Home / Westpac / Determination 12-25-234981

Determination 12-25-234981

Complaint about handling of a construction loan: non-reimbursement of builder deposit, progress payments, delays, loan reduction and repayment history reporting

FirmWestpac
Decided2025-12-02
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Borrowers with a construction loan complained about the bank's failure to reimburse a deposit, failure to detect defective work, delays, a loan reduction and RHI reporting. AFCA found in favour of the bank, requiring only that it explain the effects of reimbursing the deposit.

The loan contract placed responsibility for verifying work quality on the borrowers, the bank was entitled to revalue and reduce the loan, and losses were primarily caused by the builders, not the bank.

Issues

Subjects and remedies

financial hardshiphome or building damageno remedy

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-234981 | Financial firm | RAMS Financial Group Pty Ltd Case number: 12-25-234981 27 November 2025 1 Determination overview 1.1 Complaint On 12 May 2022, the complainant and his wife (the borrowers) entered into a $980,000 build contract with builders, Company J, for the construction of a home in W Town, Victoria (Property W). On 14 June 2022, the borrowers were unconditionally approved by the financial firm (the bank) for a $1.2m construction loan (the loan) which would also, in part, distribute $226,818.98 to refinance a pre-existing loan obtained to purchase the land. The borrowers accepted the loan offer on 16 June 2022. The complainant says: · he was required to contribute $6,818.98 and pay a $49,000 deposit to Company J, but this deposit was not reimbursed by the bank · the bank disbursed four progress payments to Company J, totalling $416,500, but did not identify or address substandard work with significant defects on Property W · after he terminated the Company J build contract and, in May 2024, appointed Company R to complete the project, there were significant delays and mismanagement of the loan by the bank, namely: > the assigned construction officer repeatedly miscalculated the loan amount, causing nearly two months of delay > the loan amount was reduced by $160,000 without clear explanation and > the valuation process lacked transparency. · to proceed with construction, he made an advance payment of $135,000 to Company R’s partner company, Company V, but due to delays in loan disbursements from the bank, Company R’s progress was hindered · he had to personally fund critical work to avoid expiry of the building permit, assume responsibility for project management and personally fund additional works to maintain construction momentum. The bank says the complainant has been provided with a number of progress payments as anticipated by the build and loan contracts but has not permitted required valuations of Property W to be conducted in order to allow the release of further progress payments to the builder. 1.2 Issues and key findings Did the bank improperly fail to reimburse the complainant? Yes. The bank had no initial obligation to reimburse the deposit, which was correctly treated as a customer contribution under the loan terms, and the $6,818.98 was paid by the complainant to settle a shortfall in the pre-existing loan which was being refinanced. However, the bank’s subsequent treatment of the deposit as a contribution was improper. Was the bank required to certify the quality of the works? No. Under the applicable contractual arrangements, the borrowers were required to satisfy themselves of the completion and compliance of the works prior to authorising relevant progress payments. Did the bank cause unnecessary delays? No. While the bank’s documentation error in the 14 July 2024 Authority to Commence caused confusion for three days, this was corrected and did not result in any undue delay. I am satisfied the bank otherwise engaged with the borrowers in a timely manner. Did the bank inappropriately reduce the loan amount? No. The bank was entitled to reassess and reduce the loan amount following the change in builder, with the adjustment based on an updated valuation and carried out in accordance with its credit policy and lending obligations. Did the bank report incorrect repayment history information (RHI)? No. The bank accurately reported missed repayments in line with its obligations, as no formal hardship arrangement was in place. Why is the outcome fair? The borrowers’ circumstances, having had two building companies default on their contractual obligations, are unfortunate and I sympathise with their position. However, I am satisfied, with the exception of some minor errors, the primary cause of the complainant’s loss was Company J and Company R, not the bank. In these circumstances, it would not be fair for the bank to compensate the complainant for losses caused by others. 1.3 Determination The determination is in favour of the bank. However, within 7 days of the date the bank is advised the complainant has accepted this determination, the bank must clearly explain to the borrowers the impacts of reimbursement of the deposit and any overpayment of a shortfall on the borrowers’ equity position and ongoing obligations under the loan contract. If the borrowers still wish to seek a reimbursement, they should make this request in writing, and the bank should process this request in line with its contractual obligations. 