Home / Suncorp Group / Determination 12-25-276149

Determination 12-25-276149

Denial of claim for retaining wall damage under escape of liquid exclusion, and compensation for claim handling delays

FirmSuncorp Group
Decided2026-03-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant's home insurance claim for cracking was accepted after initial denial, but the insurer refused cover for the front retaining wall and the complainant sought more compensation for delays. AFCA found for the insurer, as the exclusion applied and compensation already paid was fair.

The policy expressly excludes retaining walls under Escape of liquid, the insurer's delays did not cause the wall damage, and the $3,606 already paid fairly compensated poor handling.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-276149 | Financial firm | AAI Limited Case number: 12-25-276149 16 March 2026 1 Determination overview 1.1 Complaint The complainant lodged a claim with the financial firm (insurer) under his home insurance policy. This is for the widespread cracking and movement damage of the property. Initially, the insurer denied the claim on the basis that the cause of the damage is excluded under the policy. Following several assessments by the parties, the insurer accepted the claim. A dispute remains regarding the damage to the front retaining wall. The insurer maintains that the policy excludes loss or damage to retaining walls under the Escape of Liquid insured event. The complainant argues that delays in the insurer’s assessment and acceptance of the claim caused, or contributed to, the damage. In addition, the complainant is seeking compensation for the manner in which the insurer handled the claim. 1.2 Issues and key findings Did insurers’ actions cause additional damage to the retaining wall? No. This because, despite the delays in assessing the damage, the wall would have sustained damage in any event given its proximity to the leaks. On balance, the wall was expected to continue moving and deteriorating irrespective of the timing of the insurer’s assessment. Is the insurer liable for further compensation? No. I am satisfied that the compensation the insurer paid the complainant is fair and no further compensation is warranted in the circumstances. Why is the outcome fair? There is no persuasive evidence to show the insurer’s actions caused the damage or worsened the complainant’s position. On balance, the retaining wall was expected to move and sustain damage due to the underlying soil conditions and the presence of two leaks near the wall. This movement would have occurred regardless of when the insurer assessed the claim. Although there were delays, those delays did not cause additional loss. On balance, the complainant would have been in the same position even if the insurer had acted without delay. The insurer’s compensation is fair in the circumstances. 1.3 Determination This determination is in favour of the insurer. The insurer can deny the claim for the retaining wall and is not required to pay any additional compensation beyond the sums it had already paid. 2 Reasons for determination 2.1 Did insurers’ actions cause additional damage to the retaining wall? No. This because, despite the delays in assessing the damage, the wall would have sustained damage in any event given its proximity to the leaks. On balance, the wall was expected to continue moving and deteriorating irrespective of the timing of the insurer’s assessment. Policy excludes loss or damage to retaining walls caused by escape of liquid When making a claim, an insured party has the onus of establishing they suffered a loss for which their insurance policy provides cover. The insured party must establish this on the balance of probabilities (i.e. that it is more likely than not). If a claimable loss is established, the insurer has the onus of establishing, on the balance of probabilities, the application of any exclusion it relies on to reduce its liability. The complainant’s policy covers loss or damage to the complainant’s home as a result of an insured event, including ‘Escape of liquid’. The policy schedule shows the complainant holds the ‘Accidental damage at home’ optional cover. There is no dispute that: · the complainant lodged a claim for cracking and movement related damage · the insurer accepted the claim on the basis that a damaged stormwater pipe at the front of the property caused the damage · the insurer agreed to undertake the repairs once the soil dries out after a waiting period · under the insured event ‘Escape of liquid’, the policy excludes loss or damage to retaining walls. Parties dispute the cause of damage sustained to the retaining wall located at the front of the property. The complainant says because the insurer initially incorrectly denied the claim and failed to assess the structural damage in a timely manner, further damage manifested throughout the property, including to the retaining wall. On balance, the wall would have been damaged in the absence of any delays There is no dispute that the insurer accepted the claim several months after it was lodged. In his initial report, the complainant’s engineer (EM) noted displacement of the retaining wall. The corresponding photograph shows the edge of the front retaining wall right next to the letter box and the entrance to the garage. EM also observed a break in the aggy line at the edge of the retaining wall at the front of the property. He concluded there was significant movement-related damage due to the abnormal moisture conditions from several sources. This is consistent with the findings of the plumber (DD), who also identified a break in the aggy line at the front next to the retaining wall. In his report, DD marked the location of the damaged aggy line, which is immediately adjacent to the retaining wall. DD also identified breaks in the stormwater pipes at the front of the property, in addition to an open end underneath the front decking allowing water ingress. EM provided a subsequent report stating that at the time of his inspection in January 2025, he observed no damage to the retaining wall located at the front of the dwelling’s master bedroom. I acknowledge the complainant’s argument that EM’s reference to the retaining wall in his earlier report is incorrect. However, I am satisfied that this discrepancy does not affect the outcome for the following reasons. Firstly, on balance, the soil and any structures founded on it were likely to continue experiencing movement until the moisture levels normalised and the soil had time to settle. In other words, ongoing movement and associated damage to the retaining wall is expected given its proximity to two sources of water leakage. I accept the soil underneath the retaining wall would have