Cash settlement offer for storm damage inadequate; mould remediation, temporary accommodation and claim handling disputed
Text of the determination
Determination
|
Case number
|
12-25-249592
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-25-249592 21 May 2026
1 Determination overview
1.1 Complaint
The complainant is a beneficiary under a residential strata policy. The complainant lodged a claim with the financial firm (insurer) under the body corporate’s insurance policy. This is for the damage sustained to his unit following a storm.
The insurer offered the complainant to cash settle its liability. The complainant is dissatisfied with the cash settlement and states it does not adequately cover all the storm related damage and associated losses. Further, the complainant is dissatisfied with the insurer’s handling of the claim.
1.2 Issues and key findings
Is the insurer required to increase its offer for repairs?
Yes. The insurer is required to pay the complainant:
· $13,711.54 for the water damage plus interest from 9 May 2025, being the date of the updated quote, until the date of the payment less any policy deductibles
· $165 for the electrical assessment fees.
Is the insurer liable for further temporary accommodation?
The insurer is required to settle the complainant:
· four weeks for the bathroom, toilet, and linen cupboard repairs; and
· any additional period required for mould remediation, if supported by the hygienist’s assessment.
Is the insurer liable for compensation?
The insurer handled the claim poorly and is required to pay the complainant $3,000 compensation.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of receiving notice the complainant accepts this determination, the insurer is required to pay the complainant:
· $13,711.54 for the water damage plus interest from 9 May 2025, being the date of the updated quote, until the date of the payment less any policy deductibles
· $165 for the electrical assessment fees
· $3,000 for the non-financial compensation
The insurer is also required to engage a hygienist and settle the complainant for the appropriate mould remediation costs. The insurer should also settle temporary accommodation in the manner set out in section 2.2.
2 Reasons for determination
2.1 Is the insurer required to increase its offer?
Yes. The insurer is required to pay the complainant:
· $13,711.54 for the water damage plus interest from 9 May 2025, being the date of the updated quote, until the date of the payment less any policy deductibles
· $165 for the electrical assessment fees.
Parties dispute the extent of the storm related damage to the property
It is well established insurance law that the complainant bears the initial onus of establishing that a loss has occurred which is covered by the terms and conditions of the policy. This is known as a valid claim.
If the complainant establishes a valid claim under the policy, the onus then shifts to the insurer to establish the basis on which it seeks to deny the claim.
The policy covers the property against damage. It defines ‘Damage’ as accidental physical loss of, or destruction of property from any sudden and accidental cause not otherwise excluded by the policy.
There is no dispute that storm water entered the property and caused damage. Parties dispute the extent of the insurer’s liability.
The insurer assessed the damage and agreed to cover:
· two roof tiles
· reinstatement of the skydome
· the resultant water damage to the toilet and bathroom.
The insurer provided liability quote from its builder (BM) totalling $6,807.63. This is for the plastering and painting of the bathroom and toilet ceilings and cornices and the repairs for the two roof tiles and the sky dome cover.
The complainant provided a quote from his builder (PC) totalling $37,972.76. This is for the replacement of the bathroom, and repairs to the toilet and the linen cupboard.
On balance, the storm caused some but not all the mould
There is no dispute that mould is present in the bathroom and the roof cavity. The insurer’s hygienist (VA) assessed the cause and the extent of the mould. In his report, VA states:
· an abnormal fungal ecological environment is evident within the property
· the underside of the bathroom ceiling has previously been impacted by humidity damage from ongoing shower use combined with poor ventilation due to an inoperable exhaust fan
· the fungal growth backside of the ceiling lining in both the bathroom and the toilet indicate a top-down water ingress event
· surface sampling of staining on the bathroom ceiling identified mould ‘Cladosporium spp’ which is commonly associated with humid and poor ventilated bathrooms
· air sampling detected low to moderate levels of Cladosporium spp throughout the property which is consistent with cross contamination from cleaning activities undertaken without containment or air filtration in place.
VA concluded that remediation works associated with the top-down water ingress are required to return the internal environments to normal fungal ecology condition. Further VA states the backside of the ceiling above the linen cupboard does not show any fungal growth.
VA recommended the removal and disposal of the ceiling lining and associated cornices in the bathroom, the toilet and the skylight shaft.
Amongst other things, the complainant states that the insurer’s builder accidentally disconnected the exhaust fan resulting in the wide spread of mould. I am not persuaded by this argument.
