Home / Search / Determination 12-25-230766

Determination 12-25-230766

Alleged unreasonable delay in processing a partial discharge of security, causing late settlement penalties

FirmMortgageport Management Pty Ltd
Decided2025-10-13
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Borrowers sold a security property and complained the mortgage manager delayed the partial discharge, causing late settlement penalties. AFCA found the mortgage manager processed the request within required timeframes and decided in its favour.

The mortgage manager processed the discharge within the 20 business day timeframe, the borrowers notified it late, and the bank's review was outside its control, so compensation would not be fair.

Issues

Subjects and remedies

no remedy

Related

Find similar determinations

Text of the determination

Determination | Case number | 12-25-230766 | Financial firm | Mortgageport Management Pty Ltd Case number: 12-25-230766 13 October 2025 1 Determination overview 1.1 Complaint In 2024, the complainant and a co-borrower, Mr W, (the borrowers) held an investment home loan (the loan) managed by the financial firm (the mortgage manager) and financed by a second financial firm (the bank). The bank is not a party to this complaint. The loan was secured by two properties located at R Drive (Property R) and K Street (Property K). On 25 May 2024, the borrowers sold Property K. Under the contract of sale, settlement was due 35 days from the contract date. The borrowers sought a partial discharge of security to release Property K from the loan and leave Property R as the sole remaining security property. The complainant says: · the mortgage manager: > was aware of the scheduled settlement date in June 2024 > unreasonably delayed settlement until 23 July 2024 > failed to pre-emptively gather relevant information required by the bank · the borrowers and their solicitor received very little communication from the mortgage manager during the settlement period and · the borrowers suffered loss as a result of penalties applied under the Contract of Sale arising from the late settlement. The mortgage manager says the borrowers delayed in informing them of the sale and did not provide required documentation until July 2024. It also says the time taken was predominantly caused by the bank, but nevertheless the instructions were processed within a reasonable timeframe. 1.2 Issues and key findings Did the mortgage manager cause an unreasonable delay to the settlement? No. The mortgage manager processed the request within the required timeframe and acted appropriately in following up with the bank to seek updates and request an urgent escalation to proceed to settlement. Why is the outcome fair? The mortgage manager processed the discharge within the required timeframes and took all reasonable actions to try to have the bank process the request quickly. However, it was never reasonable to expect either 10 calendar day (from 23 June 2024) or same day (on 1 July 2024) processing of the partial discharge request. In these circumstances, it would not be fair to require the mortgage manager to pay compensation. 1.3 Determination This determination is favour of the mortgage manager. It is not required to compensate the complainant or take any further steps in relation to this determination. 2 Reasons for determination 2.1 Did the mortgage manager cause an unreasonable delay to the settlement? No. The mortgage manager processed the request within the required timeframe and acted appropriately in following up with the bank to seek updates and request an urgent escalation to proceed to settlement. The claim centres upon the timing of events As with any complaint arising from claims of unreasonable delay causing loss, the timeline of events is crucial in this complaint. Accordingly, a chronology of key events is set out in section 3.2 of this determination. In summary however, the borrowers sold Property K on 25 May 2024 and as the contracted settlement date fell on a Saturday, it was due to take place the following business day, i.e. on Monday 1 July 2024. It is not disputed the borrowers notified the mortgage manager of the sale on 21 June 2024 and anticipated they would be able to obtain a partial discharge authority and a variation to the loan to release Property K as at settlement on 1 July 2024. The issue in dispute is whether the mortgage manager’s conduct caused a three-week delay to settlement between 1 July 2024 and the eventual settlement on 23 July 2024. The complainant says there were issues communicating In support of her complaint, the complainant relevantly provided a number of emails which she says show the mortgage manager was difficult to communicate with and caused delays. These are: · emails dated Friday 21 June 2024: > from Mr W to the mortgage manager advising of the Property K sale > from the mortgage manager to Mr W purporting to attach the partial discharge authority and variation to loan contract form > from Mr W to the mortgage manager acknowledging receipt of the email · an email dated Monday 24 June 2024 from Mr W, providing the contract of sale and advising the forms had not been attached to the 21 June 2024 email, along with a response re-attaching the forms 10 minutes later · an email dated Friday 28 June 2024 (at 7:45am) from Mr W to the mortgage manager containing a photograph of two pages of the Contract of Sale · an email dated Friday 28 June 2024 (at 4pm) from the conveyancer asking