Insurer declined claim for bathroom and bedroom water damage, relying on shower recess leak exclusion; complainant says storm window leak caused it

FirmRACQ
Decided2026-06-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$9,236
Non-financial loss—
Amount claimed$64,198
SourceAFCA PDF

Summary

The complainant claimed $64,197.94 for bathroom and bedroom water damage and a full bathroom rebuild after a storm. AFCA found most damage was from an excluded shower leak but required the insurer to cash settle the window-wall and bedroom wall damage with a 15% uplift.

Most damage was more likely caused by an excluded shower recess leak, but water ingress through the window was accidental damage covered under Advanced cover and not excluded by gradual deterioration or mould exclusions.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All RACQ determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-228497 | Financial firm | RACQ Insurance Limited Case number: 12-25-228497 29 May 2026 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy issued by the financial firm (insurer). On 16 December 2023, the complainant lodged a claim for damage as a result of a storm on 13 December 2023. The insurer accepted storm related damages. On 17 January 2025, the complainant reported further damage to a guest bedroom wall adjoining the bathroom. Further investigation also found damage to the bathroom walls. The complainant says all the damage was caused by a leak during the storm from a window frame in the bathroom. The insurer disagrees the damage is storm related. It says the damage is excluded because it was caused by a leak from the shower recess. The complainant has completed repairs, including a full re-build of the bathroom totalling $64,197.94. She wants the insurer to cover the repairs in full and pay a 15% uplift. The complainant also says the insurer has mishandled the claim. 1.2 Issues and key findings Is the insurer required to cover the claimed damage? On balance, I am satisfied most of the damage claimed is the result of an excluded cause. However, the insurer is required to cover damage to the wall surrounding the bathroom window and damage to the bedroom walls adjoining the bathroom. Is the complainant entitled to compensation? No. The insurer’s conduct does not warrant an award of non-financial loss compensation. Why is the outcome fair? The outcome is fair because it is more likely than not most of the damage in the bathroom is due to an excluded cause. Therefore, it would not be fair to require the insurer to cover all repairs including a full bathroom re-build. 1.3 Determination This determination is partially in favour of the complainant. If the complainant accepts the determination, within 14 days of being notified of that acceptance, the insurer is required to: · partially accept the claim, · cash settle the claim as set out at section 2.1 of the determination based on: > AB’s quoted scope of works dated 27 May 2026 totalling $9,236.34, and > the reasonable costs of repairing damage to the northwest wall of the guest bedroom to be quoted by AB, > applying a 15% uplift to the AB quotes. 2 Reasons for determination 2.1 Is the insurer required to cover the claimed damage? On balance, I am satisfied most of the damage claimed is the result of an excluded cause. However, the insurer is required to cover damage to the wall surrounding the bathroom window and damage to the bedroom wall adjoining the bathroom. Policy covers damage by storm, escape of liquid and accidental damage The terms and conditions of the policy are set out in the product disclosure statement (PDS) and certificate of insurance (COI). As the damage was notified on 17 January 2025 with a date of loss being 10 July 2024, the insurer has provided the COI for the policy period 12 December 2023 to 12 December 2024. The same COI would apply to the second storm damage claim given the reported storm occurred on 13 December 2024. The PDS says the policy covers loss or damage caused by certain insured events including: · liquids leaking from certain items or devices including evaporative air conditioners and fixed domestic items (page 40 of the PDS). There is a definition for ‘Leak’ at page 116 which is: Liquids that are leaking, bursting, discharging or overflowing from household domestic appliances and furniture, pipes, gutters, tanks, drains, bathroom and toilet fixtures. · Cover for leaks specifically excludes: > loss or damage caused by leaks from shower recesses or cubicles, > loss or damage to the item or device which leaked. · Loss or damage caused by a storm. The COI shows the complainant held optional ‘Advanced cover’. At page 69 of the PDS, the policy states there is cover for loss or damage to the home caused by accidental damage. At page 114 of the PDS, the following definitions are provided: Accident – An event or incident which you did not intend or expect, Accidental damage- Damage caused by an accident. There are a number of general exclusions set out from page 82. The policy does not cover loss or damage caused by, arising out of or in connection with: · loss or damage which cannot be linked to any identifiable insured event unless otherwise stated within the benefit, · rust, corrosion, rot, mould or gradual deterioration. There is however, cover for mould damage to the home that happens within 21 days of the first loss or damage caused by the insured events including storm, and · loss or damage caused by a failure to maintain the home in good condition. Parties disagree on cause of damage to bedroom and bathroom walls While the parties agree there is water and mould damage to the bathroom and adjoining bedroom walls, they disagree on the cause of that damage. > the complainant says this is due to water ingress through the bathroom window frame at the time of the storm. The complainant also says the window itself was damaged by the storm > the