Denial of storm damage claim to balcony and balcony roof based on faulty workmanship and wear and tear exclusions, and claim for further non-financial loss

FirmQBE
Decided2026-01-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Complainants claimed for storm damage to their balcony and balcony roof, which the insurer accepted then denied after further assessments. AFCA found the insurer entitled to deny the claim and declined further non-financial loss compensation beyond the $3,000 already paid.

The proximate cause of the damage was water ingress from faulty workmanship and wear and tear, which are excluded under the policy, and the $3,000 already paid for delay was fair.

Issues

Subjects and remedies

home or building damageno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-251111 | Financial firm | QBE Insurance (Australia) Limited Case number: 12-25-251111 30 January 2026 1 Determination overview 1.1 Complaint The complainants hold a building and contents insurance policy with the financial firm (the insurer) for their home that is located in the State of Victoria (the property). They lodged a claim with the insurer for damage to the property. They say the damage was caused by a storm that occurred on 16 January 2024 (the storm). The insurer initially accepted the claim in May 2024, but later denied it in August 2024 after further assessments of the property were undertaken. The insurer says the proximate cause of the damage is faulty workmanship, wear and tear, and gradual deterioration, which are all causes that are excluded from cover under the terms and conditions of the policy. The complainants say the insurer should accept the claim and repair the damage caused by the storm. The insurer acknowledged a delay in claims handling and paid the complainants $3,000 in non-financial loss compensation. The complainants say they should be entitled to further non-financial loss compensation, given their claim experience. 1.2 Issues and key findings Is the insurer entitled to deny the claim? Yes. The exchanged material shows the proximate cause of the damage is faulty workmanship and wear and tear over time. These causes are excluded from cover under the terms and conditions of the policy. Are the complainants entitled to further non-financial loss compensation? No. Following the initial acceptance of the claim, the insurer conducted further assessments which ultimately led to the claim denial. The insurer acknowledges this caused a delay of approximately three months. The insurer paid the complainants $3,000 in non-financial loss compensation for the delay. A further payment of non-financial loss compensation is not warranted in the circumstances. Why is the outcome fair? The outcome is fair in all the circumstances because: · the damage was caused by factors that are excluded from cover under the terms and conditions of the policy · a further award of non-financial loss compensation is not warranted in this particular instance. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to take any further action in relation to this complaint. 2 Reasons for determination 2.1 Is the insurer entitled to deny the claim? Yes. The exchanged material shows the proximate cause of the damage is faulty workmanship and wear and tear over time. These causes are excluded from cover under the terms and conditions of the policy. Complainants say the storm damaged the property The property includes a rendered two-level, four-bedroom residential dwelling with balconies. It sits upon a concrete slab and supports a metal roof. The complainants say the storm of January 2024 damaged the dwelling, including an upstairs balcony and, in addition, caused part of the roof of that balcony to collapse. They arranged a make-safe to prevent further damage. The complainants lodged the claim in February 2024. They want the insurer to repair the balcony and balcony roof. The insurer accepts intense rainfall occurred during the storm. However, as stated, it denied the claim on the basis the damage was caused by factors that are excluded from cover under the terms and conditions of the policy. Complainants have the onus to establish a valid claim It is established insurance law that the complainants first have the onus to establish the claimed loss is a result of an event covered under the policy that occurred during the period of insurance. This must be established on the balance of probabilities, meaning that it is more likely than not. This is sometimes called a valid claim. If the complainants are able to establish a valid claim, the onus shifts to the insurer to show, on the balance of probabilities, it is entitled to rely on an exclusion under the policy to deny the claim, either wholly or in part. Policy covers damage caused by insured events The terms and conditions of the policy are set out in the policy documents, including the Product Disclosure Statement (PDS) and the Certificate of Insurance. The parties agree the insurer provided a copy of the policy documents to the complainants. It follows the insurer is entitled to rely upon the terms and conditions of the policy. The policy provides cover for damage caused by a variety of insured events, including ‘storm’. Page 15 of the PDS includes the following: Specified Events The following is a list of some of the most common events that may cause accidental loss or damage to your property, for which you are insured. This is not an exhaustive list: ‘Specified Events’ means loss or damage directly caused by the following events (a) to (r): […] (q) storm, tempest, rainwater, flood, wind, hail, tornado, cyclone or hurricane, freeze or weight of snow; […] The policy definitions generally mean cover is provided for damage caused by a single insured event or a series of related insured events. For example, the policy will cover damage caused by a single storm, or a series of related storms that occur during a single identifiable weather event. However, the policy does not cover damage caused by unrelated storms that occur over an extended period of time. In addition, the policy provides