Adequacy of cash settlement for flood damage to farm house, temporary accommodation, professional costs and non-financial loss
Text of the determination
Determination
|
Case number
|
12-25-257097
|
Financial firm
|
Achmea Schadeverzekeringen N.V.
Case number: 12-25-257097 27 August 2026
1 Determination overview
1.1 Complaint
The complainants hold a farm pack insurance policy with the financial firm (the insurer) that provides cover for a farm house.
On 3 March 2022, the complainants lodged a claim for damage to the house following a flood which occurred in late February 2022. The insurer accepted the claim and offered cash settlements for repairs and temporary accommodation (TA).
The complainants disagree with the insurer’s assessment of its liability for the damage and require the insurer to pay additional TA, professional costs and non-financial loss compensation.
The complainants are represented by a claims advocate. For convenience, any representation made on their behalf is referenced as being from ‘the complainants’.
1.2 Issues and key findings
Has the insurer fairly assessed its liability for the damage?
No. The insurer has not fairly assessed its liability for the damage.
Are the complainants entitled to further TA?
Yes. The insurer’s conduct has caused the complainants to incur TA beyond the policy entitlements. The insurer is to pay the complainants $36,714.30 for further TA.
Are the complainants entitled to professional costs?
Yes. The insurer is to reimburse the complainants up to $5,000 for professional costs on production of paid receipts.
Are the complainants entitled to non-financial loss compensation?
Yes. The insurer has caused extensive delays and not handled the claim appropriately. The insurer is to pay the complainants $6,300 in non-financial loss compensation.
Why is the outcome fair?
The outcome is fair as it reflects the insurer’s obligations under the policy. It ensures the cash settlement covers the insured damage and includes an allowance for contingencies. It also requires the insurer to pay additional TA costs, reimburse professional costs and compensates the complainants for the stress and inconvenience caused by its poor claims handling.
1.3 Determination
This determination is in favour of the complainants.
Within 14 days of being notified of the complainants’ acceptance of the determination, the insurer is to:
· pay the complainants $383,947.30 for building repairs less excess (unless already paid)
· pay the complainants $36,714.30 for further TA
· pay the complainants up to $5,000 for professional costs on production of paid invoices
· pay the complainants $6,300 in non-financial loss compensation.
2 Reasons for determination
2.1 Has the insurer fairly assessed its liability for the damage?
No. The insurer has not fairly assessed its liability for the damage.
Policy provides cover for damage caused by the accepted event
The complainants hold an all-in-one farm pack insurance policy which provides cover for loss or damage to insured assets listed in the Certificate of Insurance (COI) and Product Disclosure Statement (PDS).
The policy offers different levels of coverage based on the category of insured property, such as building, inventory, or vehicle. The coverage level is referred to as ‘star’ coverage, ranging from one star (lowest) to three stars (highest). Each insured risk’s level of coverage is outlined in the COI.
The complainants lodged a claim for flood damage. The insurer accepted the claim for damage to various insured assets, including the house, farm contents and unspecified vehicles.
What remains in dispute is whether the insurer has met its obligations under the policy regarding the house and if its settlement offers are fair and reasonable given the circumstances. This determination does not consider the settlement for farm contents or unspecified vehicles.
Insurer has offered a cash settlement
On 24 March 2025, the insurer offered to cash settle the claim in the following manner:
· building repairs $222,495 based on quote from the insurer’s builder (CB) dated 29 March 2023 (including $10,000 allowance)
· additional allowance for asbestos, fireplace and oven $10,000
· 15% contingency uplift $34,874.25
· foundation allowance $8,000
· less policy excess $10,000
· final repair offer $265,000.
The insurer had initially declined foundation works, relying on the findings from its engineer (CD) following a forensic engineering assessment in its report dated 23 December 2022. However, in June 2024, it accepted foundation repairs and used an allowance of $8,000 which it had adopted from the complainants’ builders (SR) quote.
The insurer had a quantity surveyor (CR) review quotes obtained from CB and SR. CR provided a quote validation report dated 25 January 2024. CR adjusted CB’s quote to include the freestanding hut and a hot water heater. CR says that SR’s quotation could not be considered for assessment as they had not disclosed their fully quantified allowances and the only costs they have shown are provisional and prime costs sums.
The insurer says its builder CB, confirmed that the quote was actionable. It also says CR reviewed the quote and found that it was reasonable, within tolerance and sufficient to reinstate the property.
The insurer relies on the policy terms extracted in 3.2 of the determination. It says its offer exceeds the minimum contractual entitlement because it reflects the full reinstatement cost at validated 2022 market rates, without depreciation for the building’s age and condition.
Complainants say insurer’s offer is inadequate
The complainants say the insurer’s offer of settlement is inadequate. They say there has been no remediation work undertaken, leaving the property in an extended state of disrepair. They have obtained their own quotes which they say should be preferred.