2 Reasons for determination 2.1 Did the bank improperly fail to reimburse the borrowers? Yes. The bank had no initial obligation to reimburse the deposit, which was correctly treated as a customer contribution under the loan terms, and the $6,818.98 was paid by the complainant to settle a shortfall in the pre-existing loan which was being refinanced. However, the bank’s subsequent treatment of the deposit as a contribution was improper. The borrowers obtained less financing than they required As a preliminary matter, it should be clearly noted the build contract, and the loan contract, establish two different sets of obligations for the borrowers. Further, I understand the borrowers already had a contractual obligation to repay another financial institution for the pre-existing loan relating to the purchase of the land at Property W. Firstly therefore, as at 16 June 2022 when the borrowers signed the loan with the bank, they: · owed $226,818.98 to a different financial institution · were contractually obliged to finance the $980,000 build contract with Company J and · had just entered into a loan contract for $1.2 million with the bank. However, the borrowers’ liabilities totalled $1,206,818.98, not $1.2m, which meant there was a known shortfall the complainant was required to cover. On 8 July 2022, $226,818.98 was settled from the new loan to cover the outstanding debt amount of $225,710.18 on the pre-existing loan, as well as relevant fees and charges. This is where the shortfall of $6,818.98 arose. The borrowers were required to finance this amount directly as it exceeded the amount of their borrowing. The complainant has provided documentation showing he had discussions with one of the bank’s representatives, a Mr NM, on 7-8 July 2022 which indicated the complainant paid the shortfall directly to facilitate settlement of the pre-existing loan in accordance with the borrowers’ obligations. I am therefore satisfied the complainant was required to pay the shortfall and is not entitled to any reimbursement of this amount from the bank. The deposit was to be reimbursed subject to certain conditions Secondly, the borrowers paid the $49,000 deposit from their own funds on 27 June 2022. The loan contract says: [The bank] will release a 5% deposit on the Builder’s Contract amount before the Authority to Commence is issued on the condition that the deposit is referred to in the progress payment schedule of the builder’s contract and the builder’s contract is signed. The bank first provided an Authority to Commence on 10 October 2022 after all the required documentation was provided by the complainant on 28 September 2022 via email. The bank says this was the first time it was made aware of the deposit having been paid, but as will be shown below, it was certainly aware prior to the Authority to Commence being issued. I am satisfied the deposit was referred to in the progress payment schedule on page 41 of the build contract and was signed on 12 May 2022. However, the bank says it could not locate any formal reimbursement request from 2022, and it therefore classified the deposit as a customer contribution, not a pending reimbursement. In its Authority to Commence letter, the bank relevantly said: A breakdown of the funds available to be drawn down from your loan account, along with any contribution that you must make towards the construction are summarised below. Please note that only $973,181.02 will be available to be released through progress payments for the first stage and any customer contributions will need to be paid before any loan funds will be released. | Building Contract Fixed Price Amount - House | $980,000.00 | Total Fixed Price Contract Amounts | $980,000.00 | less Amount Available for Construction | $973,181.02 | Total Customers Contribution | $6,818.98 | less Total Amount Paid | $49,000.00 | Your contribution left to Pay | $0.00 This breakdown shows: · part of the construction funds had been used to meet the shortfall in the pre-existing loan which was refinanced and · the bank was aware the borrowers had already contributed to the construction through paying the deposit. As an aside, given the complainant had already paid the shortfall on 7 July 2022, there was no basis for the contribution to have been deducted from the available amount for construction. This appears to be an error by the bank. However returning to the issue of the reimbursement of the deposit, there are no contemporaneous documents to show the borrowers sought to have the deposit reimbursed in 2022. While I acknowledge the complainant says the borrowers experienced significant financial hardship resulting from the non-reimbursement, arising from the need to draw funds from their business and disruption to day-to-day operations, it is reasonable to expect there would be some email correspondence or written record of the complainants seeking to have this deposit reimbursed from the loan funds at the time. Further, in the absence of a request for reimbursement, I am satisfied the bank’s classification of the payment as equity in the project was consistent with industry practice. However, I am satisfied, over the course of the complaint, the bank has been on notice of the borrowers’ position regarding the deposit and their preference it be reimbursed. As there is nothing in the loan contract which says reimbursement needs to occur within a particular timeframe, this option should be explored now. I also note, in its submission to AFCA 1 July 2025, the bank relevantly said: Once the Authority to Commence is issued we can review for reimbursements, if the customer has paid funds to the builder as part of the required shortfall we cannot reimburse them the funds. However, if they have paid more than the required shortfall amount then they are entitled to a reimbursement. As part of this process, the impacts on the borrowers’ equity position and ongoing obligations under the loan contract should be clearly explained to the borrowers to determine whether they still wish to seek the reimbursement. It may also be advisable for the borrowers to seek independent accounting advice about their use of funds from their business to pay a personal liability. 