For clarity, I accept VA identified two sources for the mould:
· humidity damage from the ongoing shower use exacerbated by the lack of ventilation
· the top-down water ingress event.
Firstly, a contemporaneous assessment conducted by the insurer’s assessor (EX) and the complainant’s restoration company (WD) following the claim lodgement showed mould to different areas of the bathroom. This included underneath the light fittings, in the cornices, and on parts of the ceiling.
WD attended the property approximately two days following the storm and mould is evident in his photographs taken during that inspection. This is also consistent with EX’s initial assessment conducted approximately two days following the storm.
On balance, I accept mould was a pre-existing issue prior to the subject water ingress event. There is no dispute that the insurer has remediated the mould previously, however it has subsequently re-manifested.
While the complainant raised concerns regarding VA’s assessment, he did not provide any persuasive evidence to refute its findings.
Secondly, I acknowledge the complainant’s argument that the further mould was caused by the insurer’s error. The complainant’s electrician (VL) states he investigated the non-functional exhaust fan which is located in the bathroom. In his report, VL states:
· the exhaust fan switch had been physically disconnected at the wall switch
· the ceiling light had been disconnected at the fitting only
· based on the wiring layout and the test results, it appears the intention during the original disconnection was to isolate the ceiling light circuit, however, the fan switch was mistakenly removed instead of the light switch wiring
· no fault was identified to the exhaust fan, and the disconnection appears manual rather than due to equipment failure.
The complainant submits that the insurer’s builder, who carried out the make safe repairs, has accidentally disconnected the exhaust fan. The exchanged information shows that the insurer carried out the make safe repairs in November 2024. The insurer refutes this assertion and has provided its electrician’s compliance certificate outlining that he disconnected the bathroom oyster light due to water ingress.
Even if I were to accept (which I do not) the insurer’s builder has accidentally disconnected the fan, I am not satisfied the insurer is liable for the mould inside the bathroom. There is no compelling contemporaneous evidence to show that the complainant has advised the insurer of this issue after the make safe repairs but rather later months.
Importantly, I accept the proximate cause of the evident mould in the bathroom is the inadequate ventilation, which is a pre-existing condition. While the non-functioning exhaust fan may have exacerbated the situation, I am not satisfied it is the operative cause of the loss.
That said, I accept the exchanged evidence indicates that some mould manifested following the water ingress event, for which the insurer is liable.
VA identified fungal growth to the backside of the ceiling lining in the bathroom and toilet. Further, in February 2026, BM noted the wool batts above the bathroom showed it had been wet.
VA stated that regardless of the ventilation issue, fungal growth on the backside of the ceiling lining of both the toilet and bathroom is consistent with the top-down water ingress event.
Relevantly, VA did not take any samples of the noted fungal growth in the ceiling cavity. However, the photographs show substantial fungal growth to the skylight shaft and timber framing. This is in addition to the backside of the ceiling’s linings.
I am satisfied the insurer is liable for the remediation of the noted fungal growth in the roof cavity. Neither party provided any evidence outlining the nature and type of mould in the roof cavity above the toilet and bathroom, nor the appropriate remediation method.
No persuasive evidence the bathroom requires demolition and replacement
I have carefully considered the complainant’s quote. I am not satisfied that it fairly or reasonably reflects the extent of the storm damage to the bathroom. In other words, there is insufficient evidence that the entire bathroom has been storm damaged.
There is no persuasive evidence to show that the shower screen and cabinet, the waterproofing, the window or the vanity were damaged or required to be replaced to remediate the water damage to the ceiling and upper walls.
While WD notes the elevated moisture levels following the event, there is no conclusive evidence to support a full bathroom replacement is warranted. The exchanged evidence shows that the damage is limited to the roof cavity and the upper parts of the walls. There is no persuasive evidence that the water has travelled beyond these areas. I acknowledge the complainant raised several arguments; however, I am not persuaded by them for the reasons set out above.
The insurer’s assessment does not factor in all of the damage
The insurer’s scope is largely limited to plastering and painting the ceilings and the cornices of the bathroom and toilet.
I have carefully considered the exchanged evidence and the parties’ respective submissions. I am not satisfied the insurer’s cash settlement offer is fair or accurately reflect the storm related damage, including the mould remediation for the roof cavity and the replacement of affected ceilings as VA recommended.
