Cash settlement amount and scope of repairs after sewage damage to granny flat; temporary accommodation and compensation

FirmAuto & General
Decided2026-05-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant disputed the insurer's cash settlement for sewage damage to her granny flat and sought temporary accommodation, legal fees and compensation. AFCA found the insurer's scope incomplete and required a revised quote settled with a 20% uplift if cash settled, but rejected the other heads.

The policy allows the insurer to repair or cash settle at repair cost, and the scope must cover all works recommended by the hygienist, while temporary accommodation applies only if the home is unliveable and both parties contributed to delay.

Issues

Subjects and remedies

home or building damagepay claimreassess claim

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-236976 | Financial firm | Auto & General Services Pty Ltd Case number: 12-25-236976 23 April 2026 1 Determination overview 1.1 Complaint The complainant lodged a claim with the financial firm (insurer) under her home and contents insurance policy on 16 August 2024. The granny flat including its contents at the property had sustained damage after category 3 sewage water escaped and entered the property. The insurer accepted the claim and offered a cash settlement because the relationship between the parties, including its builder JP, had broken down. The complainant is represented by a solicitor. For ease of reference, both the complainant and her solicitor will be referred to as ‘the complainant’ unless specifically mentioned. The complainant seeks the insurer to increase the settlement offer based on her builders’ (HE, RM and VI) quotes, pay temporary accommodation and compensation for its claim handling. The contents damage settlement is resolved between the parties. 1.2 Issues and key findings Is the insurer’s settlement fair? No. The repair quotes presented by both parties, including JP’s remediation quote, are incomplete and do not cover all the works recommended by the insurer’s hygienist EH. JP’s final quote should be revised to include all works recommended by EH. The insurer’s offer to have JP complete the repairs or to include a 20% uplift for cash settlement is fair in all the circumstances. The insurer is not obliged to pay for temporary accommodation as the damage to the granny flat does not render the complainant’s home unliveable, pursuant to the terms of the policy. The complaint did not involve technical issues and arguments. The complainant has not established she is entitled for reimbursement of the professional fees incurred. Is the insurer required to pay compensation? No. The complainant not allowing the insurer to conduct further assessment at the property did not assist both parties. Both parties contributed to the overall delays in finalising the claim and complaint. Why is the outcome fair? Parties are bound by the policy terms and conditions. It is fair the insurer should increase the settlement offer covering repairs of the damage caused by the claimed event. 1.3 Determination This determination is substantially in favour of the insurer. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to settle the claim as detailed in section 2.1. The insurer is not required to pay temporary accommodation costs, professional fees or non-financial loss compensation. 2 Reasons for determination 2.1 Is the insurer’s settlement fair? No. The repair quotes presented by both parties, including JP’s remediation quote, are incomplete and do not cover all the works recommended by the insurer’s hygienist EH. JP’s final quote should be revised to include all works recommended by EH. The insurer’s offer to have JP complete the repairs or to include a 20% uplift for cash settlement is fair in all the circumstances. The insurer is not obliged to pay for temporary accommodation as the damage to the granny flat does not render the complainant’s home unliveable, pursuant to the terms of the policy. The complaint did not involve technical issues and arguments. The complainant has not established she is entitled for reimbursement of the professional fees incurred. Parties provided different views on scope of works and repair costs The complainant says: · she refused to allow the insurer’s builder JP to reattend the property because it had attended the property on three occasions previously. JP should have prepared the scope of works based on its initial assessments · JP failed to identify black mould under the bathroom sink. JP’s quote is materially deficient because it: > fails to mention multiple areas of substantial damage > fails to address the contamination and structural impact > fails to meet health and safety requirements · her builders conducted extensive investigations and suggested a full strip out will be required · she rejects the characterisation she was ‘uncooperative’ given the fact she was very lenient with the insurer until she felt that her rights were being compromised. The insurer says: · it initially offered to cash settle the claim because JP refused to repair the property. This is because of the complainant’s interactions with it. JP has since agreed to complete the repairs · JP’s initial assessment was hindered by the need to remove soiled contents and have restoration works completed prior to providing a fully realised scope. The complainant has not allowed JP to reattend the property since November 2024 · EH advised all items which were 600mm above ground level should be replaced. JP’s final scope was prepared on a worst-case-scenario basis. This was that everything in the affected area be replaced up to a height of 1200mm, double that recommended by EH · VI’s area of scope of works was excessive to the dimensions of the room or the previously assessed areas of damage. It is not liable for the cost of improvements · JP’s scope of works and final quote is reasonable, appropriate, complete and actionable · if cash settlement is proposed, it would apply a 20% uplift to accommodate transfer of risk. Insurer should increase the cash settlement for repairs The policy states: When we can repair or rebuild We will have one of our assessors, builders or other suppliers assess your home and provide us with a scope of work to complete the repair or rebuild. If the assessed scope of work and quote is less than your sum insured and we can complete the work, we will repair or rebuild your home to