was the insured event (escape of liquid). The insurer should have accepted the claim for bathroom damage on 9 June 2025.
Complainant disputed the insurer’s denial
On 17 June 2025 the complainant disputed the insurer’s denial of the claim for the bathroom damage. Subsequently, in a letter from the insurer which was dated 27 March 2025 (but which was clearly later than that date because it referred to ‘main events’ to 4 July 2025), the insurer maintained its denial and also relied upon the gradual deterioration exclusion. Again, the insurer’s further denials were despite the insurer’s own experts’ reports.
Complainant provided information regarding damage to the bathroom
On 19 August 2025 the complainant provided three videos, including one video of 5:58 minutes duration of the complainant standing in the shower and showering and two videos of bathroom measurements. The complainant said the distance from the bathroom entrance to the shower door was 895mm and that this was too far for water to escape through the 3.9mm gap under the shower door to cause the high humidity recorded (up to 99% on the left and 94% on the right). The first video showed that the amount of water that splashed out of the shower was ‘very, very little’. The complainant said water had flooded the bathroom for more than seven hours and the 99% moisture was caused by the fridge pipe, as PB had concluded.
Insurer agreed to undertake further investigations
On 9 September 2025 the insurer said it needed clarification from FP because FP’s report confirmed that water was escaping under the shower door, but also that the main cause of the insured event was the split kitchen fridge nylon reducer. The insurer said that while FP confirmed the shower door leak, its report ‘did not address whether this was the sole cause of the bathroom damage, or whether the kitchen leak also contributed. Given the kitchen leak entered multiple rooms, and the bathroom [was] directly adjacent, attribution of causation [was] critical to resolving this dispute fairly’.
Based on the exchanged information:
· there was no need for further clarification by the insurer in September 2025 because, as the insurer acknowledged, FP’s report confirmed the main cause of the insured event was the split kitchen fridge nylon reducer which leaked and spread water into multiple rooms
· the insurer adopted the wrong test of causation in stating that it needed to determine whether the shower door leak was the ‘sole cause of the bathroom damage, or whether the kitchen leak also contributed’. This approach did not comply with the test of causation (as referred to in the above section of this determination under the heading ‘proximate cause’) which is that, when establishing the cause of the damage to the complainant’s property it is the proximate cause that must be established. The proximate cause is not necessarily the first, the last or the sole cause of the damage but is the dominant or effective or operative cause.
Further report was obtained by insurer
The insurer obtained a further report from PB dated 10 October 2025. PB concluded:
· damage was found to the bathroom door jambs, architraves and door
· elevated moisture in the vanity kickboards and cracking to the bathtub tiling silicone
· bathroom tiles were in good condition with no ‘drumming’ of tiles
· elevated moisture at the right corner of the shower screen only and no elevated moisture in the plasterboard wall linings backing onto the shower in the dining room
· the damage was ‘consistent with a single/one off event’
· there were building defects in the bathroom (entry floor tiles did not have a water stop, weep holes were not of adequate depth and no visible vapour barrier).
PB said that the repairs could not be warranted due to the building defects. PB provided a quote dated 13 October 2025 in the amount of $4,246.68 for hallway and bathroom repairs.
On 6 November 2025 the complainant said that due to the seven hour duration of the flooding and the delay of eight months (without proper drying and remediation by the insurer during the initial remediation), he was concerned about the significant risk of secondary damage, specifically mould and structural decay, which may not be visible on the surface.
Complainant said that insurer had removed drying equipment from the bathroom and he sought a professional assessment
On 25 November 2025 the complainant said that the insurer removed drying equipment from the bathroom and laundry areas during the initial remediation. The complainant said this was the primary cause of mould growth and structural decay which was then present in the bathroom subfloor and vanity. The complainant said that a specialist report was required at the insurer’s cost. The complainant sought the insurer’s acceptance of the damage in the bathroom, for the insurer to cover the cost to repair or replace the bathroom floor structure (including subfloor repair, waterproofing, and tiling) and the replacement of the vanity unit.
On 26 November 2025 the insurer said it was reviewing the claim regarding potential damage to the bathroom vanity and subfloor.