2.2 Was the bank required to certify the quality of the works? No. Under the applicable contractual arrangements, the borrowers were required to satisfy themselves of the completion and compliance of the works prior to authorising relevant progress payments. The loan contract sets out the bank’s obligations The relationship between the bank and the borrowers is contractual. As a starting proposition, the loan contract, incorporating the bank’s standard terms and conditions (the terms), sets out the rights and responsibilities in respect of the other party. The bank was not required to certify quality of works Sections 6.4-6.5 of the terms relevantly says: 6.4 You must make any progress payment claim by completing a Progress Payment Request substantially in the form of the documents we provide to you and attaching the relevant builder’s invoice. 6.5 You must ensure that the building is complete to the stage shown in each Progress Payment Request before requesting the progress payment for that stage. and sections 6.17-6.20 which relevantly say: Standard of work 6.17 You must ensure that all building work on the mortgaged property is carried out as we have approved and in accordance with all laws and requirements of the relevant authorities. 6.18 If we monitor the work, we do so only for our own purposes and, even if we make a progress payment, it does not mean that the building work is necessarily satisfactory. You are responsible for ensuring that all plans are followed and that all materials and workmanship are satisfactory. 6.19 You must obtain our consent before you change or vary in any way any plans and specifications we have approved. You must pay the cost of any such change or variation. You must satisfy us that you can meet the cost at the time you seek our consent to the change or variation. 6.20 In the event of any dispute between you and the builder, we may, but are not obliged to, make all reasonable efforts to assist you to resolve the dispute. You agree that we are not liable in connection with any assistance or acts performed on your behalf as your representative. Despite any acts by us to the contrary, we are not, and do not become, a party to any oral or written contract between you and the builder. As a result, I am satisfied the quality of the works should have been verified by the borrowers prior to authorising the relevant progress payment be released to Company J. It was not the bank’s obligation to do so. 2.3 Did the bank cause unnecessary delays? No. While the bank’s documentation error in the 14 July 2024 Authority to Commence caused confusion for three days, this was corrected and did not result in any undue delay. I am satisfied the bank otherwise engaged with the borrowers in a timely manner. The complainant changed builder in 2024 A chronology of key events is set out in section 3.2 of this determination. In summary, following issues with the construction in 2024, the complainant made the decision to terminate the Company J contract and entered into a new build contract with Company R on 8 April 2024 (the Company R build contract). He informed the bank on 7 May 2024, and on 22 May 2024, the complainant provided the bank with the new Company R building contract, insurance certificates, and payment schedule. Unfortunately, due to formatting issues with the electronic files, the bank was unable to access the documents. It advised the complainant of this promptly. The complainant subsequently resent the documents in PDF format, and these were successfully received on 30 May 2024. Upon receipt of the documents, the bank commenced a reassessment process, which included commissioning a new “As If Completed” valuation. This was in accordance with the loan terms which, at sections 6.11 and 6.14-6.15, relevantly says: 6.11 We will arrange any building inspection by our valuer or other expert. We will pay the cost of any such inspection for the final progress payment to your builder, but you must pay the cost of any inspection we require for any other progress payment. […] 6.14 You must use a licensed builder. We only lend any amount that is being used for making progress payments to your builder if: (a) you have complied with clause 1; and (b) we have received a copy of: (i) all plans and specifications for your proposed building work, approved by any relevant authority; (ii) a copy of a fixed price building contract signed by all borrowers and the licensed home builder (it must contain their licence number(s) and a schedule of required payments); (iii) your home builder’s all risk insurance policy, covering the property until the construction is finished, which notes our interest as