The complainants have provided quotes from builders for the repairs:
· SR, undated: $324,357.50 (incl GST)
· JB, dated 3 November 2023: $306,614.50 (incl GST)
· JA, dated 31 July 2024: $313,978.75 (incl GST).
The complainants obtained a report from a hygienist (NC) dated 18 September 2023. NC observed evidence of category 3 water ingress, up to 600 mm high. NC noted that no strip out or remediation work had been undertaken. NC confirmed the presence of mould on surfaces inside and outside the property following mould testing. NC says there was the potential for mould growth to be present in inaccessible areas of the site, including the wall cavities throughout the site.
The complainants obtained a report from a restorer (CE) who assessed the property on 29 August 2025 and provided a report dated 3 September 2025. CE confirmed the findings from NC about the nature of the floodwater and that no mould remediation was undertaken following the event by the insurer. CE says the delay in drying the property has led to the development of extreme visible fungal activity throughout the building. CE says the entire building is significantly contaminated with deep-penetrating microbial activity, including the walls and wall cavities.
CE prepared a quote dated 23 September 2025 for remediation. The quote totals $44,687.50.
Insurer says complainants’ quotes include non-claim related damage
The insurer says the reinstatement costs presented by the complainants are excessive when compared to the SOW from its engineer (CD) and the costings which were validated by the quantity surveyor CR.
The insurer says:
· the quote from JB does not provide a clear cost breakdown
· the complainants’ quote from SR does not provide sufficient detail, particularly regarding the cost breakdown related to the foundations
· the complainants’ builder included work such as underside repairs of the building, external trims, structural floor, and drainage. CD assessed these as maintenance related work
· the complainants’ report from NC did not include all necessary information as it recommended for further assessment by an engineer
· the quote from CE covers demolition and mould remediation only and specifically excludes asbestos removal and any reinstatement works. The total aligns with the allowances contained in the quote from CB for strip and restoration ($36,606 incl margin and GST).
The insurer disputes that it was responsible for the property’s deterioration. It says that strip out works were not completed at the request of the complainants while they considered cash settlement options and whether they may relocate the dwelling for flood prevention purposes.
It says the report from CE does not consider the potential impact of the complainants’ decision to halt works. Further, it does not provide a position on the actual cause of the mould or fungal ecology.
Complainants obtain further reports, including quantity surveying
The complainants obtained a report from a quantity surveyor (AF) dated 13 April 2026. AF reviewed the insurer’s SOW and quotes, the complainants’ quote from SR and provided commentary.
AF identified extensive asbestos cement sheeting throughout the house, including the eaves, internal walls and ceilings. AF said work that disposes or exposes the sheeting must be undertaken by a licensed asbestos removal contractor, and the exposed sheeting must be removed. AF also said the insurer’s quotes should include asbestos testing.
AF also noted that that it is likely the local council will require Development Approval and associated certificates given the extensive works that are required which will incur additional costs. AF also says the house may need to be raised so that the floor level complies with the current requirements. AF says that the insurer’s SOW and quotes have not allowed for this.
AF says:
· the damage to the subfloor and piers is attributable to the flood, noting the extent of the flood
· CR’s SOW fails to specify the actual materials to be used and therefore a valid comparison cannot be made between the quotes of SR and CR
· CR and CB have relied on incorrect quantities. AF says there is a 40% shortfall for the removal and replacement of timber flooring (50m2 versus 70m2 measured)
· CR also miscalculated the number of WC suites and flyscreen doors
CD’s SOW (upon which CR’s quote is based) failed to include:
· subfloor works
· mould remediation, including remediation to the timber framing, subfloor and any remaining surfaces, and removal of external vinyl plastic cladding to allow for mould remediation of the chamferboard wall linings behind
· external cladding which it says is flood damaged, external architraves to doors and windows, and replacement of eave linings
· removal of internal wall and ceiling linings which are asbestos cement sheeting
· under measured door frames and like for like doors, missing framing to the cavity sliding door
· various timber trims including architraves, cornices, skirtings and the like were missing
· some removal and reinstatement of fittings missing
· some tiling including tiling of a shower hob, wall tiles to the oven recess, floor tiles in front of the fireplace
· plumbing of a WC suite and some plumbing fixtures
· electrical items including replacement of electrical meter box, replacement of light fittings, TV aerial cabling and telephone cabling
· items in the detached office including a door and timber threshold to door, sanding of floor
· council and planning fees
· preparation of a Construction Management Plan and Waste Management Plan as required by the council as part of its Construction Certificate application.
AF initially assessed the replacement cost at approximately $502,767 (inclusive of GST) but said a detailed bill of quantities was needed to determine a more precise amount. AF later prepared a bill of quantities dated 22 May 2026 which totalled $349,043. The complainants rely on the assessment of $349,043.