insurer says the water damage was primarily caused by deteriorated grout/seals and cracked tiles in the shower recess together with waterproofing failure (or inadequate waterproofing). The parties agree: · at the time of the storm in 2023, the property was 9-10 years old, · damage and mould was discovered in the bedroom adjoining the bathroom, shower area wall, and toilet area wall within the bathroom in 2025, · rotted timbers were found behind plasterboard in the bathroom, · no plumbing leaks were found, · there was a leak from the window frame in the bathroom based on spray testing, · at the time the damage was discovered, there was an air-conditioning unit that had pipe work going up through the wall in the bedroom, and · the damage to the walls has been occurring over an extended period. Complainant says cause of damage is stormwater ingress through window The complainant says the damage is directly linked to the storm/cyclone event in December 2023 and water entering through the bathroom window frame. The complainant has made a number of submissions in support of her position including that: · prior to the storm, the bedroom and bathroom were in excellent condition, · the damage began during this storm event and developed since that time, · water ingress through the bathroom window during the storm was highly likely given the property’s north-facing exposure and the extreme rainfall recorded during and after the event. Her builder has confirmed this is the source of the water ingress, · the property was constructed to a high standard and passed all certification requirements, · waterproofing would not normally deteriorate within 10 years of application, · the insurer has not proven any other cause caused or contributed to the damage, · if the storm was even one of several contributing factors, the damage is still claimable under the policy, · the source of the leak is the window where water entered behind the waterproofing, plasterboard and into the cavity. She says the ingress would have occurred during major rain events or routine external cleaning- such as hosing or window washing. · the shower recess was flood-tested and no leak found, · her experts did not identify any plumbing leak from the air conditioner, and · the air-conditioner had a leak in the condenser unit related to gas in the outside unit. This is unrelated to the air-conditioning pipe and did not contribute to water damage at the window and surrounding areas, The complainant has provided · a photograph of the window area after demolition which she says shows signs of adequate waterproofing in this area. The complainant says this contradicts the insurer’s engineer’s finding that no visible waterproofing was in place. The insurer disagrees the photograph demonstrates adequate waterproofing was in place, · documents relating to other damage she has claimed under the policy which she says is related to the storm event. This includes mould in the bathroom which the insurer denied in July 2024, · a summary of costs for the repairs she has arranged and invoices dated between July 2025 and August 2025 issued by her builder, KC, for the bathroom renovation works, and · a quote from her builder, KC, dated 25 March 2025 relating to the bathroom demolition. Complainant’s experts The complainant engaged air conditioner mechanic, EA. EA’s report dated 10 March 2025 and related scope of works/invoice dated 14 March 2025 says their testing indicated a suspected leak in the condenser. The complainant opted to replace the air conditioning system. The complainant engaged builder, KC, to assess the damage. KC attributes the damage to water ingress from the window frame during the 2023 storm. Most relevantly, KC’s report dated 4 March 2025 and supplementary report says: · water was applied to the external walls and windows, noting large quantities of water streaming in under the shower louvered window. The leak was isolated to the window sill. No other water entry points were detected. · KC concludes leak was found to be a leaking window frame. This water that was on outside of any waterproofing was building up & being trapped in the void created by the rebated slab and the tile bedding. · the leak had been occurring for 12 or more months given the amount of rotten framework, · such damage would have been caused by exposure to an abnormal amount of water, · during testing, no signs of waterproofing failure were observed. The waterproofing was intact, and the damage was located underneath it. Insurer says damage is due to a shower leak and is excluded The insurer engaged builder, AC, to assess the damage and report on causation.AC engaged leak detection specialist, CL. In summary, the CL leak detection report dated 13 February 2025 says there may be a number of factors contributing to the damage being: · cracked tiles on the shower base, · deteriorated and missing grouting/seals including around the grate drain in the shower. In particular: > grouting appears damp in places and may have become porous, > sealant around the grate drain in the shower was deteriorated and missing in some places, > CL says flood testing of the shower base was not possible as there is no lip on the base, · calcium stains on tiles indicate the waterproof membrane may be compromised, · use of a shower curtain beside a non-tiled wall may be contributing to the water damage, · window frame is holding water. The water pooling may be seeping into the wall. · cracks in the exterior wall. A moisture metre was used on the exterior wall and much higher than normal readings were found. CL’s report is supported by a number of photographs. In particular, these show deteriorated grouting and sealant, cracks in the shower and cracks to the external wall AC inspected the site on 16 February 2025 and its report says: > Water damage to gyprock walls on opposite side of shower and villaboard walls next to the shower