Firstly, I am not satisfied the water damage is limited to the ceilings only. This is because BM’s assessment in 2026 shows cracking in the upper parts of the walls.
WD assessed the property on 12 November 2024 and states:
· high moisture readings are evident to the toilet and bathroom ceilings
· possible water ingress had passed the ceiling and worked its way down the wall structure
In his report WD says there are high moisture levels to the walls as well as the ceilings of the bathroom, toilet and linen cupboard. The exchanged photographs show several high moisture readings. The photographs show that the readings are limited to the upper parts of the walls and the ceiling.
Secondly, the insurer’s quote does not factor in any mould remediation to the roof cavity including above the toilet and the bathroom. There is no dispute that manifested fungal growth and the possibly damaged batts are related to the storm event.
While the insurer maintains that BM’s quote is fair and reasonable, it has not demonstrated its adequacy. In other words, the quote does not factor in the removal, disposal and/or treatment of the mould affected areas in the roof cavity. Further, the exchanged evidence does not clearly establish the correct rectification method to address the mould affected structure.
For clarity, I do not accept that the insurer is liable for internal mould remediation within the bathroom itself. This is because I am satisfied, on balance, that this mould is pre-existing and was exacerbated by inadequate ventilation.
Thirdly, I acknowledge the insurer says that there is no damage to the linen cupboard. I do not accept this assertion. The floor plan shows the linen cupboard is located in between the bathroom and the toilet. There is no dispute that both areas have been water damaged. On balance, I accept the linen cupboard has been damaged during the storm event.
The insurer’s quote is a reasonable starting point for quantum assessment
The insurer says it is unable to carry out the repairs due to maintenance related issues to the roof, mainly the absence of weep holes. That said, the complainant does not dispute that a cash settlement is an appropriate method of resolving the claim.
Given the breakdown of communication between the parties and the complainant’s lack of trust, I accept a cash settlement is a reasonable option to settle a long dispute. Further, under the terms of the policy, the insurer can either repair the damage or pay the amount it would cost to repair.
I have carefully considered the exchanged evidence and the parties’ submissions. On balance, I accept the storm has damaged the bathroom, toilet and linen cupboard beyond the scope reflected in BM’s estimate.
On balance, I accept it is plausible that water has affected the upper sections of the walls. BM’s assessment in February noted further cracking damage to the walls which BM attributed to the storm event.
That said, I am not satisfied that a full bathroom replacement is substantiated in the circumstances. While WD suggests that water travelled down the walls, there is no persuasive evidence to support this assertion. WD’s moisture readings primarily relate to the ceilings and cornices, rather than lower wall areas. In other words, there is insufficient evidence to demonstrate that significant volumes of water travelled down the walls so as to impact the entirety of the bathroom.
On balance, if this were the case, further indicators of damage, such as staining to the walls or paint bubbling beyond the upper sections, would likely be evident, as is seen in the cornices. This is not the case here.
VA recommended the replacement of the ceilings in the bathroom and toilet. This has not been reflected in BM’s quote. PC’s quote estimated the replacement of the entire bathroom wall sheets and ceiling as $2,220 and the painting as $1,900. I note these figures relate to the entire bathroom and are GST exclusive.
BM has estimated the plastering and the painting of the bathroom to be $5,457.45. I note this amount does not factor in the replacement of the ceilings or the upper sections of the walls. Therefore, I consider it is fair and reasonable, for the purpose of finality, that the insurer adds a 50% contingency to BM’s bathroom quote to reflect the replacement of the ceiling, cornices and the upper parts of the walls.
Having regard to PC’s allowances of $2,220 for wall and ceiling replacement and $1,900 for painting (GST exclusive), I am satisfied that applying a 50% contingency uplift to BM’s allowance results in a reasonable approximation of the additional scope. In this context, the uplift is proportionate and adequate to capture the ceiling replacement, cornices, and upper wall works not otherwise included.
Therefore, within 14 days of receiving notice the complainant accepts this determination, the insurer is required to pay the complainant $8,186.18
· $5,457.45 for the estimated bathroom repairs
· $2,728.73 as 50% contingency to factor in the replacement of the ceilings and upper parts of the walls.
For completion, I will make the following comments. I note the complainant says additional cracking has formed near the bathroom window and the ceiling line and that these cracks were not present prior to the storm. I accept the above cash settlement will factor in the cracking in the ceiling line.
