Home / Hollard / Determination 12-25-262511

Determination 12-25-262511

Cash settlement amount for storm damage, temporary accommodation and compensation

FirmHollard
Decided2026-04-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$201,062
Non-financial loss$4,000
Amount claimed—
SourceAFCA PDF

Summary

Complainant disputed the insurer's cash settlement for storm damage, temporary accommodation and sought compensation. AFCA required a higher building settlement including tiles, $39,090 accommodation and $4,000 non-financial loss, rejecting indirect loss and extra framing and electrical claims.

Under the policy and a fairness approach, the insurer must fund reasonable reinstatement including tiles with a 20% contingency and accommodation up to the policy limit, but unsupported framing, rewiring and income loss claims were not established.

Issues

Subjects and remedies

health or medicalhome or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-262511 | Financial firm | The Hollard Insurance Company Pty Ltd Case number: 12-25-262511 23 April 2026 1 Determination overview 1.1 Complaint The complainant held a home insurance policy with the financial firm (insurer). In March 2025, he lodged a claim for storm damage to the lower level of the property. The insurer accepted the claim and offered to cash settle the building damage. The complainant disputes the settlement amount, as he says it does not sufficiently allow for contingencies. He also says the insurer failed to remediate mould at the property and provided inadequate temporary accommodation. He wants the insurer to cash settle the claim based on his repair quotes, plus a contingency and temporary accommodation. The complainant also seeks compensation for indirect loss and non-financial loss. 1.2 Issues and key findings Is the insurer required to increase its cash settlement offer? Yes. In addition to the accepted repair quotes totalling $115,771.48, the insurer is to cover the cost of supplying and installing the tiles (estimated at $19,205). It is fair for the insurer to cash settle the building repairs for $161,971.77 inclusive of a 20% contingency. Is the complainant entitled to temporary accommodation? Yes. The insurer made reasonable attempts to find temporary accommodation and provided multiple options which were not accepted. The complainant requires accommodation until the repairs are complete. It is fair for the insurer to cash settle this for $39,090. Is the complainant entitled to compensation? Yes. The insurer is not required to pay any compensation for indirect financial loss. However, it is fair for the insurer to pay $4,000 compensation for non-financial loss as offered. Why is the outcome fair? The insurer is covering the reasonable cost to repair the property and paying for temporary accommodation in accordance with the policy. The complainant is also being compensated for his stress and inconvenience due to the delays and errors on the claim. It would be unfair to award compensation for indirect financial loss in the absence of compelling evidence. 1.3 Determination This determination is partially in favour of the complainant. Within 14 days of acceptance of this determination, the insurer is to pay the complainant: · $161,971.77 for the building damage (including $1,000 excess waiver) plus interest under s.57 of the Insurance Contracts Act 1984 from 24 October 2025 to the date of payment · $39,090 for temporary accommodation · $4,000 compensation for non-financial loss 2 Reasons for determination 2.1 Is the insurer required to increase its cash settlement? Yes. In addition to the accepted repair quotes totalling $115,771.48, the insurer is to cover the cost of supplying and installing the tiles (estimated at $19,205). It is fair for the insurer to cash settle the building repairs for $161,971.77 inclusive of a 20% contingency. Background and issues in dispute The insurer provided the complainant with the policy documents including the Certificate of Insurance (COI) and Product Disclosure Statement (PDS). The insurer is therefore entitled to rely on the terms of the policy to determine its liability for the claim. The COI shows that the complainant held ‘Essential’ building cover. There is no dispute the complainant has established a claimable loss under the policy for storm damage. The dispute relates to the insurer’s cash settlement offer and how the claim was handled. The insurer engaged the following contractors who attended on the dates shown: · restorer, RI, on 15 April 2025 · builder, AR, on 22 April 2025 · repair contractor, QA, on 3 July 2025 AR undertook some remediation works, but the complainant says these were inadequate. AR provided a report in May 2025 but did not provide a scope of works (SOW) for repairs. The complainant engaged his own builder, ER, who submitted a report dated 5 June 2025. ER reported that the ground floor of the property was inundated by floodwater. This caused damage to two bedrooms, the living/dining area, kitchen, stairwell, bathroom and toilet. ER also reported significant mould growth at the property. The complainant provided an itemised quote from ER to repair the property and complete mould remediation in the amount of $84,722. Insurer has offered to cash settle the building damage The insurer offered to accept the ER quote of $84,722 and has made several cash settlement offers throughout the dispute: · July 2025 - offered to pay $93,194.20 based on the ER quote plus 10% contingency · 5 September 2025 - offered a further $34,154.42 based on the QA quote plus 10% · 15 September 2025 - offered to increase the contingency to 15% · 8 October 2025 - offered to increase the contingency to 20% The insurer’s correspondence to AFCA says ‘20% contingency applied to the repair quote’. It is unclear whether this applies to both the ER and QA quotes. The complainant’s response dated 20 October 2025 states that the insurer offered $138,925.78 for repairs (including 20% contingency and waiver of the $1,000 excess). The insurer did not refute this. I am therefore satisfied the insurer is prepared to cash settle the building damage by paying the complainant $138,925.78 comprised of: · QA quote for $31,049.48 + 20% contingency = $37,259.38 · ER quote for $84,722 + 20% contingency = $101,666.40 Complainant says the insurer’s settlement offer is inadequate The complainant says the insurer’s cash settlement offer is inadequate because: · it excludes replacement costs for structural framing, floor tiles and electrical works · the QA quote relates solely to strip-out and remediation with no restoration works included · the contingency fails to adequately cover potential remediation and reconstruction costs. The complainant wants the insurer to cash settle the building claim based on the following quotations plus a 20% contingency: · ER SOW $84,722.00 + variations of $22,170 (tiles) + $7,350 (framing) = $114,242.00 · QA SOW $31,049.48 · AS SOW $25,505.43 The QA quote covers strip out and restoration only The ER quote dated 21 July 2025 ($84,722) covers the following works: · demolition and waste disposal · mould remediation · internal doors and architraves · skirting boards · kitchen replacement · bathroom replacement · electrical safety and reconnection · painting The complainant provided an updated version of the ER quote in October 2025, which states: · a variation will apply if the tiles need to be replaced (estimated at $22,170). · a variation will also apply if framing needs to be replaced (estimated at $7,350) The QA quote dated 25 July 2025 ($31,049.48) covers strip out of the damaged areas and restoration, including microbial treatment for exposed frame cavities and subflooring. However, it does not appear to include reinstatement of these areas. It is therefore insufficient to return the property to its pre-damage condition. Framing The ER report relevantly states: Framing behind plasterboard will need to be inspected. If replacement is required, an estimated additional cost of $11,000 will be added to the original $85,000. ER’s revised quote provided in October 2025 states: A variation will also apply if framing needs to be replaced. Remove and dispose of roughly 42lm of existing framing $2100 Supply and install 21.1lm x 3.75m new timber framing mgp10 at $350lm Total $7350.00 Based on the available information, I am not satisfied the complainant has shown that the framing was damaged by the storm event and needs to be replaced. The complainant could have allowed the insurer to complete the strip out and restoration works, which would have enabled an assessment of the framing, but he did not. In the circumstances, he has not established the framing is a claimable loss, and it would be unfair to require the insurer to pay any amount for the framing. To the extent that additional framing works may be required following the strip out, I consider the contingency is sufficient to cover the cost of this. Tiling The AR report dated 14 May 2025 states that the tiles are unaffected. However, it was obtained early in the claim and both ER and QA mention the floor tiles. The ER report dated 5 June 2025 states: 6. Floor Tiles: · At this stage, floor tiles appear structurally intact and are not included in the estimate. · However, due to the extent of water exposure, there is a risk they may deteriorate or delaminate over time. ER’s revised quote provided in October 2025 states: A variation will apply if tiles need to be replaced this will be charged as follows Removal and disposal of floor tiles roughly 70m2 $2920.00 Supply and install floor tiles roughly 70m2 $19205.00 Tile allowance $72.50m2 Total $22,170.00 Significantly, the QA quote allows $3,150 to strip out the tiling and states: Tiler | Uplift of existing floor tiles. Grind substrate ready for new floor tiles. Approx 70m2 I accept the complainant’s position that the amount quoted by QA does not cover the supply and installation of replacement tiles. While there is no clear evidence of damage to the floor tiles, the insurer’s own expert allowed the cost of stripping out all tiles and preparing the floor for new tiles. It is unclear whether this is because QA found the tiles were damaged or to allow for restoration of the subfloor. Either way, the insurer has accepted the QA quote. When this is considered together with ER’s comments about the possibility of damage to the tiles, it is fair for the insurer to pay the cost of replacing the tiles. This is necessary to ensure the property is fully reinstated. ER estimated the cost of supplying and installing the tiles at $19,205. In the absence of any other quotes and noting it is a large area, I