cover for accidental damage. Page 15 of the PDS also states: You are insured against: · accidental loss or damage (including but not limited to, the ‘Specified Events’ listed below)… to your home and/or contents at the site during the period of insurance unless we say otherwise in this policy wording (see ‘Section 7: When you are not covered (General exclusions)’). ‘Accidental’ damage is generally defined as unintended and unexpected damage to the property. Cover is subject to limitations, conditions and exclusions The cover provided by the policy (in relation to both accidental damage and damage caused by specific insured events) is subject to limitations, conditions and exclusions. General policy exclusions are set out at pages 30 to 33 of the PDS. In this matter, the insurer relies upon the following policy exclusions to deny the claim: Section 7: When you are not covered (General exclusions) […] There is no cover under any section of your Policy for any claim, loss, cost, damage, injury, death or legal liability caused by or arising from: • your failure to fix: a defect; a structural fault; a design fault; or faulty workmanship, as soon as is reasonable after you become aware of it, or a reasonable person in the circumstances would have become aware of it; • your failure to fix damage that existed prior to the incident or occurrence as soon as is reasonable after you become aware of the damage, or a reasonable person in the circumstances would have become aware of it; […] There is no cover under any section of your Policy for any: • wear, tear, depreciation, rust, oxidisation, corrosion, fading… • defect, structural fault, design fault or faulty workmanship. Make safe and repairs were completed On 25 January 2024 PL, plumber, completed a make safe and repairs for the complainants, including the following works: · full gutter clean to both sides of the roofline removing all debris · stripped flashings and perimeter cappings to allow for the removal of the box guttering · supply and installation of approximately 8l metres of new box guttering · application of fiberglass over rusted out roof sheeting · application of two coats of waterproofing fibre membrane to roof sheeting. PL did not comment on the cause of the damage. Additional make safe and repairs were undertaken by HE, builders in April 2024, including the installation of timber framing and propping to the lower and upper-level balconies. HE did not provide any instructive commentary about the cause of the damage. Complainants also engaged an engineer to inspect the property The complainants arranged for BO, engineer, to inspect the property shortly after the storm occurred. BO also inspected the property on subsequent occasions over the following 12 months or so. BO provided two reports dated 24 January 2024 and 20 December 2024. BO’s December 2024 report includes the following observations and comments: · there is evidence of corrosion at the corner connection of the upper-level balcony, but corrosion can develop rapidly due to moisture and environmental exposure · the insurer should not dismiss the claim for the damage to the upper-level balcony based on potential maintenance issues at the roof level · Melbourne experienced storms at the time of the insured event and it is more likely the storm directly impacted the connection of the balcony, rather than the cause proposed by the insurer · on the balance of probabilities, the damage to the balcony is not directly related to roof maintenance issues · the significant storms may have compromised the sealant within the balcony structure, leading to water ingress and shear failure at the connection · the beam forming the balcony appears to be in reasonable condition and, if the damage was due to prolonged maintenance issues, more widespread corrosion would be evident · the insurer cannot reasonably dismiss the issue as a maintenance matter without supporting evidence for the balcony area · it is reasonable to conclude the damage is not directly caused by roof-related issues. Complainants have established a valid claim I am satisfied the complainants have established a valid claim for the damage to the balcony. This is because: · the insurer accepts the storm occurred and was severe in nature · the complainants say the damage occurred during the storm. They said they heard a loud bang during the night and discovered the ceiling of the upper-level alfresco balcony had fallen · the complainants say BO’s reports support their submission that the storm was the proximate cause of the damage · the damage was unintended and unexpected. As stated, the onus now shifts to the insurer to show, on the balance of probabilities, it is entitled to rely on an exclusion under the policy to deny the claim, either wholly or in part. Insurer also arranged for experts to inspect the property BR, builder, inspected the property on behalf of the insurer on 26 March 2024. Upon inspection, BR observed the damage and concluded: In my opinion, [the] damages were caused by [the] damaged box gutter overflowing or leaking, into the ceiling void and onto the steel support (the steel support post is contained within a decorative plaster column and the water leak was not visible to the insured). The water has travelled down the steel support/column and onto the timber and steel framing below. The timber and steel framing have been compromised by the water and the upper-level steel support has dropped approximately 40mm. The insurer appointed SG, loss adjuster, to assist with the management of the claim. SG provided several reports dated between 10 July 2024 and 1 May 2025. SG’s engineering services, SE, also provided a detailed report after inspecting the property on in July 2024. SE concluded: The moisture damage to the balcony ceiling has occurred due to defective construction of the roofing that is unable to prevent rainwater ingress to the roof frame. In a supplementary report dated 1 May 2025, SG summarised SE’s evidence and concluded: … the cause of the deterioration damage to the timber and steel structure of the