the same standard, specification, or quality… If you request a cash settlement If we are able to repair or rebuild, but we agree to your request to pay you a cash settlement, we will pay you the amount it would have cost us to repair or rebuild, plus any applicable Additional Benefits stated in this PDS… The policy allows the insurer to choose the claim settlement method. While the insurer offered options to progress the claim, the complaint remained unresolved between the parties because the relationship broke down. EH attended the property on 17 September 2024 and provided a report on the works required to remediate and repair the damaged property. I acknowledge the complainant says the insurer’s assessors spent minimum time at the property during their assessments. I am however satisfied the insurer is entitled to follow its process in assessing the true extent of its liability for the damage, provided there are no unreasonable delays. I have reviewed the quotes presented by the complainant’s builders and JP’s final quote. I acknowledge the concerns raised by the insurer about the quotes presented by HE, RM and VI. Builders HE’s and RM’s quotes do not provide a detailed breakdown of the scope of works and costs. RM’s quote includes replacement of the damaged tiled flooring with engineered timber flooring. VI’s quote includes a stone bench top to replace the original laminate bench top. I do not consider VI’s quote to be fair or complete. This is because its quote does not include flooring replacement and includes improvements or items not included in EH’s report. I also do not accept the insurer is obliged to accept cover for upgrades to the granny flat. The builders from both parties have quoted varying amounts for material, labour and the cost of kitchen cabinet replacement. JP’s quote allows for the laminate bench top to be removed and reinstated. However, I accept the laminate benchtop may be damaged during the removal and reinstallation process. An allowance for this variation will be covered under the uplift to the settlement offered by the insurer. Based on EH’s recommendations, I accept the bathroom plumbing and the bathroom vanity require replacement. It is also fair the toilet suite is replaced in the process given the exposure to sewage during the claimed event. The complainant did not agree the kitchen bench sink and bathroom vanity sink could be preserved and reused as the property was exposed to sewage contamination. She also says there were visible signs of a compromised structural integrity. The complainant says the retention of contaminated materials is unsafe and not compliant with basic remediation standards. Given EH did not recommend the replacement of the kitchen sink and the bathroom vanity basin, the insurer is entitled to remove and reinstall these during the repair process. During EH’s assessment, there was no evidence showing a complete strip out was required or the electricals were impacted by the claimed event, as suggested by the complainant’s builders. However, EH did say the demolition process may reveal further unseen damage. While ES referred to plaster board damage, it did not consider the water had reached the timber frames nor the brick lining as indicated by the complainant’s builders. EH said sewage reportedly backed up in the rear garden before spreading around the area. There was a gap in the slab which had likely allowed category 3 water to enter the soil beneath the garage/bathroom. EH recommended that an engineer should assess the concrete slab for possible movement. None of the builders have commented on this point. An allowance for this assessment should be included in JP’s quote. I consider JP’s quote covering the repair area more than what was recommended by EH is generally fair. It is however fair that JP’s quote revised to include the additional items discussed above. Insurer should increase the cash settlement for remediation and restoration While I acknowledge the complainant is a medical doctor, she has not provided an independent hygienist or expert report confirming the extent of repairs and restoration required to reinstate the property. EH said the remediation of the property should extend to the external areas affected by the Category 3 water event. Areas of concrete ground, soil and garden areas as well as the external walls of the home were affected by the event and shall be restored in line with the porosity-based guidelines referred to in EH’s report and in the S500. The insurer should assess its liability for all the works recommended by EH pursuant to the policy terms and conditions. The restoration and remediation quote from the insurer was prepared before EH’s visit and I consider it is inadequate. It does not cover all the works recommended by the EH. Given this, the insurer should obtain a revised quote for remediation and restoration works covering all works recommended by EH including the following: · undertake demolition/removal of affected materials · undertake decontamination, mould remediation and drying · complete post remediation verification (PRV). How the insurer should settle the claim I acknowledge the complainant’s preference to not allow JP or the insurer’s trades to enter the property for further assessment and repairs. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to request an updated actionable quote from JP that includes the items discussed above. Given JP is now willing to complete the repairs, the complainant has the option to allow the insurer to conduct remediation and repairs to the property. This would give the complainant an opportunity to have all the issues discussed above (including damage that is currently unseen) covered by the insurer’s repairs plus the works to be covered by the insurer’s repair guarantee. However, if the complainant chooses the cash settlement option, within 14 days of receiving JP’s revised quote, the insurer is required to cash settle the complainant this quote with a 20% uplift for contingencies and the loss of a lifetime guarantee on repairs. Insurer not obliged to pay temporary accommodation costs The complainant seeks the insurer to pay her for emergency accommodation and other expenses incurred because the family could not stay at the property after the claimed event. She says they could not tolerate the smell from stage 3 contaminated water impacting the damaged areas. While the complainant says the insurer had approved cover for