However, there is no persuasive or conclusive evidence to establish that this damage is related to the subject storm event. While I note that cracking is present in areas where water damage to the cornices and ceilings has been identified, and there may arguably be a causal link in those immediate areas, this does not extend to damage located further from the point of water ingress.
While the complainant relies on WD’s moisture readings, I am not satisfied it is persuasive to establish a causal link between the storm and damage that is located remotely from the point of water entry.
Insurer is required to pay complainant $4,831.15 for toilet and linen cupboard
BM provided a quote for the plastering and the painting of the toilet totalling $992.68. PC’s quote factors in the replacement of the linen cupboard. This is in addition to the replacement of the toilet ceiling and the wall between the toilet and bathroom and the internal sheets of the skylight that has been affected by the storm event.
BM did not include the wall between the toilet and the bathroom in its quote. For finality, I accept that insurer should play the complainant for the replacement of this wall. PC noted water damage to this wall and the insurer did not refute PC’s assertion.
I find PC’s quote to be conclusive and in line with VA’s recommendations. Therefore, for finality, I consider it fair that the insurer pays the complainant $4,831.15:
· $2,464.91 for the replacement of the linen cupboard
· $2,366.24 for the repairs to the toilet.
Insurer is required to pay complainant $694.21 for the roof tiles and sky dome
Parties do not dispute the roof tiles, and the sky dome cover were damaged during the storm. BM provided a quote for these repairs totalling $603.66. The complainant does not dispute BM’s quote.
Given these items are not in dispute, I consider it fair that the insurer pays the complainant $603.66 plus 15% contingency totalling $694.21.
There is no persuasive evidence the insurer settled this portion of the claim.
Insurer is required to engage a hygienist to assess the roof cavity mould
Neither party has clearly established the appropriate remediation method regarding the manifested fungal growth in the roof cavity in light of VA’s assessment. For clarity, VA recommended the removal of the ceiling linings and associated cornices in the bathroom, toilet and the skylight shaft in the toilet. While part of VA’s recommendation has been factored in above settlement, I accept the insurer is required to assess the extent of the fungal growth damage to the roof cavity that is related to the storm event.
Therefore, within 14 days of receiving notice the complainant accepts this determination, the insurer is required to contact the complainant to organise a hygienist assessment. This hygienist should review VA’s assessment, undertake his/her own investigation, including taking any necessary samples. The hygienist should compile a costed scope of works.
The insurer is then required to cash settle the complainant for the cost of mould remediation (to the extent this is not covered by the works above) and should also include the cost of any post remediation verification if applicable. For clarity, the insurer is only liable for the remediation that has manifested in the roof cavity related to the top-down water ingress event.
It is fair the insurer reimburses the complainant $165 for VL’s fees
The claim notes show that the insurer was considering reimbursing the complainant for WD’s fees. It is unclear whether it has done so or not.
I am satisfied that WD has assisted the complainant in establishing the water ingress event. While he did not establish the extent of the loss, WD’s assessment triggered further investigations. Unless the insurer has done so, it is required to reimburse the complainant for WD’s fees.
The complainant VL’s invoice totalled $165. The complainant says:
· he hired VL due to electrical safety issues
· VL assessed the exhaust fan
· the light wiring was live and was hanging through the ceiling since the make safe repairs
· VL made the area safe and temporarily covered the ceiling opening
The exchanged information shows that VL has carried out some make safe repairs to secure live wires. I consider it is fair that the insurer reimburses the complainant $165 for VL’s fees.
The complainant says he has incurred costs to obtain a quote for repairs. The complainant did not provide any invoices or proof of payment to substantiate this.
2.2 Is the insurer liable for temporary accommodation?
The insurer is required to settle the complainant:
· four weeks for the bathroom, toilet, and linen cupboard repairs; and
· any additional period required for mould remediation, if supported by the hygienist’s assessment.
The policy covers temporary accommodation in certain circumstances
There is no dispute the policy covers the reasonable cost of temporary accommodation incurred if the lot is unfit to be occupied for its intended purpose due to damage to the property.
The policy states that the insurer will pay temporary accommodation until the time the unit can be occupied again following the completion of the repairs.
The complainant says that he is entitled to receive temporary accommodation as the property was not habitable for an extended period of time. While I acknowledge the complainant’s substantial submissions regarding the habitability of the property since the claim lodgement, there is no persuasive evidence that the complainant has incurred any costs. In the circumstances, the insurer is not required to reimburse accommodation costs that were not actually incurred.