The complainants also obtained an engineer’s report (AM) dated 10 June 2026 following a site visit. AM was engaged to report on the structural adequacy and serviceability of the sub-floor of the property following the flood. AM says:
· the floodwater from nearby R River flowed past the house with a velocity of more than 0.5m/s
· the house was not built to withstand the catastrophic event of February 2022, noting that it is estimated to be a 1 in 1,000-year event
· the edge footings were affected as greater lateral forces were generated, the soil capacity was lessened as the water was present for a long time, and minor disturbances or turbulences causing erosion as the water went past the corners and edges of the property
· these factors affected the founding soil outside and the footings have settled more on the outside compared to the rest of the footings inside
· minor settlement in the timber piers under the building have been caused by the flooding.
AM recommended major re-stumping with new deep footings and steel posts.
Complainants say AF’s costings should be preferred
The complainants say that AF’s quantified SOW most accurately reflects the required repair costs, being $349,043.
The complainants made a commercial offer to resolve the matter. However, this offer was subsequently withdrawn.
Insurer must exercise discretion to cash settle fairly, reasonably and consistent with utmost good faith
An insurer generally has a discretion under the policy to either repair the damage, replace the item or pay the cost of either the repairs or replacement. However, this does not mean an insurer can unilaterally decide how to settle the claim.
When exercising a discretion under the policy, the insurer must do so fairly, reasonably and consistent with the principles of utmost good faith.
The complainants do not dispute the insurer cash settling the claim. However, the extent of the insurer’s liability and quantum is in dispute.
A cash settlement must be based on a reasonable quote for claim related repairs, actionable by a retail customer. An uplift is then to be applied to the quoted amount to allow for contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs.
Insurer maintains its offer is fair
The insurer says that AF’s report does not provide sufficiently reliable, itemised, or evidence-based material to support a re-assessment of the previously validated repair quote. It says AF does not distinguish between:
· damage caused by the insured event
· deterioration due to prolonged inactivity and environmental exposure, and
· works attributable to age, design, or regulatory compliance requirements.
The insurer again says that the repairs and strip outs were paused at the complainants’ request while settlement options were considered. The insurer says the mould proliferation and deterioration may have resulted from this period of inactivity.
The insurer maintains that its assessment of the claim is fair and reasonable having regard to the information obtained during its assessment of the claim.
Complainants’ SOW and Bill of Quantities is preferred
I prefer AF’s SOW and Bill of Quantities to the insurer’s assessment for the following reasons:
· AF identified significant omissions from CD’s SOW and CR’s cost analysis. CR conducted a desktop review, and CD prepared the SOW in December 2022. In contrast, AF inspected the property three times and prepared a comprehensive Bill of Quantities
· the insurer later accepted liability for the foundations, and accepted that the assessment omitted asbestos removal, the fireplace and oven. However, its allowances of $8,000 for foundations and $4,500 for asbestos removal do not account for the extent of the asbestos, council approvals or engineering costs
· CD and CR did not adequately account for mould. CE found mould in the wall cavities. AF allowed for the removal of affected wall and ceiling linings, many of which contain asbestos cement sheeting. The insurer has not provided evidence that refutes AF’s findings about the asbestos
· CD attributed the ceiling and roofing damage to maintenance. However, AF attributed the movement and opened joints in the ceiling linings to structural movement, dampness and mould. CE also identified mould on the ceilings. Given this evidence, and the insurer’s revised position on the foundations and the lack of remedial drying following the insured event, I am satisfied the ceiling damage resulted from the flood
· The insurer did not inspect the property until about two months after the flood. By the time the complainants asked it to stop further strip-out work in September 2022, little remediation had occurred. CB confirmed at that time that drying and restoration were still required. I am satisfied the insurer’s delay significantly contributed to the deterioration and mould at the property.
In September 2025, CB said it could likely undertake the repairs once the foundations were completed and certified. However, it also said the quote might need to be reviewed for current market rates and to ensure the scope covered all items. This does not establish that the quote was actionable which is required for a cash settlement.
For these reasons, I am satisfied AF’s Bill of Quantities is to be preferred.
Uplift of 10% for contingencies to be applied
As the insurer has elected to cash settle the claim, I am satisfied that it is appropriate to include a 10% uplift for contingencies and the loss of a lifetime guarantee on repairs. I am satisfied a 10% contingency uplift is sufficient as:
· the Bill of Quantities was recently prepared
· it has taken into consideration the rural location
· because the property will be extensively stripped back, unidentified damage or other issues is less likely.
Within 14 days of being notified of the complainants’ acceptance of this determination, the insurer is required to cash settle the complainants in accordance with the Bill of Quantities from AF. The insure must include a 10% uplift for contingencies and the loss of a lifetime guarantee on repairs. Therefore, the total amount the insurer is required to pay the complainants for repairs is $383,947.30 less excess.