southeastern section of the balcony is gradual moisture ingress through the cracks in the surface near the southeastern columns of the balcony. The dished down surface near the south-eastern columns also has caused rainwater ponding and further moisture ingress to the structure. The dished down and cracked surface near the south-western columns of the balcony, as well as the cracks to the rendered cladding to the southern side of the dwelling, have occurred due to settlement of the inadequately supported balcony posts over the long term as a result of defective and non-compliant construction of the balcony. Hence, the proximate cause of the damage to the balcony and rendered cladding to the southern side of the dwelling is considered to be defective and non-compliant construction of the balcony. SG also noted the application of sealant to the cracked surface near the balcony posts by a previous owner and stated: [This] indicates that the failure of the connection joint of the balcony posts and resultant dished down and cracked surface near the balcony posts had occurred in the past prior to the purchase of the property by the Insured. Furthermore, historical photographs of the dwelling that were captured prior to the event and prior to the installation of the temporary props confirms that the cracks to the southern side of the dwelling had existed prior to the [storm]. In addition, SE provided a scope of works (SOW) regarding the rebuilding of the balcony dated 11 July 2024. The SOW includes illustrative photographs of the damage. CR, roof plumber, inspected the property on behalf of the insurer on 24 July 2024, after the make safe and initial repairs had been completed. CR reported, amongst other things: · the depth of the original box gutters was non-compliant · where the make safe has been carried out directly over the affected area, the depth of the new box gutter is also non-compliant. The depth is only 35mm. Minimum depth should be 100mm · the new sump in the section of box gutter that had been replaced as a make-safe is also non-compliant. It has been installed inside the gutter instead of underneath it · the apron flashings only cover one rib on the roof sheets, instead of two ribs · the bottom of some roof sheets have had water proofing membranes applied to them due to rusting · the screws on the parapet cappings are rusted, as well as missing rivets and being poorly sealed · the remainder of the roof showed evidence of waterproof patches over rusted roof sheets. CR concluded the damage was caused by faulty workmanship and installation issues. SG subsequently summarised the conclusions of SE, BR and CR. SG says the proximate cause of damage was defective construction of the circular column base to the first-floor balcony. This allowed water to pond near the columns and gradually ingress into the balcony roof. SG further concluded that moisture damage to the balcony ceiling was due to defective roofing construction, which failed to prevent rainwater ingress into the roof frame. Proximate cause of damage needs to be assessed Damage can have more than one cause. For instance, in this matter the complainants say the damage was caused by the storm. In contrast, the insurer says the damage was caused by a combination of factors, such as wear and tear, faulty workmanship and a failure on the part of the complainants to fix a defect, both of which are excluded under the terms and conditions of the policy. In deciding whether the policy responds, it is necessary to identify the proximate cause of damage. The proximate cause is not necessarily the first or the last or the sole cause of the loss. It is the effective or dominant or operative cause of the loss. If there are several causes of a loss operating contemporaneously, each must be examined for the qualities of reality, predominance and efficiency as the active, efficient cause that sets a relevant chain of events in action. If one cause would have caused the harm in any case, and the other would not have done so in the absence of the first, the first is the proximate cause. Storm was not the proximate cause of the damage In all the circumstances, I am of the opinion the exchanged material shows the storm was not the proximate cause of the damage. Indeed, I am satisfied the damage to the balcony was primarily and predominantly caused by factors that are excluded from cover under the terms and conditions of the policy including, primarily, wear and tear over time and faulty workmanship. It follows the insurer is entitled to deny the claim. This is because of the following considerations. First, BO’s report dated 20 December 2024 acknowledges corrosion within the balcony, yet it does not satisfactorily explain the cause of corrosion. Indeed, in comparison to the evidence upon which the insurer relies, BO’s explanation about causation is generally speculative and somewhat inconclusive, and it does not provide substantive, persuasive evidence regarding the cause of the damage. Second, I acknowledge the complainant says the property was well maintained before the balcony roof collapsed. Moreover, they say they were not aware of any pre-existing issues (including faulty workmanship or defects). The complainants say the sealant, cracks and construction issues noted by the insurer’s experts were not disclosed or visible as structural concerns before the insured event occurred. They also submit that, if these issues were visible, they were present when the property was insured. However, I note SG’s supplementary report dated 23 April 2025. This report includes street view images of the property taken in 2013 and 2023, which show cracks in the rendered cladding, well prior to the insured event. Moreover, despite delivering two reports following the insured event, I note BO was initially engaged by the complainants in December 2023, about a month before the storm occurred. BO states the purpose of their inspection at that time was as follows: [BO] completed an initial site inspection and provided an initial consultant advice notice requesting further investigative works