consider it fair for the insurer to add this amount to its cash settlement offer (plus a 20% contingency). Electrical works ER reported that a full electrical safety audit and testing is required on the lower level and quoted $4,550 for these works. QR quoted approximately $2,474 for electrical works including disconnection, storage of unaffected fittings and installation of two new power points. The complainant has provided a quote from AS dated 8 October 2025 to perform electrical works for $25,505.43. This includes rewiring the downstairs area, installing new power outlets, light fittings and switches, plus testing and verification. AS has not provided any commentary on whether the electrical system was tested and found to be damaged. The complainant says AS inspected the property and observed the wiring had deteriorated, but there is no supporting evidence or expert reports on causation. In the absence of any persuasive evidence showing that a full rewiring is required due to the storm event, I consider it fair for the insurer to settle the electrical works based on its offer to pay the amounts quoted by ER and QA ($7,024) plus an uplift for contingencies. To the extent that additional electrical works are required, I consider the contingency is sufficient to cover the cost of this. Fair for insurer to cash settle the building claim for $161,971.77 The insurer submits that its settlement offer is fair and reasonable. The insurer says that without evidence, it is unable to verify the complainant’s estimated cost. I have reviewed the quotes by ER and QA and note that there appears to be some duplication between the two in relation to the strip out and remediation costs. Despite this, the insurer has offered to settle the claim by paying the amounts shown in both quotes. I consider the insurer’s cash settlement offer to be mostly fair. However, the insurer is also required to cover the cost of supplying and installing the tiles (estimated by ER at $19,205). This brings the amount payable for building repairs to $161,971.77 inclusive of a 20% uplift: · ER SOW $84,722.00 · ER quote for tiles $19,205.00 · QA SOW $31,049.48 · Subtotal $134,976.48 · 20% uplift $26,995.29 · Total $161,971.77 I consider an uplift of 20% is sufficient to cover contingencies, including any increased costs and the possibility that further works may be required to the framing and electrical. The fact that the insurer agreed to settle both quotes shows that it acted in good faith and provides the complainant with an additional buffer. The insurer is to pay $161,971.77 in full and final settlement of the claimed building damage. The insurer made numerous cash settlement offers to the complainant in a genuine attempt to resolve the dispute. However, it has not shown that it attempted to pay the amounts it had accepted. I consider it fair for the insurer to pay interest on the building settlement sum under section 57 of the Insurance Contracts Act 1984 from 24 October 2025 (date of response to AFCA after tiling quote received) to the date of payment. 2.2 Is the complainant entitled to temporary accommodation? Yes. The insurer made reasonable attempts to find temporary accommodation and provided multiple options which were not accepted. The complainant requires accommodation until the repairs are complete. It is fair for the insurer to cash settle this for $39,090. Policy covers temporary accommodation subject to limits The policy says temporary accommodation can be provided when the property is unliveable. This is explained on page 27 of the Product Disclosure Statement (PDS): Emergency accommodation We Cover When your building is insured and a claim for loss or damage is covered under the policy, and you cannot safely reside in your home because of loss or damage caused, we will pay for reasonable temporary accommodation costs for you and any family member living at your home at the time of the Insured event, for the time it will take to repair or rebuild the building to a liveable condition. Under ‘Essential’ cover, this benefit is limited to the lesser of 12 months’ rent, or 10% of the building sum insured ($39,090 in this situation). The claim notes show that the complainant identified mould within three days of the storm event, but there is no evidence showing that the property was unliveable at that time. The insurer says the complainant initially declined temporary accommodation and advised a preference to remain at the property. The complainant acknowledges this but says it was due to his mother passing away. The complainant later advised that the mould growth had worsened and raised concerns about the associated health risks. The exchanged photos show black mould, and the insurer appears to accept that the property is unliveable. I am satisfied that temporary accommodation is required until the repairs are complete. Insurer provided complainant with multiple accommodation options The complainant says the insurer has not provided adequate temporary accommodation. The insurer’s claim notes on 3 July 2025 show that the complainant had previously declined temporary accommodation due to their large number of pets. The complainant has a total of 10 pets, including three dogs, two cats and five birds. On 24 July 2025, the insurer submitted a request for its accommodation partner, HR, to