2.2 Are the complainants entitled to further TA?
Yes. The insurer’s conduct has caused the complainants to incur TA beyond the policy entitlements. The insurer is to pay the complainants $36,714.30 for further TA.
Temporary accommodation payable
I acknowledge the policy contains a 12-month limit for TA and the insurer paid this benefit during the claim. It also offered to cash settle the complainants the remaining entitlement under the policy in the sum of $11,714.30. However, I do not consider the limit applies in circumstances when these costs have been incurred due to the insurer’s conduct rather than the claim. I consider the former applies because:
· the insurer’s first cash settlement offer was made on 31 March 2023, more than 12 months after the insured event
· the insurer has incorrectly assessed its liability under the policy
· the complainants have spent a significant amount of time in temporary accommodation whilst challenging the insurer’s position (and ultimately done so successfully).
Therefore, I consider it fair the insurer should pay the complainants’ further period of TA in accordance with its policy terms. Neither party has provided an estimate of repair time. However, the repairs are extensive, and the complainants have incurred costs in living away from the property for more than four years.
I am therefore satisfied that it is fair and reasonable that the insurer pays further TA in the amount of $25,000 based on the entitlements under the policy. This is in addition to the sum of $11,714.30 previously offered by the insurer as the remaining benefit under the policy.
2.3 Are the complainants entitled to professional costs?
Yes. The insurer is to reimburse the complainants up to $5,000 for professional costs on production of paid receipts.
The complainant incurred professional costs
Under Rule D.5, AFCA may require a financial firm contribute to the professional costs a complainant incurred during a complaint. These costs can be awarded if the complainant needed an expert to understand or establish their claim. These costs are normally capped at $5,000 unless special circumstances apply.
Insurer is required to reimburse professional costs up to $5,000
The complainants obtained reports from hygienists CE and NC, quantity surveyor AF and engineer AM. They also say that they incurred costs obtaining quotes from several builders.
I am satisfied that these reports have assisted in my understanding of the issues in dispute. The insurer is therefore required to reimburse the complainants up to the sum of $5,000 within 14 days of receiving copies of paid invoices from them.
2.4 Are the complainants entitled to non-financial loss compensation?
Yes. The insurer has caused extensive delays and not handled the claim appropriately. The insurer is to pay the complainants $6,300 in non-financial loss compensation.
AFCA can award compensation for non-financial loss
Under paragraph D.3.3 of the AFCA Rules, AFCA may award up to $6,300 for non-financial loss where the insurer’s conduct causes an unusual degree or amount of physical inconvenience, time taken to resolve the situation, or interference with the complainants’ expectation of enjoyment or peace of mind.
Insurer is to pay the complainants $6,300 compensation
I am satisfied that it is appropriate to award the complainants the maximum compensation available under the AFCA Rules.
Although the claim arose following a significant natural disaster, the insurer did not handle the claim appropriately. It significantly delayed its initial assessment and did not promptly arrange remediation consistent with accepted industry practice following flooding.
The insurer says remediation did not proceed because of the complainants’ request. However, that request was not made until September 2022, about seven months after the flood.
The complainants say that despite moving into TA on 7 March 2022, the insurer did not reimburse them for TA until 29 November 2022. They say this caused them financial strain.
I am satisfied the insurer’s claim-handling delays caused a high level of impact for a long time. The maximum award for non-financial loss is therefore appropriate.
2.5 Why is the outcome fair?
The outcome is fair as it reflects the insurer’s obligations under the policy. It ensures the cash settlement covers the insured damage and includes an allowance for contingencies. It also requires the insurer to pay additional TA costs, reimburse professional costs and compensates the complainants for the stress and inconvenience caused by its poor claims handling.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Additional information
Product Disclosure Statement - 20 September 2021
|
Page
|
Policy term
|
21
|
Temporary accommodation
a) If your house cannot be fully or partly used as a result of an insured loss, we will pay for temporary accommodation until your house is rebuilt or restored:
i. we will pay up to 52 consecutive weeks of temporary accommodation up to a maximum of $25,000 for any one event.
b) if your house is not rebuilt or restored, we will pay up to 16 consecutive weeks of temporary accommodation up to a maximum of $10,000 for any one event.
c) no excess is payable when you make a claim under this additional benefit.
|
23
|
If you do not wish to repair or rebuild
a) If we have chosen to repair or rebuild your damaged building and you do not wish to repair or rebuild, we will pay you the lesser of:
i. The amount it would cost to repair or rebuild your building to the same condition it was in immediately prior to the loss or damage up to the amount of the insured sum noted on your Certificate of Insurance, minus any amount for depreciation based on the age and condition of your building.
ii. …