are undertaken to expose the primary connection details at the corner edge of the balcony. Please refer to initial [BO] report – 23054… Review Structural Integrity of Balcony - 13.12.2023 with commentary of existing balcony configuration and condition. In its first report dated 23 January 2024 (that is, following the storm), BO said of that earlier inspection in December 2023: [BO] had previously reviewed the balcony and was of the opinion the connection between the corner column (C1) and the adjoining structural beams (B5) running perpendicular to each other to frame out the balcony had been adversely impacted and required further investigation by exposed the members for additional review. This adds weight to the insurer’s submission that the complainants were likely aware of an issue with the balcony before the insured event happened. Third, the identification of previous substantial repairs to the roof the property, as well as the application of sealant to the cracked surface of the balcony posts by a previous owner, tend to indicate the presence of pre-existing issues. In this regard, CR’s report includes many illustrative photographs of the roof which, amongst other things, depict the extent of the pre-existing roof damage and works undertaken to repair such damage. This supports the insurer’s submission that wear and tear over time had affected the roof. Fourth, expert reports relied upon by the insurer include photographs showing water stains on the balcony roof prior to the storm, as well as substantial wear and tear and corrosion in the internal balcony and column structures. It is reasonable to conclude such corrosion and wear and tear had been occurring well before the insured event happened. Fifth, CR’s evidence regarding non-compliant guttering is not contested. Sixth, SG’s and SE’s conclusions about the cause of the damage are generally consistent with BR’s conclusion. In summary, I am satisfied the exchanged material shows the proximate cause of the claimed damage was water ingress as result of faulty workmanship (including defects) and wear and tear over time. It follows the insurer is entitled to rely upon the terms and conditions of the policy to deny the claim. Insufficient information to show the claim was denied due to repair costs In their written submissions the complainants express concern that the claim was denied due to the cost of repairs initially quoted. The insurer acknowledges it confirmed acceptance of the claim on 12 April 2024. The insurer says this decision was based upon the information and evidence available at the time. Once further evidence was obtained, it was entitled to alter is decision to deny the claim. However, the complainants say the insurer only exercised its right to obtain further evidence after receiving an initial quotation for the repairs. The insurer says when it receives a SOW or a quotation for claim-related repairs, criteria exist which allows the SOW or quotation to be accepted without further review. However, in this case, the cost of repairs exceeded the relevant threshold, and the matter was referred to the insurer’s specialist claims team to validate the submitted costs. Upon receiving the initial quotation, the specialist claims team identified concerns about the cause of the claimed damage. The insurer’s specialist claims team then instructed the claims team to arrange a further assessment to validate the cause of damage and prepare a revised SOW. Based on the claim notes provided by the insurer, I am satisfied the procurement of additional evidence was not due to the cost of repairs quoted initially, but rather the referral team’s assessment of the cause of damage. The insurer says, in any event, due to the nature of the works required, the claims team would have engaged an engineer regardless. On this basis, I am satisfied the claim was not denied due to the cost of repairs. 2.2 Are the complainants entitled to further non-financial loss compensation? AFCA may award non-financial loss compensation in certain circumstances Under the AFCA rules, non-financial loss compensation (capped at $6,300) may be awarded in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, complainants should note that non-financial loss is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Moreover, non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer. Non-financial loss compensation already paid by the insurer I accept the complainants in this matter have suffered an unusual degree of physical inconvenience and interference with their expectation of enjoyment and peace of mind. In recognition of this, the insurer paid the complainants $3,000 in non-financial loss compensation. However, the complainants say their hardship has continued from 16 January 2024 through to the time they lodged their complaint with AFCA, a period of more than 18 months. On this basis, they seek $6,000 in non-financial loss compensation (see the complainants’ written submissions). I reviewed the insurer’s claim notes. On balance, I am persuaded that, apart from the additional assessments and its change in decision about claim acceptance, there is no evidence of unreasonable delay caused by the insurer. AFCA expects complainants to be moderately robust when making a claim. Compensation is not awarded for the ordinary inconvenience involved in the claims process. I do not consider it reasonable for further compensation to be paid. I accept the insurer has not made an error in its claims handling or decision that would warrant additional compensation. Based on this, I am satisfied the $3,000 in non-financial loss compensation already accepted by the complainants is fair and reasonable in the circumstances. 2.3 Why is the outcome fair? Damage not caused by an insured event The outcome is fair in all the circumstances because: · the damage was caused by factors that are excluded from cover under the terms and conditions of the policy · a further award of non-financial loss compensation is not warranted in this particular instance. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.