On 9 December 2025 the insurer said it accepted the complainant’s claim for the bathroom flooring and vanity unit. The insurer apologised for providing the incorrect Scope of Works (SOW) and said that the correct SOWs were for both $4,246.68 and $11,687.36. The insurer acknowledged the complainant’s concerns regarding the removal of drying equipment from the bathroom which had been flooded for seven hours and that this could lead to decay and mould in the wooden subfloor. The insurer said there was no evidence that the concrete subfloor sustained damage but agreed that an invasive inspection would be carried out jointly by an assessor and a builder, together with the complainant. The insurer said the repairs to the bathroom vanity had been accepted and that, when the new vanity was installed, it would be correctly positioned and resealed using silicone which would address the cracking. The insurer agreed that invasive inspection was the most appropriate approach to determine whether there was further damage.
Insurer engaged its experts to reinspect the damage
The insurer provided a report from BR dated 29 December 2025 which concluded:
· water damage to the kitchen cabinetry and swelling to kick boards, end and servery panels
· no wet area water stops which did not comply with Australian Standard 3740
· the wet areas were inspected for ‘drummy floor tiles’ but no drummy tiles were present which ‘evidenced’ the wet area flooring had not been compromised
· the insurer had not installed drying equipment to the wet areas but that wet areas did not require drying equipment because they are fully tiled and, if built to code, were designed to withstand large volumes of water
· RR had been appointed to undertake further investigations and would drill holes in the vanity kick boards to inspect for water proofing and visual mould growth.
The insurer provided a report from RR dated 2 January 2026. RR found the cause of loss to be related to escape of liquid and the following damage:
· vanity was separated from the wall in bathroom
· visible mould under the kitchen cabinets and bathroom vanity
· vanity kickboards had been drilled and a small amount of mould was located
· small sections of mould had been found under the cabinets in the kitchen
· the flooring in the bathroom had been inspected and no issues had been found
On 3 March 2026 the insurer said the bathroom was not constructed in accordance with AS 3740 standard and that a drummy tile test found no drummy tiles were found, which indicated that the subfloor remained uncompromised. The insurer relied upon its builder’s statement that drying equipment was generally not required for wet areas because they were designed to withstand significant water exposure. The insurer said there were small amounts of mould in the bathroom vanity but that its replacement was already part of the scope of works and there was no further damage to the bathroom.
Based on the exchanged information, the insurer’s reliance upon BR’s conclusion that the wet areas did not require drying equipment due to being fully tiled and designed to withstand large volumes of water:
· did not properly address the volume of water (of approximately seven hours in duration) which had escaped into the bathroom
· did not properly address the installation of non-tiled bathroom items such as vanities, door jambs and architraves and the door which the insurer acknowledged was damaged.
On 5 March 2026 the complainant said the insurer’s reliance on a ‘drummy tile’ test was inadequate because a ‘drummy’ sound only indicated a failure of the adhesive bond to its backing but that the subfloor had been exposed to near-total moisture (99.9%) saturation for over eight months and had experienced structural decay and mould. The complainant said RR’s report recorded mould which confirmed his concerns in November 2025. The complainant said the mould resulted from the insurer’s decision to remove the drying equipment in March 2025. The complainant also expressed concerns that BR and RR were both subsidiaries of the same parent company (AR) which gave rise to a conflict of interest and a concern about the independence of its assessments. The complainant also said it was inconsistent for the insurer to accept water damage to the vanity but to refuse an invasive inspection of the tiles which were below and adjacent to the vanity and been exposed to the same water leak.
The complainant sought:
· the appointment of independent inspectors (at the insurer’s cost) to conduct a full, invasive inspection (including lifting representative tiles) to assess the subfloor’s structural integrity and uncover any hidden mould growth
· independent air and surface testing by a qualified Indoor Environmental Professional (IEP) to perform microbiological air and surface sampling in the bathroom and kitchen, to ensure the living environment was safe
· a comprehensive remediation plan for repairing the bathroom floor and subfloor and the remediation of the mould in the bathroom and kitchen in accordance with building and health standards.
On 27 April 2026 the insurer declined to perform further invasive testing. On 5 May 2026 AFCA provided a Preliminary Assessment which the complainant rejected on 12 May 2026.