The exchanged evidence shows that the insurer has paid for some temporary accommodation previously under the claim.
The insurer should allow four weeks of accommodation
I accept the insurer is liable for accommodation for the duration of the insurable repairs. Considering the evidence as a whole and the extent of the repairs to be carried out to the toilet, bathroom and the linen cupboard, I accept the temporary accommodation benefit is triggered for the duration of the repairs. There is no dispute the bathroom and the toilet would be rendered unusable for the duration of the repairs.
The insurer has estimated the repairs to take approximately two weeks. However, I consider it fair and reasonable to extend this period to four weeks to allow for the replacement of the ceilings, as recommended by VA. For clarity, this four-week period relates solely to the rectification of the water damage and does not include remediation period of fungal growth within the roof cavity.
The hygienist, to be engaged by the insurer to assess the fungal growth in the roof cavity, should also estimate the duration required for mould remediation, including any associated repairs. The insurer must then add this remediation period to the four-week accommodation period outlined above, if warranted.
In other words, the hygienist should assess whether it is necessary for the complainant to vacate the property during the remediation works. If so, the insurer must compensate the complainant for any additional reasonable accommodation costs incurred for that period.
Accordingly, based on the most extensive (reasonable) scope of works, the insurer is required to compensate the complainant for reasonable temporary accommodation costs, including:
· four weeks for the bathroom, toilet, and linen cupboard repairs; and
· any additional period required for mould remediation, if supported by the hygienist’s assessment.
2.3 Is the insurer liable for compensation?
The insurer handled the claim poorly and is required to pay the complainant $3,000 compensation.
The complainant is not satisfied with the insurer’s handling of the claim
AFCA may award compensation for non-financial loss if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and delays. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation.
Amongst other things, the complainant says the insurer:
· mishandled the claim causing excessive and avoidable delays
· initially denied the claim based on inaccurate assumptions and misrepresented facts
· failed to remediate the mould in a timely manner
· delayed offering alternative accommodation
· ignored the health impact on his family.
The insurer is required to pay the complainant $3,000 compensation
The exchanged evidence shows the complainant raised concerns regarding the cleaning products that were used by the insurer during the mould remediation. I accept the insurer provided information to show that ‘Chloradet’ is approved for use in residential and hospital setting. Further, the exchanged emails show that the mould remediator accommodated the complainant’s concerns where possible. I acknowledge, however, there was a breakdown of communication between the parties.
I acknowledge the complainant’s concerns given his partner was pregnant at the time. That said, there is no persuasive evidence that the insurer has used an inappropriate product or that there was another product that was more appropriate.
While I accept the insurer is not liable for some of the manifested mould given it is pre-existing, I equally accept the insurer at times was dismissive of the complainants’ concerns. For example, the complainant raised concerns regarding potential cavity damage. Although the insurer later accepted the presence of additional damage, it did not take reasonable steps to incorporate these findings into its scope of works or to address them in a timely manner.
Further, VA did not adequately address the mould within the roof cavity. While the presence of mould was noted, no sampling was undertaken, nor was a clear remediation methodology provided
The available evidence also indicates the insurer initially denied the claim based on an incorrect understanding of the circumstances. In particular, the insurer does not dispute that it mistakenly attributed damage arising from its own make-safe works to pre-existing roof issues. I accept that the insurer, at times, lost proper oversight of the claim, resulting in avoidable delays.
Having regard to the above, I am satisfied the insurer has handled the claim poorly. In particular, it failed to properly investigate and quantify the full extent of its liability, despite having access to sufficient information through multiple assessments.
The claim notes further indicate that much of the communication was initiated by the complainant, rather than the insurer. I accept that the manner in which the claim was handled has caused inconvenience and distress to the complainant and his family.
Accordingly, I consider it fair and reasonable that the insurer pays the complainant $3,000 in compensation for its poor claims handling.
2.4 Why is the outcome fair?
The parties are bound by the terms and conditions of the policy. The available evidence shows that the complainant suffered storm-related damage beyond that reflected in the insurer’s offer, although not to the full extent claimed by the complainant. In the circumstances, it is fair and reasonable that the insurer increases its settlement to account for additional damage, and that it engages a hygienist to properly assess the fungal growth within the roof cavity. It is also appropriate that the insurer compensate the complainant for its poor claims handling.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.