is consistent with waterproofing malfunction/deterioration. > ‘Water definitely looks to be condensation on aircon pipes in wall and tracking around bottom of wall,…’ The insurer also engaged an engineer, IL. IL inspected the premises on 25 March 2025 and provided a report dated 24 April 2025. IL concluded that: · water damage in the bedroom and bathroom was primarily caused by a long-term leak from the shower enclosure due to inadequate/degraded or ineffective waterproofing occurring for years, · the report concedes the bathroom had been stripped out and removed from site prior to IL’s inspection and therefore the condition of the waterproofing could not be confirmed. However, it also says a photograph provided by the complainant’s builder showed plasterboard behind tiles saturated and there was ‘no evidence of waterproof membrane behind tiles’, · IL says its unlikely water entering through the window from rain events could have caused the damage to the shower area. Complainant has not established window leak during storm was sole cause of damage Taking a balance view of the exchanged information, I am not satisfied the sole cause of the claimed damage in the bathroom and guest bedroom is water entry through the bathroom window during the storm/cyclone event in December 2023. This is because: · there is insufficient information to support a finding the window was damaged during the storm event. I am not convinced the drop in pressure during the storm (or other conditions) is likely to have caused the window to fail as the complainant asserts. · while some water ingress may have occurred during the storm, it is not likely this water ingress caused all the damage now claimed. There is no clear information on the quantity of water that would have entered (if any) during the storm noting that it is not known when the damage to the window occurred, · the expert reports relied upon by both parties indicate the damage was significant to walls around the shower. I am satisfied it is likely that deteriorated grout, seals and cracked tiles in the shower would have been the main cause of damage in this area. Relevantly: > The KC report dated 4 March 2025 and IL engineering report identified significant damage in the shower area. In particular, the KC report says: ‒ Wet plaster was removed by hand from the bedroom side and ‘this exposed the rear of the shower wall & again it was visually wet soft’. > I find the photographs in the CS leak detection report and AC building report compelling information demonstrating the deteriorated/missing grout, seals and cracked tiles, > IL‘s report is persuasive as to its reasoning that the damage was primarily caused by a long-term leak from the shower enclosure. In particular, IL says: ‒ the majority of the damage was located around the shower enclosure, ‒ water ingress from the window is unlikely to have caused damage to timber bottom plates on the opposite side of the shower enclosure, · I acknowledge KC says ‘any cracked grout or tiles were likely the result of the leak, not the cause. The water undermined the structure beneath, leading to deterioration of the tile bedding and surrounding framework’. I am not convinced however that it is likely the deteriorated grout, seals and cracked tiles were caused by any water ingress through the bathroom window. It is more likely these issues are due to wear and tear or gradual deterioration. Further, there is no information which shows the property which was about 10 years old at the time of the second claim had bathroom maintenance carried out including re-grouting · I acknowledge the experts disagree on whether the waterproofing in the shower was inadequate or failed. However, on a balanced view of the information, I am satisfied it is more likely than not compromised or inadequate waterproofing contributed to the damage in the shower area. In particular: > I acknowledge KC (which conducted the strip out) says ‘During testing, no signs of waterproofing failure were observed. The waterproofing was intact, and the damage was located underneath it. However, the KC report does not provide details of testing and photographs to confirm the presence and condition of the waterproofing. > further, the insurer’s plumber, CL which inspected the bathroom prior to the strip out noted ‘calcium stains on tiles indicate the waterproof membrane may be compromised’, > IL’s report acknowledges the presence of some waterproofing but also says a photograph provided by the complainant’s builder showed plasterboard behind tiles saturated and there was ‘no evidence of waterproof membrane behind tiles’. > given the above and the severity of the damage in the shower area, I am satisfied it is likely the condition of the waterproofing (or lack of sufficient waterproofing) contributed to the damage. · the exchanged information indicates other factors, including the use of a shower curtain, cracking to an exterior wall and a suspected leak in the AC condenser, may have contributed to some of the damage. Damage from leaking window is covered under ‘Advanced cover’ Given the spray testing carried out, I am persuaded water would have entered through the window over time possibly during multiple rain events and cleaning activities. I am satisfied the requirements for Advanced cover (accidental damage) is triggered in the circumstances. I am satisfied the damage to these walls was caused by an ‘accident’ as defined in the policy. This is because the complainant would not have intended or expected the event/incident of the window failing and this has likely caused some of the claimed water damage to this area. Insurer’s liability is limited to damage caused by water leak from window For the reasons set out above, it is more likely the walls around the shower (including that adjoining the toilet and vanity) were damaged by a leak from the shower recess. The insurer is not liable for this