temporary accommodation expenses, the insurer says no such cover was approved. Its representative had only asked her to submit the invoices for the insurer’s consideration. The insurer says the complainant is not entitled to any temporary accommodation as the main house was still liveable after the incident. The PDS says: Temporary accommodation costs Sometimes damage to your home and contents can mean you can't stay living at your insured address. If your home becomes unliveable as a result of an insured event at the insured address and we agree to pay your claim, we will pay for temporary accommodation. The complainant says her parents who were intending to stay at the granny flat arrived and they were required to obtain accommodation for the period. She submitted the following: · 36 nights accommodation in Melbourne CBD $6,282.59 · parking $1,540 · petrol $4,320 (to and from the CBD) · food $10,800 (while in CBD). The complainant says she had lost the functional use of her granny flat, which was a fully functional part of her resident and used for family accommodation for her parents. I acknowledge the complainant’s submissions. The policy provides cover for temporary accommodation if the entire home becomes unliveable. It does not apply where a part of the home is unliveable, unless usual activities like cooking and sanitation (ie, bathing and toileting) cannot be performed. The house remained habitable. There was no actual damage to the main house itself and the circumstances of the sewage spill, while inconvenient, did not prevent the family from living in the house. The hygienist’s report makes no reference to any health risk to people living in the main house. EH also did not deem the main house was unliveable. The complainant has not provided any expert information supporting her contention that the house was not habitable as a result of the odours from the granny flat. The insurer is therefore not required to provide cover for temporary accommodation or for other general living expenses incurred while the family were staying away from their home. Insurer not obliged to pay professional fees $5,000 The complainant also seeks the insurer to pay $5,000 for the legal fees incurred. I accept the insurer’s submission the complaint did not require technical assessment of the issues in dispute. Given this and noting AFCA is a free service and accessible without the need for representation, I am not satisfied the insurer is obliged to contribute towards the legal fees incurred. 2.2 Is the insurer required to pay compensation? No. The complainant not allowing the insurer to conduct further assessment at the property did not assist both parties. Both parties contributed to the overall delays in finalising the claim and complaint. AFCA may award compensation in certain circumstances Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss where the insurer’s actions have caused an unusual amount of: · physical inconvenience · time taken to resolve the situation · interference with the complainant’s expectation of enjoyment or peace of mind. We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. When considering non-financial loss compensation, AFCA looks at what is reasonable and fair in all the circumstances. In considering what is fair in all the circumstances, it is appropriate to factor the overall claims experience, rather than focusing on specific individual events. Insurer should pay non-financial loss compensation 20 months have passed since the claimed event, and the damaged granny flat remains unrepaired. The delay is largely the result of a breakdown in the relationship between the complainant and the insurer and the complainant’s refusal to grant access to her property. The insurer’s trades initially attended the property to assess the damage days after the claim was lodged. Then there was a period of delay while the insurer waited for the complainant to return a signed authority so that restoration could proceed. The complainant was reluctant to provide an authority without being given full details of proposed repairs. The insurer maintained that this was not possible until the initial restoration was completed and a further building assessment was done. The claim notes show the insurer attempted to explain the claims process on how the extent of damage would be assessed. The complainant did not accept its proposal and requested the insurer to offer a settlement based on its initial assessments. During this period, JP reported to the insurer that the complainant’s conduct towards its trades was inappropriate, and they were not prepared to return to the property for repairs. JP has since agreed to complete the works. The complainant is however not willing to allow the insurer’s trades to return to the property for repairs. The evidence shows there was a lack of understanding between the parties such that they could not work together. It is unfortunate the claim unfolded in this way. I accept that the insurer’s initial estimate was inadequate. However, I accept its request to reattend the site following removal of the damaged contents and completion of restoration works was reasonable. It was not reasonable for the complainant to have denied the insurer access. Even if the complainant was unwilling to have the insurer’s trades complete the work, it would have been reasonable to allow the insurer to form a more accurate view of the cost of repairs to offer an appropriate cash settlement. The complainant refusing to allow JP to conduct further assessment at the property has not assisted both parties. I accept JP’s initial quote was inadequate and incomplete. Given the ongoing dispute, the insurer could have requested JP to provide the comprehensive repair quote based on EH’s recommendation, at a time earlier than September 2025. While I acknowledge the insurer’s claim handling caused emotional distress and inconvenience to the complainant, I am satisfied both parties have contributed to the overall claim delays. They could have worked together to resolve the claim and complaint at an earlier time. Given the above, I am not satisfied the insurer is obliged to pay non-financial loss compensation to the complainant. 2.3 Why is the outcome fair? Parties are bound by the policy terms and conditions. It is fair the insurer should increase the settlement offer covering repairs of the damage caused by the claimed event. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.