mortgagee on it; (iv) your Home Owner’s Warranty Insurance (if applicable); and (v) any other document or information we reasonably require, which are satisfactory to us. 6.15 When all of the conditions in clauses 6.13 (if applicable) and 6.14 have been met, we will issue you with an Authority to Commence Construction, subject to clause 3. While the complainant says the new $540,000 contract was merely for completion of the original project to the same specification and using the same materials, in circumstances where: · there had been a change of builder and a termination of the original build contract · four progress payments totalling $416,500 had been paid to Company J in accordance with its progress payments schedule as follows: > Base Stage: $98,000 > Ground Floor Frame Stage: $73,500 > First Floor Frame Stage: $73,500 > Ground Floor Lockup Stage: $171,500 · the new contract was to complete the construction for $540,000 – an overall reduction of $23,000 in the build cost even though two years had passed from the date of the original build contract, and the cost of materials and labour had likely increased I am satisfied it was reasonable for the bank to review the construction project. To do so, I am also satisfied a revised valuation was required to assess the updated projected value of the property and to ensure the loan-to-value ratio remained within acceptable parameters under the bank’s credit policy. The bank required amendments to, and explanations about, the Company R build contract Under the Company R build contract, the initial payment schedule was for four equal amounts representing 25% of the total contract price, as follows: · Deposit: $135,000 · Fixing Stage: $135,000 · Lockup Stage: $135,000 · Final Stage: $135,000 However, this equal payment structure: · was in breach of clause 11.7 of the Company R build contract as the deposit price was more than 5% of the Original Contract Price · did not reflect standard construction staging and · was inconsistent with the actual progress of works. Given this, as a condition of its revised credit assessment, the bank was entitled to ensure disbursements would align with the value of work completed at each stage and therefore require amendments be made to the progress payment schedule. The revised progress payment schedule was: · Lock up Stage: $108,000 · Fixing Stage 1: $135,000 · Fixing Stage 2: $135,000 · Final Stage: $162,000 I am satisfied the bank’s approach was consistent with good industry practice. Secondly, as part of its reassessment process, the bank sought clarification about a payment of $135,000 made to Company V, a related entity to Company R, for the Lockup Stage – First Floor. The complainant says the payment was made to maintain construction momentum while awaiting loan disbursements and, while the invoice was issued by Company V, the attached Progress Payment Request Form was completed on 6 May 2024 instructing the payment on behalf of Company R. The bank was entitled to confirm this arrangement was consistent with the revised building contract and that future disbursements would be directed to the appropriate party, Company R. The bank issued an incorrect Authority to Commence for the Company R build contract After resolving the above issues, on 14 July 2024, the bank issued a second Authority to Commence letter which relevantly said: A breakdown of the funds available to be drawn down from your loan account, along with any contribution that you must make towards the construction are summarised below. Please note that only $396,681.02 will be available to be released through progress payments for the first stage and any customer contributions will need to be paid before any loan funds will be released. | Building Contract Fixed Price Amount – House | $540,000.00 | Total Fixed Price Contract Amounts | $1,005,500.00 | less Amount Available for Construction | $396,681.02 | Total Customers Contribution | $608,818.98 | less Total Amount Paid | $135,000.00 | Your contribution left to Pay | $473,818.98 On 17 July 2024, the bank emailed the complainant and relevantly said: We just had a message from our contact centre team asking us to revise this based on the funds already paid to your builder, we do apologise as this appears to be an oversight on our part to not allocate these funds as already being paid. Please disregard the documents previously send and find attached documents updated to reflect the payments you’ve already made. They also asked us to clarify why the stage amounts had changed and it was because we had to updated the progress payments schedule as per your builders revision (also attached.) Based on this you’ve already paid the Lockup Stage and partially paid Fixing Stage 1. When you make your next payment authorisation just send us a receipt for the shortfall of $8,318.98. This email attached a second Authority to Commence, dated 17 July 2024, which relevantly said: A breakdown of the funds available to be drawn down from your loan account, along with any contribution that you must make towards the construction are summarised below. Please note that only $396,681.02 will be available to be released through progress payments for the first stage and any customer contributions will need to be paid before any loan funds will be released. | Building Contract Fixed Price Amount – House | $540,000.00 | Total Fixed Price Contract Amounts | $1,005,500.00 | less Amount Available for