arrange temporary accommodation for the complainant. HR responded that no pet friendly accommodation was available in the area. The complainant says the insurer gave misleading assurances that suitable accommodation would be arranged, then later changed its position and proposed the dogs and cats be placed in shelters and the complainant and his partner move into a one-bedroom unit. The insurer’s liability is determined based on the terms of the policy, and it is entitled to change its position if additional information comes to light. The policy states that the insurer will pay reasonable temporary accommodation costs for dogs and cats up to a limit of $500 (see page 28 of the PDS). There is no cover for birds. The insurer declined to pay additional costs or organise accommodation for the complainant with their animals, as these costs are not covered under the policy. On 11 September 2025, the insurer offered $1,500 per week to be reimbursed and suggested various accommodation options. The complainant declined these options, saying four of the five locations are widely known for criminal activity. As an alternative, the insurer offered to supply a portable ensuite to the property so the complainant could remain with his pets while avoiding the damaged bathroom. This was also declined. Based on the available information, I am satisfied that the insurer provided the complainant with multiple accommodation options which he did not accept. Insurer is not required to arrange temporary accommodation The complainant says he and his partner both have busy work schedules and do not have time to be searching for alternate accommodation. In addition, the complainant has identified health issues and says he is vulnerable to the effects of black mould. I acknowledge and empathise with the complainant’s position. However, every insurance claim comes with a level of inconvenience. I do not accept that it is solely the insurer’s responsibility to arrange temporary accommodation. Page 54 of the PDS states that the complainant must cooperate with the insurer’s reasonable requests and do everything he can to help the insurer to settle the claim. I consider the insurer has acted in line with the policy and made reasonable attempts to find solutions to the temporary accommodation issue. I acknowledge that it may not have been viable for the complainant to pay temporary accommodation costs up front and seek a reimbursement. However, he could have suggested an alternative that met his needs. I do not accept that no rental properties are available in the area. Fair for insurer to pay policy limit for temporary accommodation Given the protracted nature of the dispute and the impasse between the parties, I consider it fair for the insurer to cash settle the complainant’s entitlement to temporary accommodation. The insurer is not required to make retrospective payments for accommodation costs that were not actually incurred. However, I am satisfied that temporary accommodation is required until the completion of repairs and I consider it fair for the insurer to pay these costs up front. There is little information regarding how long the repairs will take, but the scope of works is significant, and I expect it would be at least a few months. The policy limits cover for temporary accommodation to the lesser of 12 months’ rent or $39,090 (10% of the building sum insured). The policy does not provide guidance on how rent is to be calculated. The insurer previously offered $1,500 per week based on its online searches, but these were for small units. There is no information regarding the cost to rent a comparable house. Based on the available information, I consider it fair for the insurer to pay the complainant the policy limit of $39,090 for temporary accommodation. This covers 6 months at $1,500 per week. As the limit has been reached, no additional amount is payable for the complainant’s pets. The insurer is to make this payment within 14 days of receiving notice the complainant accepts this determination. This will enable the complainant to find accommodation without further delay. 2.3 Is the complainant entitled to compensation? Yes. The insurer is not required to pay any compensation for indirect financial loss. However, it is fair for the insurer to pay $4,000 compensation for non-financial loss as offered. Insurer is not required to pay compensation for indirect loss Under paragraph D.3.2 of the AFCA Rules, we may require an insurer to compensate a complaint for indirect financial loss (also known as consequential loss). For complaints made after 1 January 2024, this is capped at $6,300 per claim. The policy does not cover loss of income. Page 44 of the PDS states: You are also not covered for … · compensation for distress, inconvenience or any other non-financial or consequential losses; This means AFCA will only award compensation for indirect loss if the complainant suffered an additional loss because the insurer mishandled the claims. We may reduce the amount of compensation we award if this loss was partially caused by the complainant’s own actions, or by factors outside an insurer’s control. The complainant says he lost income due to delays in property assessments. He has asked AFCA to award compensation for financial loss due to leave taken from work to be