damage as the policy clearly excludes damage caused by a leak from a shower recess. However, I am satisfied water ingress through the window frame more likely than not caused or significantly contributed to damage to the wall around the window itself (excluding the shower area) and the adjacent bedroom walls which were mould effected. This is since · both the complainant’s builder, KC and the insurer’s builder, AC and plumber CL, identified water ingress from the window as being a possible contributing factor to the damage, · KC’s report says the damage to the wall towards the louvered window ‘was visibly worse’. The AB quote dated 27 May 2026 includes repairs to the bathroom wall around the window, the bathroom ‘return wall to the door’ and the ‘wall linings to the bedroom opposite of bathroom nib wall 3m2’. The complainant says a second wall in the bedroom had mould damage and required repairs. The IL report states mould growth was reported in the corner of the northwest wall of the bedroom and photographs are provided of removed wall linings during the repair process. Given the proximity of this wall to the leaking bathroom window frame, I am satisfied the damage to the wall was more likely caused by the leak from the window frame. Therefore, I am satisfied the insurer’s liability extends to repairing the northwest wall of the bedroom (as referred to in the IL report). Insurer has not established exclusion clause applies to all damage I acknowledge the insurer says that even if it were accepted that the damage has been caused by a leak from the window frame (and not a leak from the shower recess), that leak has been occurring for a significant period of time potentially during other rain events. This is the view of KC. The insurer says the damage would in any case be excluded because the policy does not respond to damage not from a single event. Noting I have found a valid claim under accidental damage has been established, I am not satisfied that damage caused by water ingress over time is excluded. This is since the definition of ‘Accident’ does not require that the event or incident was ‘sudden’. Neither is there a requirement that the damage as a result of the accident was sudden. While there is a general exclusion for mould and gradual deterioration, the policy provides cover for mould damage to the home that happens within 21 days of the first loss or damage caused by the insured events. In this case, the insured event is the accidental damage. I am satisfied it is more likely than not mould would have developed within 21 days of the water entry caused by the failed window. Therefore, I am satisfied the insurer is not entitled to rely on the mould and gradual deterioration exclusion clauses to deny cover for the repair of the wall around the window (excluding the shower area) and adjoining bedroom walls. Insurer is not liable for full bathroom re-build I acknowledge the complainant says she had to re-build the bathroom because: · repairing the window frame required breaching the waterproofing system, and · this was a direct and necessary consequence of repairing claimable damage. The complaint also says: · the PDS confirms that when an insured event is accepted, the insurer is obligated to reinstate the property to its pre-loss condition. In this instance, this requires full rebuild to meet certification and waterproofing standards. · this is also consistent with ASIC Report 768 and INFO 253, · the window leak alone, even without any other contributing factor, would have required a full bathroom rebuild. I am not convinced the insurer is liable for the full bathroom rebuild because: · I have found it is more likely than not, the significant damage to the shower area (wall behind vanity and adjacent toilet wall) was caused by a leaking shower recess. I do not accept the leak from the window caused all the damage in the bathroom. As cover for the shower leak damage is excluded, the insurer is not liable for repairs to this portion of the damage, and · it is fair and reasonable that the insurer be required to cover the portion of repairs related to the wall around the window (excluding shower area), return wall to the door, and the guest bedroom wall adjoining the bathroom. Insurer is to cash settle based on AB’s quotes The insurer has provided an updated quote from builder AB dated 27 May 2026 which totals $9,236.34. It includes: · plastering and waterproofing of the wall around the window and the return wall to door, · painting and tiling works, · supply and installation of the bathroom louvre window, · replacement of plasterboard walls linings in the guest bedroom wall adjoining the bathroom including painting. I am satisfied this quote is fair and reasonable for the included works. However, the insurer should also obtain a quote from AB for repairs to the northwest wall of the bedroom (referred to in IL’s report) which was found to have mould damage. The insurer should cash settle the claim based on these two quotes. I acknowledge the complainant says the insurer’s quote is inadequate even for the limited scope of works. I have reviewed the KC invoices provided by the complainant relating to the bathroom renovation. I do not consider it is possible to distinguish the repair works and related costs for which the insurer is liable (as set out above) from the broader repair works included in these invoices. In the circumstances, I am satisfied it is fair and reasonable for the insurer to cash settle the complainant based on the total of the AB scope of works/quote in the amount of $9,236.34 and a further quote to be provided by AB for the northwest wall of the bedroom. The insurer should also apply a 15% uplift to the quoted works for the reasons set out below. Insurer should apply a 15% uplift In the event that AFCA finds an insurer should cash settle a claim based on a reasonable quote for claim related repairs (actionable