Insurer to pay an uplift on any cash settlement
When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. Further, if additional works are identified, the insurer will include those. Therefore, when the insurer settles a claim by paying the cost of repairs, it transfers these risks to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s industry knowledge and bargaining power. AFCA considers that if an insurer cash settles a claim, it should generally pay an allowance for this transfer of risk. Based on the exchanged information, a 20% uplift is fair and appropriate on any cash settlement regarding the claim.
Fair and appropriate for independent mould remediation specialist and builder
In the circumstances and based on the exchanged information, the insurer has not correctly assessed the claim.
Within 28 days of receiving notice of the complainant’s acceptance of the determination, the insurer shall:
· appoint an independent mould remediation specialist:
> to inspect the property and prepare a report for the full remediation of the property together with sample testing from a NATA-accredited (National Association of Testing Authorities, Australia) laboratory
> to engage the independent mould remediation specialist to perform a full mould remediation of the property
· provide the names of three independent builders to the complainant
· upon the provision of the names of the three independent builders, the complainant is to choose one builder and communicate his selection to the insurer in writing
· within 14 days of receiving notice of the builder the complainant selected, the insurer is to make suitable arrangements for the appointment of the builder to prepare a SOW and to ensure that:
> the new builder shall perform a full, invasive inspection (including lifting tiles) to assess the structural integrity of the bathroom and its floor and to identify all necessary repairs to the bathroom and the kitchen and the proper remediation and removal of mould
> the new builder shall provide an estimate of the repair period
> the new builder’s SOW shall include an actionable quote and detailed costing for all necessary repairs to the complainant’s property, including the cost of the necessary repairs to the bathroom and the kitchen
· upon receipt of the new, independent builder’s SOW, the insurer shall provide it to the complainant within seven days
· upon receipt of the independent builder’s SOW, the complainant is to choose whether he wishes the insurer (at its cost) to engage the new, independent builder or, alternatively, to receive a cash settlement together with a 20% uplift (which is fair to account for unexpected contingencies and the transfer or risk etc.) and to communicate his choice to the insurer in writing
· dependent upon the complainant’s election, the insurer shall either:
> engage (at its cost) the new, independent builder to complete the repair works based upon the new builder’s SOW
> or, alternatively, cash settle the complainant for the cost of the repair works based on the new builder’s SOW plus a 20% uplift within seven days of receiving notice of the complainant’s election for a cash settlement
· if required, the insurer shall arrange and pay for temporary accommodation costs in accordance with the policy for the complainant from the date of the complainant’s acceptance of this determination (including the estimated repair period by the new builder) until the repair works are completed.
· the complainant shall provide access to his property to the insurer’s representatives, the independent mould remediation specialist, and the independent builder to conduct the necessary inspections, testing and repair and rebuilding works until their completion.
2.2 Is the complainant entitled to non-financial loss compensation?
Yes. The complainant is entitled to compensation for non-financial loss.
AFCA can award compensation for non-financial loss
Under AFCA’s Rules, it can award up to $6,300 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. AFCA takes a conservative approach to compensation for non-financial loss. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim.
Insurer is required to pay non-financial loss compensation
In the circumstances of the complaint, it is not productive, and not fair to the parties, to traverse each aspect of the protracted claims history and the extensive number of communications. It is fair and appropriate to seek to progress the resolution of the complaint and the claim, including a fair assessment of non-financial loss compensation, without further delay. As referred to in section 3.1 of this determination, all the information the parties have provided has been reviewed and considered.
The insurer apologised for the complainant’s claims experience.
Based on the exchanged information, the complainant has experienced extensive delays and inconvenience due to the insurer’s poor claims handling. The complainant repeatedly followed up the insurer regarding the status of the claim to the bathroom which the insurer should have accepted based on its own experts’ reports. The insurer’s actions have delayed the repairs being performed to the complainant’s bathroom and the kitchen and led to mould damage. The complainant will also experience further delays when the further inspections and repairs are performed.
In the circumstances, it is fair for the insurer to pay the complainant $4,000 in non-financial loss compensation.
2.3 Why is the outcome fair?
The outcome is fair because the complainant should have the option to choose whether the insurer repairs the property or pays him a cash settlement together with an uplift. An award of non-financial loss is also fair.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.