been affected by the leaks, prior to the discover of any damage. The insurer’s engineer (MC) observed that the leaking stormwater pipe is located directly beneath the retaining wall. MC recommended that once the stormwater pipe is repaired, the cracks in the dwelling should be monitored for a 12month period. In essence, MC advised that the parties should wait at least 12 months for the soil to stabilise before reinspecting the movement related damage. I accept this is the usual process to allow the soil to dry out. While EM’s second report states that no damage was observed to the retaining wall located in front of the master bedroom initially, he did not provide any comments or explanation on his earlier observation regarding displacement of the retaining wall. Secondly, I do not accept the complainant’s assertion that the insurer allowed an active water leak to continue for almost six months and failed to stop the leak. The complainant’s experts identified the leaks and linked it to the widespread movement damage. It is the complainant’s duty to mitigate any further damage and address the sources of the leak. Further, repairing the damaged pipes is the responsibility of the complainant, not the insurer. The exchanged evidence shows that DD’s report was created on 20 January 2025. On balance, I accept the complainant was aware of the leaking pipes since January 2025. Considering the exchanged information, I accept the proximate cause of the damage to the retaining wall is leaking stormwater pipe and aggy line. I have carefully considered the exchanged evidence and the parties’ arguments. I am not satisfied that the insurer’s delays in assessing the damage or accepting the claim has either caused or contributed to the damage. Simply, there is no causal link between the damaged wall and the insurer’s handling of the claim. The insurer can deny the claim for the retaining wall Under the insured event ‘Escape of liquid’, the policy clearly and expressly excludes loss or damage to retaining walls. Considering the exchanged evidence, I accept this exclusion defeats the complainant’s claim for the retaining wall damage. I have also considered whether the ‘Accidental damage at home’ optional cover advances the complainant’s position. In this instance, it does not. Under this optional cover, the policy excludes loss or damage that is covered under an insured event, as a claim can be made for loss or damage under the applicable insured event. In other words, the loss must be considered under the relevant insured event and in this case, the damage to the retaining wall is specifically excluded under the ‘Escape of liquid event’. While I acknowledge the insurer has insufficiently investigated the claim at the start, I am not satisfied that this has contributed to the loss. The insurer can deny the claim for the retaining wall damage and is not required to take any further action in this regard. 2.2 Is the insurer liable for further compensation? No. I am satisfied that the compensation the insurer paid the complainant is fair and no further compensation is warranted in the circumstances. AFCA may award compensation for non-financial loss AFCA may award compensation for non-financial loss if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and delays. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. The complainant is dissatisfied with the insurer’s handling of the claim. Amongst other things, the complainant says: · the insurer failed to acknowledge the complainant’s concerns regarding the sagging and the cracking of the ceiling in the master bedroom · following several complaints, the insurer attended to the issue and installed wooden battens · he took time off work to accommodate several assessments. The insurer’s compensation is fair in the circumstances Having carefully considered the exchanged evidence and the parties’ arguments, I accept the insurer initially handled the claim poorly. The insurer’s initial assessment was inconclusive. Broadly, the complainant had a valid claim under the ‘Accidental damage at home’ optional cover and the insurer continued to argue that he has not established damage occurred due to an insured event. While the insurer agreed to reimburse the complainant for EM’s fees for his initial report, I accept the insurer should have engaged an engineer itself given the nature and the extent of the damage. The complainant is claiming for EM’s expert fees for his second report. However, I am not satisfied that the insurer is liable for these fees. This is because the second report did not advance the complainant’s position. I accept the insurer has pre-maturely declined the claim based on an inconclusive assessment. I also acknowledge the complainant’s phone call with the insurer in December 2024. At that point the insurer could have acknowledged the complainants’ concerns and arranged further assessments. Further, I note the complainant’s argument that there were delays in carrying the make safe repairs for the ceiling. That said, once the complainant provided EM’s report, the insurer proceeded with further assessment which eventually led to the acceptance of the claim. The exchanged evidence shows that the repairs are on hold pending completion of the required drying period, in accordance with MC’s recommendations. The exchanged information also shows the insurer offered the complainant $5,000 which the complainant rejected. I note parties are not bound by any previous commercial offer to resolve the complaint. The insurer has paid the following sums to the complainant: · $300 compensation for the poor claim handling · $750 excess waived · $1,250 ex-gratia compensation to assist with repair of the retaining wall · $1,306 compensation, equivalent to the cost of the annual premium Over the course of the claim the insurer paid the complainant the above sums in recognition of the complainant’s claim experience. I accept these amounts constitute fair compensation for the poor claim handling and the avoidable delays. I am not satisfied that any further compensation is warranted in the circumstances. 2.3 Why is the outcome fair? There is no persuasive evidence to show the insurer’s actions caused the damage or worsened the complainant’s position. On balance, the retaining wall was expected to move and sustain damage due to the underlying soil conditions and the presence of two leaks near the wall. This movement would have occurred regardless of when the insurer assessed the claim. Although there were delays, those delays did not cause additional loss. On balance, the complainant would have been in the same position even if the insurer had acted without delay. The insurer’s compensation is fair in the circumstances. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.