by an insured) AFCA may require the insurer to apply an uplift (usually between 5% and 20%) to the quoted amount. The purpose of the uplift is to allow for contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs. In this case, the complainant has already completed repairs and is seeking a reimbursement of costs she has already incurred for repair works. I am satisfied the insurer is not liable for all of the repairs. While repairs have been completed, having regard to the purpose of the uplift, I consider it fair and reasonable that the insurer apply a 15% uplift to AB’s repair quotes. This should be included in the cash settlement amount. Complainant’s submissions In addition to the matters already addressed in this determination, the complainant has made a number of submissions in support of her position which have been carefully considered. These do not assist the complainant because: · while I acknowledge the complainant’s builder is the only expert to have conduct invasive testing, the KC report fails to provide details of testing carried out or sufficient photographs to support some of the assertions within the report. Taking a balanced view of all the reports, the leak from the window is unlikely to have caused all of the claimed damage in light of the issues with the shower identified by CL and the severity of damage around the shower identified by all the experts, · the complainant says the insurer accepted damage to bedroom 3 related to storm water ingress but denied cover for the bathroom and guest bedroom despite the shared external wall, identical orientation and exposure, and consistent evidence of ingress. I have considered the exchange information relating to bedroom 3. I am satisfied that the primary cause of damage to bedroom 3 can be distinguished from the primary causes of the current claimed damage, · I acknowledge the complainant says she noticed and reported moisture in the bathroom at the time of the assessor’s attendance in respect to the first claim. The assessor said this was due to environmental factors and did not undertake any inspection or testing. However, there is insufficient information to reach a finding that the insurer unreasonably or negligently failed to investigate the window and any water entry in the context of the storm claim. It is not clear from the exchanged information if there were indications of water ingress through the window frame that could potentially impact the walls when the first claim was assessed, · the complainant says the pre-purchase inspection conducted in late 2018 documented the property was in good condition with no signs of water ingress, structural damage or waterproofing failure. However, I give limited weight to this report because it states that determining whether shower areas are watertight Is beyond the scope of this inspection. · the complainant says no leak was observed or detected from the shower recess and refers to pressure testing which found no leaks. However, the pressure testing conducted only confirmed no leaks were detected from water supply pipes. Leaks from a shower recess can occur due to grout failure or the failure of (or lack of) waterproofing membrane. · the complainant has referred to the determination issued in AFCA case 510592 which she says supports her position. While every complaint is to be considered based on its own circumstances, I have reviewed case 510592. The circumstances of that case can be distinguished from the current case. The insurer in that case did not rely on an exclusion clause for leaks from a shower recess. 2.2 Is the complainant entitled to compensation? AFCA can award compensation for non-financial loss ​​Under our Rules, AFCA can award up to $6,300 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. ​In assessing whether to award compensation, AFCA expects complainants to: · ​be moderately robust, · ​bear the normal degree of inconvenience experienced when a problem occurs, and · ​take reasonable steps to minimise the inconvenience suffered. Complainant’s concerns The complainant has raised a number of concerns regarding the insurer’s handling of the claim which have been carefully considered. Among the complainant’s concerns are · breaches of GICOP related to fair, transparent and timely claims handling, · the insurer has failed to act in good faith, · the insurer relied on expert reports that are not comprehensive and speculative, and · the insurer refused to consider her expert reports or contact her builder. The complainant says the insurer’s conduct has caused stress, frustration, and led her to incur expenses related to repairs and investigations which have been unnecessary, Non-financial loss is not warranted I have carefully considered the above concerns. I am not convinced the insurer’s conduct warrants an award of compensation. I am not satisfied there has been any substantial delays caused by the insurer mishandling the claim. The second claim was notified on 17 January 2025 and a decision provided on 14 April 2025 following assessments by CL and AG. A complaint was lodged on the same day and a response was provided on 15 April 2025. I acknowledge the claim has been prolonged. However, this was mainly due to the need for further assessment due to disagreement between the parties’ experts on the cause of the damage. The insurer was entitled to investigate the damage and its cause in order to form a view on policy response. The insurer has adequately considered the reports obtained by the complainant. The denial of the claim does not of itself amount to mishandling of the claim. 2.3 Why is the outcome fair? The outcome is fair because it is more likely than not most of the damage in the bathroom is due to an excluded cause. Therefore, it would not be fair to require the insurer to cover all repairs including a full bathroom re-build. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.