Construction | $813,181.02 | Total Customers Contribution | $608,818.98 | less Total Amount Paid | $0.00 | Your contribution left to Pay | $608,818.98 The complainant says the 14 July 2024 letter included incorrect amounts, which led to confusion and concern from Company R about the borrowers’ financial capacity to complete the project. Although the bank accepted it had made an error and the documentation was rectified, I accept the error may have affected the complainant’s credibility with Company R and contributed to delays in construction. The complainant says Company R hesitated to proceed with work due to uncertainty about the available loan funds and he experienced reputational strain and logistical setbacks during this period. The bank did not cause undue delays However, the period between the error and its correction was only three days. I am not satisfied this would have caused the reputational strain and credibility damage the complainant asserts. Based on the timeline at section 3.2 of this determination, the reassessment process, including valuations, documentation review, and payment schedule adjustments, was conducted within timeframes consistent with the bank’s internal credit policy. The bank was responsive at each stage, and I am satisfied it is more likely than not the delays were caused by the builder’s lack of completion of the required works at each stage than the bank’s conduct. As a result, I am not satisfied the bank caused unnecessary delay in progressing the payments due under the loan. 2.4 Did the bank improperly reduce the loan amount? No. The bank was entitled to reassess and reduce the loan amount following the change in builder, with the adjustment based on an updated valuation and carried out in accordance with its credit policy and lending obligations. The bank was entitled to obtain revised valuations As set out in the chronology, following the change in builder, the bank commissioned a new “As If Completed” valuation on 5 June 2024. As noted above, section 6.11 of the loan terms entitled the bank to obtain updated valuations given the change to the build contract. While the complainant had previously disputed the valuations obtained and requested a different valuer be used, the bank was under no obligation to agree to this request. It appropriately advised the complainant he could obtain his own independent valuation of the property if he wished to dispute the bank’s decision. I am satisfied the bank was entitled to rely on independent valuations unless there is evidence of procedural irregularity or bias. No such evidence has been provided. In addition, the complainant raised concerns regarding a 27 March 2025 “As Is” valuation (as opposed to an “As If Completed”. However, this valuation was used for internal credit assessment purposes and did not directly impact the loan amount. As a result, I am not satisfied the complainant has been disadvantaged by the 27 March 2025 valuation. The bank was entitled to adjust the loan following the revised valuation The 5 June 2024 valuation re-assessed the property at $1,300,000, a reduction from the original valuation of $1,500,000. This was due to a reduction in both the land value (due to changes in the local market between 2022 and 2024) and in the capital developed value. As a result of the $200,000 value reduction, the bank adjusted the loan amount from $1.2m to $1.04m to maintain a loan-to-value ratio which was acceptable for its credit policy. The updated valuation reflected prevailing market conditions and construction risk, and the bank adjusted the loan amount accordingly. The complainant was advised of the valuation outcome, the loan variation and the resulting $143,319 shortfall. The complainant confirmed the borrowers’ capacity to meet the difference and successfully took steps to do so. In the circumstances, I am satisfied the bank acted appropriately in respect of the valuations and variation to the loan. 2.5 Did the bank report incorrect repayment history information (RHI)? No. The bank accurately reported missed repayments in line with its obligations, as no formal hardship arrangement was in place. AFCA can consider whether RHI is accurate and up to date AFCA can consider whether a complainant’s credit file contains information that is accurate and up to date. If the financial firm has incorrectly reported RHI on a complainant’s credit file, AFCA can compel the financial firm to correct this information. AFCA considers that a payment is overdue if, during the month to which the RHI relates, there was at least one overdue payment which was 15 or more days overdue. The financial firm is not prohibited from reporting RHI while AFCA considers a complaint. The Privacy Code sets out RHI reporting requirements RHI is outlined in the Privacy (Credit Reporting) Code 2014 (Privacy Code). Under the Privacy Code, when reporting RHI the financial firm must: · ensure the grace period for an overdue payment is at least 14 days beginning from the date the financial firm’s system first classified the payment as in arrears · not disclose RHI more frequently than once each month · for each month only disclose whether the payment was either not overdue or that there was an amount overdue · disclose RHI as a code representing the age of the oldest outstanding payment and · ensure that while an account is subject to a financial hardship arrangement for each month disclose financial hardship information (FHI) as the relevant FHI code (code A or code V) representing the hardship arrangement and an RHI code (code 0 or code 1) representing whether the arrangement was met or not met. The complainant requested suspension of direct debit payments On 22 April 2025, the complainant emailed the bank and relevantly said: I have not received a fair and detailed explanation regarding the previous valuation, nor the reason for undervaluing the building. I would appreciate a clear justification for this assessment. Additionally, could you please clarify how the bank expects the client to cover the significant shortfall in funding as the project progresses, given the approved loan limit? I request that this matter be escalated to your superiors. In the meantime, please arrange to put my loan repayments on hold until the issue is resolved. I am satisfied the complainant’s email of 22 April 2025 did not convey the borrowers were, or would be unable, to meet their obligations. The instruction to put loan repayments on hold was not grounded (at that time) in an inability to pay, but a refusal to do so due to the ongoing dispute. In these circumstances, I am satisfied the complainant had not provided the bank with a hardship notice which complied with section 72(1) of the National Credit Code. Repayment obligations remained despite suspension of direct debit The bank responded to the complainant’s email on 28 April 2025 and relevantly said: As per your request I have requested your loan repayments be put on hold, however if payments are missed and your loan accounts are behind, this may have impacts on your Comprehensive Credit Reporting. In the absence of any hardship agreement, the borrowers remained contractually obligated to continue making repayments, notwithstanding the dispute. Further, the bank advised the complainant of the potential impact of putting the loan repayments on hold. The bank reported adverse RHI When the borrowers missed their repayment obligations in May 2025, the bank reported the missed payments to credit reporting bodies. This reporting was consistent with the bank’s obligations under the Privacy Act and the Credit Reporting Code. The complainant says the bank mischaracterised their request and did not adequately explain the consequences of suspending direct debit. I am not satisfied this is the case but am satisfied the reporting of missed payments was factually accurate and aligned with regulatory requirements. The impact on the borrowers’ credit file does not, in this context, establish a breach of duty by the bank. The bank was entitled to report missed repayments in the absence of a hardship arrangement. The reporting was accurate, procedurally appropriate, and consistent with its legal obligations. 2.6 Why is the outcome fair? The borrowers’ circumstances, having had two building companies default on their contractual obligations, are unfortunate and I sympathise with their position. However, I am satisfied, with the exception of some minor errors, the primary cause of the complainant’s loss was Company J and Company R, not the bank. In these circumstances, it would not be fair for the bank to compensate the complainant for losses caused by others. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Chronology Timeline of key events | Date | Event | 12 May 2022 | Company J build contract signed | 2 Jun 2022 | First “As If Completed” valuation conducted: $1.5m | 16 Jun 2022 | Loan contract signed by borrowers | 27 Jun 2022 | Deposit paid to Company J: $49,000 | 8 Jul 2022 | Settlement of pre-existing loan | 16 Sept 2022 | Building Permit issued | 28 Sept 2022 | Complainant notified the bank the deposit had been paid | 10 Oct 2022 | Initial Authority to Commence (re Company J) issued by bank | 8 Apr 2024 | Company R build contract signed | 5 May 2024 | Company V issues Invoice for $135,000 on behalf of Company R (due same day) | 6 May 2024 | Borrowers sign Progress Payment Request Form for 5 May 2024 invoice | 7 May 2024 | Complainant notifies bank of termination of Company J contract and appointment of Company R | 22 May 2024 | Complainant provided documentation relevant to Company R build contract | 5 Jun 2024 | Second “As If Completed” valuation conducted: $1.3m | 26 Jun 2024 | Bank requests reduction in loan limit to $1.04m and for borrowers to meet $143,319 shortfall | 2 Jul 2024 | Complainant confirmed shortfall could be met and $135,000 had already been paid | 3 Jul 2024 | Bank required alterations to Company R progress payment schedule | 14 Jul 2024 | Second (Incorrect) Authority to Commence (re Company R) issued by bank | 17 Jul 2024 | Third (Correct) Authority to Commence (re Company R) issued by bank | 22 Jul 2024 | Complainant provided receipt for $8,318.98 shortfall payment | 27 Jul 2024 | Progress inspection conducted by bank | 5 Aug 2024 | Bank confirmed valuer’s understanding of fixing stages 1 and 2 | 15 Oct 2024 | Complainant confirmed fixing stages 1 and 2 completed | 30 Oct 2024 | Bank inspection confirmed fixing stages incomplete and bank held off on fixing stage progress payments due to incomplete works. Bank advised of outstanding items and of steps to properly reflect borrowers’ contribution of $35,318.98 and outstanding invoice amount of $99,681.02. | 11 Nov 2024 | First Company R Progress Payment: $99,681.02 | 23 Dec 2024 | Second Company R Progress Payment: $135,000

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.