available for the insurer’s trades. In support of this, he has provided details of his employment together with timecards and payslips showing his regular hours worked and rate of pay. The complainant says that: · RI was booked to attend the property on 15 April 2025 between 8-10am but arrived at 11.40am and stayed for about 40 minutes. · AR was booked to attend on 22 April 2025 between 1-3pm but arrived at 3.40pm and stayed for about 1 hour and 15 minutes. The complainant has provided SMS messages confirming the booking times and timecards with notes stating that: · he lost 4 hours and 50 minutes for the pay period starting 14 April 2025 · he lost 4 hours and 10 minutes for the pay period starting 21 April 2025. I acknowledge it is inconvenient to take time off work to facilitate assessments, and this may have a financial impact. However, I consider the need to take time off primarily arose from the property being damaged by the storm event rather than errors made by the insurer. The appointments in April 2025 were initial attendances by the insurer’s restorer and builder. Assessments are expected to occur during business hours, are part of the normal claim experience and the policy excludes this type of loss. Loss of income due to time taken off work outside the scheduled appointment time may be an indirect loss caused by the insurer if its trades acted unreasonably. In this claim, the total extra time required due to delayed arrival of trades was approximately 2.5-3.5 hours. The claim arose from a cyclone which caused widespread damage and put strain on insurance service providers. While not ideal, I do not consider the late arrival of trades was significant or unreasonable in the circumstances. Further, even if I were to find that the additional time was lost due to the insurer’s actions, the complainant has not provided enough information to support his claim for loss of income. The payslips show that the complainant works regular overtime. However, they do not cover the assessment dates, and it is unclear whether he took paid or unpaid leave on those days. To the extent that he took paid leave or lost the opportunity to work a few hours of paid overtime, I consider this can be fairly dealt with as a non-financial loss. Compensation for indirect financial loss is not warranted in the circumstances. Fair for insurer to pay $4,000 compensation for non-financial loss Under AFCA’s Rules, AFCA may award compensation for non-financial loss where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation for non-financial loss. In assessing whether to award compensation, AFCA expects complainants to be moderately robust and bear the normal degree of inconvenience experienced when a problem occurs. AFCA considers the severity and impact of the financial firm’s conduct on the complainant. The complainant says the insurer mismanaged the claim, engaged in disrespectful and misleading conduct and withheld QA’s scope of works. He also says the insurer’s communication was poor and he had to call persistently and wait on hold to get updates. In addition, the complainant says the insurer’s contractors made errors on the claim including: · RI failed to properly dry and remediate the property thus permitting further mould growth · AR acted unprofessionally and failed to provide a SOW, delaying the claim for 4 months · QA provided incomplete SOWs covering strip-out but not reinstatement. He says his engagement of ER arose due to the incompetence of the insurer’s contractors. I have reviewed the insurer’s claim notes and other relevant information. I am satisfied that there were some delays and errors by the insurer and its trades which caused stress and inconvenience to the complainant, including: · there were delays initially assessing the claim and after AR’s attendance · RI and AR both arrived late to their scheduled appointment times · AR most likely did not adequately dry and remediate the property as mould is still present · the insurer delayed providing the QA SOW for 7 weeks. The complainant has identified vulnerabilities. I am satisfied that he suffered an unusual degree of stress and inconvenience due to his claims experience. I consider it unsatisfactory that he remained living in a property impacted by mould for a prolonged time. However, he contributed to the issues experienced because he refused to allow the insurer to complete further assessments and did not assist the insurer to find temporary accommodation. In October 2025, the insurer offered to waive the complainant’s $1,000 excess and pay $4,000 compensation to account for his vulnerabilities and the inconvenience experienced. This is a generous offer, and I consider this fair and reasonable in the circumstances. The insurer is to pay $4,000 for non-financial loss and waive the $1,000 excess as offered. 2.4 Why is the outcome fair? The insurer is covering the reasonable cost to repair the property and paying for temporary accommodation in accordance with the policy. The complainant is also being compensated for his stress and inconvenience due to the delays and errors on the claim. It would be unfair to award compensation for indirect financial loss in the absence of compelling evidence. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy terms

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.