for the complainant to follow up with the broker as the bank’s solicitors did not hold instructions for settlement the following Monday · an email from Mr W to the mortgage manager on Saturday 29 June 2024 forwarding the conveyancer’s email and asking for advice about what was happening On 18 July 2024, the complainant emailed the mortgage manager and relevantly said: We had sold this property in May with long settlement and you didn’t have the paper work prepared by 1st July [Mr W] even sending email on the 2nd July when it wasn’t settled on the 1st specifically asking if there was any more paperwork we needed to provide 15 days later you sent an email asking for more paperwork to be done Now we have had no response and this is to be settled on the 23rd July The bank requested further information from the mortgage manager It was not until 28 June 2024 that the mortgage manager received the variation to the loan contract form and 1 July 2024 that it received the completed discharge authority, albeit after close of business. On 4 July 2024, the mortgage manager forwarded the completed forms to the bank. The mortgage manager requested the request be escalated as the settlement was overdue. While the bank’s conduct does not form part of this complaint, it appears the bank did not advise the mortgage manager of its need for further information until 9 July 2024. There was a further request on 16 July 2024. The borrowers provided the relevant information on 16 July 2024 (after close of business) and the mortgage manager responded to the bank on 18 July 2024. On 19 July 2024, the bank requested more information and the mortgage manager responded on the same day. The bank eventually booked settlement for 23 July 2024, and settlement occurred on that day. The mortgage manager commenced the request within reasonable timeframes After being advised of the sale of the property, the mortgage manager responded on the same day, purporting to attach the relevant documents for the borrowers to sign. While it does not dispute any of the emails provided by the complainant, it has provided some additional correspondence, including an email from Mr W to his conveyancer on Tuesday 2 July 2024 which relevantly said: I did respond yesterday asking to extend till Friday but it would seem that I sent it to [Ms J] by mistake. I have spoken to [mortgage manager] today and we have sorted the paperwork. Hopefully that is all that is required. I am happy to move settlement till Friday if that is required. The mortgage manager also provided emails between various parties, including the borrowers, as follows: · an email dated 4 July 2024 advising all documentation had been submitted to the bank, but its usual Service Level Agreement (SLA) is 15 business days, although an escalation had been requested · an email dated 5 July 2024 advising the mortgage manager was unable to advise an exact date for settlement as the loan was under review by the bank and settlement was very unlikely to be achieved that day · an email dated 5 July 2024 from Mr W to the mortgage manager relevantly saying: I understand you are at the mercy of the bank but if this is not settled by Monday […] it will cost me $400 for legal + a further $180-$200 (approximately) per day. · emails dated 8 July 2024 advising Mr W it was unlikely the mortgage manager would have daily updates on the bank’s progress and a subsequent exchange about when the bank or mortgage manager would have updates for the borrowers. On the available information, I am satisfied: · the complainants sold Property K on 25 May 2024 with a 35-day settlement period · the mortgage manager only knew about the sale of Property K from 21 June 2024 onwards – 27 days into the 35-day timeframe · the discharge forms notified the borrowers a discharge request could take up to 20 business days to process · on 1 July 2024, the borrowers signed the discharge request form and acknowledged they had understood the timeframes required by the mortgage manager to process the discharge request and · the mortgage manager did not receive the completed forms from the borrowers until after close of business on 1 July 2024, the initial date of settlement. The complainant’s delay in notifying the mortgage manager of the sale contributed to the delay in settlement. This is because the mortgage manager could not have known the property had sold until it was informed by the borrowers of the sale. I am satisfied the complainant was aware of the timeframes required by the mortgage manager to process the partial discharge request from at least 24 June 2024 at the latest. When the borrowers completed the discharge form on 1 July 2024, they should have reasonably been aware that day’s settlement date could not be met. As the mortgage manager could not have begun the process to arrange discharge until such time as it received the complainant’s notification, I am satisfied there was no delay to the start of the partial discharge process which was caused by the mortgage manager. The mortgage manager conducted the process reasonably The complainant has asked why the mortgage manager did not pre-emptively request the information subsequently requested by the bank and expedited the process in this manner. The mortgage manager says: · the Variation to Loan Contract form contained the requirements for documents needed · it only received a signature page of the Variation to Loan Contract form from the borrowers on 28 June 2024 and · it subsequently submitted the available information, hoping the bank would not require a full assessment. The Variation to Loan Contract form says a minimum requirement of income verification would be needed. It lists documents required and states ‘all documents and information must be sent with the application.’ I am satisfied the borrowers were on adequate notice of the documents that would be required by the bank to process the request. The mortgage manager acted appropriately in submitting the completed forms on 4 July 2024, albeit without the supporting documentation. Any further time given to the borrowers to provide the supporting documentation would have inevitably caused additional delays to the settlement date. The bank advised it commenced its assessment of the request on 16 July 2024. While the mortgage manager had tried to expedite the bank’s consideration, I am satisfied this was out of the mortgage manager’s control. The bank subsequently requested the mortgage manager obtain additional information from the borrowers which went beyond the minimum income verification requirement, including: · Complete employment details · Details of additional lending held by the complainant · Monthly living expenses · Clarification of adults in the household · Current credit report · Recent personal loan statements and · Confirmation of the property value. The mortgage manager forwarded the information request to the borrowers on the same day and, on 18 July 2024, requested a waiver of the income and valuation requirements noting the settlement was overdue. On 19 July 2024, this request was subsequently approved by the bank and the settlement completed on 23 July 2024. On the basis of the above, the mortgage manager acted appropriately in ensuring the settlement proceeded within the service level timeframes. It could not reasonably have known what information the bank’s credit team would request ahead of the bank’s consideration of the request and therefore was not in a position to have pre-emptively gathered the information from the borrowers. Even if all relevant information had been provided with the initial request, I am satisfied the bank would more likely than not have only commenced its review on 16 July 2024 in any case. The mortgage manager regularly provided updates to the complainant While the complainant says the borrowers and their solicitor received very little contact from the mortgage manager, the email exchanges between the parties show the mortgage manager kept in regular contact with the borrowers. The mortgage manager also responded to requests for information and updates from the borrowers within a reasonable timeframe. The mortgage manager processed the discharge within the required timeframes The mortgage manager was required to process the discharge to settlement within 20 business days from the date it received the completed forms. As the discharge form was not received until after the close of business on 1 July 2024, the timeframe for processing should be considered to commence on 2 July 2024. Accordingly, the mortgage manager was required to process the discharge by 24 July 2024. As the settlement was completed on 23 July 2024, I consider the mortgage manager processed the request within the required timeframes. 2.2 Why is the outcome fair? The mortgage manager processed the discharge within the required timeframes and took all reasonable actions to try to have the bank process the request quickly. However, it was never reasonable to expect either 10 calendar day (from 23 June 2024) or same day (on 1 July 2024) processing of the partial discharge request. In these circumstances, it would not be fair to require the mortgage manager to pay compensation. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Chronology Timeline of key events | Date | Key events | 25 May 2024 | · Contract of sale (COS) executed by the complainant. · COS stated the settlement date to be 35 days from the contract date. | 21 June 2024 | · Mr W notified the mortgage manager the property had sold. · The mortgage manager: > sent Mr W the Authority to Discharge form and the Variation to Loan Contract form for completion > requested a copy of the COS. · Mr W advised he would provide the COS shortly. | 24 June 2024 | · Mr W: > emailed the COS to the mortgage manager > requested the forms again as this was not received in the previous email. · The mortgage manager resent the forms. | 28 June 2024 | · Signed Variation to Loan Contract form received. | 1 July 2024 | · Borrowers sign the Authority to Discharge form · The mortgage manager received the completed discharge form (after hours). | 4 July 2024 | · The mortgage manager: > sent the completed forms to the bank and > advised the borrowers of bank’s processing timeframe of 15 days | 9 July 2024 | · The bank requested the borrowers provide information regarding their income, living expenses and additional debts held. | 16 July 2024 | · Mr W provided the information requested. · The bank requested additional information from the mortgage manager. | 18 July 2024 | · The mortgage manager requested income and valuation requirements to be waived. · The mortgage manager sent a follow up email and requested urgent approval. | 19 July 2024 | · The bank waived the income and valuation requirements and provided partial discharge approval. · Settlement booked for 23 July 2024. | 23 July 2024 | · Partial discharge and settlement completed.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.