Insurer denied a variation of $5,476.02 to relocate the electrical point of attachment for storm and hail roof replacement; non-financial loss also claimed
Text of the determination
Determination
|
Case number
|
12-25-224709
|
Financial firm
|
RACQ Insurance Limited
Case number: 12-25-224709 29 October 2025
1 Determination overview
1.1 Complaint
The complainant is represented by CC, claim managers. Unless otherwise indicated, both the complainant and CC will be referred to as ‘the complainant’.
The complainant holds a building and contents policy with the financial firm (the insurer) for his home that is located in the State of Queensland (the property). He lodged a claim for storm and hail damage to the property in November 2023. The date of loss was determined to be December 2019.
The complainant’s preferred builder, AC, and the insurer’s builder, RB, inspected the property and assessed the damage and loss. The insurer then accepted the claim, and cash settled the complainant based on RB’s scope of works (SOW).
In January 2025, AC submitted a variation for $5,476.02, being the costs associated with relocating the property’s electrical point of attachment (POA). However, the insurer denied the variation. It says the POA is already compliant and does not have to be moved to complete the works.
The complainant disagrees and says, amongst other things, regulations essentially require the POA to be relocated. It says the insurer should therefore accept the variation.
CC also says the insurer should pay the complainant $1,000 in non-financial loss compensation.
1.2 Issues and key findings
Is the insurer entitled to deny the variation?
Yes. The exchanged material demonstrates the insurer is entitled to deny the variation.
Should the insurer pay non-financial loss compensation?
No. It would not be fair and reasonable to compel the insurer to pay non-financial loss compensation in this instance.
Why is the outcome fair?
The outcome is fair in all the circumstances because:
· the exchanged material shows the variation is not required to complete the storm-related repairs
· an award of non-financial loss compensation would not be reasonable and appropriate in this instance.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action in relation to this complaint.
2 Reasons for determination
2.1 Is the insurer entitled to deny the variation?
Yes. The exchanged material demonstrates the insurer is entitled to deny the variation.
Complainant says the POA must be relocated
The property includes a single storey, detached, brick-veneer dwelling with a low-pitched metal roof. The exchanged material indicates the dwelling was constructed in about 1995.
On 2 November 2023, the complainant lodged the claim. At that time, he told the insurer a hailstorm that occurred almost four years previously, on 11 December 2019 (the storm), damaged the property, primarily the roof.
As indicated, the insurer accepted the claim and paid a cash settlement to the complainant in the sum of $52,700.31 on 19 July 2024. The works covered by the insurer mainly involve the replacement of the property’s roof. The claim was then closed by the insurer.
On 23 January 2025, AC submitted a report and variation, stating:
As suggested by [RB, an] electrical safety assessment was conducted. Based on the report, it was determined that due to unsafe and unforeseen conditions of the [POA], [EX, the retail energy supplier] has advised engaging an electrician to relocate the fuse to the main pole before commencing any roof repair work. Until this relocation is completed, the roof repair work cannot proceed…
In [AC’s] professional opinion, we have determined that the following additional works are required in conjunction to our [SOW] to bring the property to a pre-event condition and to complete the overall works within accordance to the current BCA/NCC.
The insurer sought the opinion of RB who, on 6 February 2025, concluded the variation was not necessary because:
1. the fuse is already on the street pole and not on the POA
2. an exclusion zone can be created around the area, or the fuse pulled whilst working in the area, to prevent risks, and then reinstated after completion
3. there are no legal or code compliant reasons to upgrade what is already in place. Whilst it is not ideal, it is compliant and can remain the way it is.
Based upon this evidence, the insurer determined the roof replacement could proceed without removing or upgrading the overhead connection. It therefore denied the variation on 13 February 2025.
Experts provided opinions
CC also provided a safety advice that had been commissioned by BB, builder. The safety advice was performed by JW of EQ, a state government owned corporation which draws together a group of Queensland electricity distribution, retail and energy services businesses. JW’s safety advice outlined a mandatory exclusion safety zone which needed to be addressed when completing the works at the property.
RB then reviewed the safety advice and discussed it with JW. RB said JW advised:
The current situation with the overhead connection is fine and can remain. [JW] recommends it gets upgraded to the current installation method, however, confirms it is not necessary and can be completed at any time after the roof replacement if the owner chooses to upgrade.
To replace the roof in the current situation, [JW] recommends the fuse is pulled during works within the exclusion zone and reinstated after those works are completed.
Based on our experience, an exclusion zone can be installed, the roof can be replaced without the removal and upgrade of the overhead connection and no variation is required.
I further confirm there is no recommendation from [JW] to move the fuse that is correctly installed.
In support of the claim for the variation, EC provided written submissions dated 24 July 2025, in which it states, amongst other things:
The POA was compliant prior to the date of loss. Its relocation only became necessary in the course of works undertaken to replace the entire roof of the Insured Property.
In the course of works undertaken, a live electrical cable ran across the work zone. Work Health and Safety regulations require a 3-metre clearance from live lines during construction, therefore rendering relocation of the POA mandatory to safely complete the roof replacement.
Variation is not required to complete the storm-related works
In all the circumstances, I am satisfied the exchanged material shows the POA does not need to be relocated to complete the works. Therefore, the variation is not required. It follows the insurer is entitled to deny the variation.
This is because of the following considerations.
First, RB and JW agree the repairs can be safely undertaken if an exclusion zone is established and other safe work methods are adopted. This strategy does not require the relocation of the POA.
Second, JW supported the premise that the works could be undertaken after pulling the fuse and reinstating it upon completion. I note the problem regarding an absence of power to the property could then be alleviated by the provision of a generator on site.
Third, I note AC inspected the roof of the property and provided a report dated 31 October 2023. It then provided a detailed SOW for the storm-related works shortly thereafter. The SOW contains the following relevant items:
· isolate street pole power 2 fuses, supply and install timber shroud, reconnect power when safe with clearance/safety certificate provided
· obtain EX Safety Advice for mains power disconnect and reconnect.
This indicates AC was of the opinion the necessary works could be completed without relocating the POA. Moreover, it can be reasonably concluded that, had AC thought the POA needed relocation, it would have included the costs associated with relocation in its original SOW.
Fourth, I am satisfied RB’s conclusions are rational, logical and reasonable. RB acknowledged the POA’s position presents some challenges, but that such challenges can be managed safely without relocating the POA. RB stated that, during repair works, the POA can be isolated and barricaded, and a Safe Work Method Statement can be issued. This would include the disconnection of the fuse to ensure there is no live power in the area while works are undertaken, followed by appropriate barricading to complete the repairs safely. I am satisfied this is a reasonable approach.
Fifth, I acknowledge CC says the electrical trades claim they cannot certify the works unless the POA is relocated: However, I am not persuaded this is, indeed, the case. There is no requirement for electrical contractors to certify the POA itself in this instance. As RB says, the electrical trades are permitted to legally disconnect and reconnect as needed under the guidance of EX, and RB (for example) is fully capable of completing these works in a manner that is both legal and compliant, without the need for unnecessary and unapproved upgrades.
Sixth, I acknowledge CC says the work methods proposed by the insurer, such as creating an exclusion zone or pulling the fuse during the works, are merely short-term risk mitigation measures and workarounds which are not practical or sustainable solutions. However, I am not satisfied CC has provided persuasive evidence which shows these proposed safe work methods are impractical or unreasonable in this particular instance.
In conclusion, the exchanged material shows the POA relocation is not necessary to complete the works. It follows the insurer is, therefore, entitled to deny the variation.
2.2 Should the insurer pay non-financial loss compensation?
No. It would not be fair and reasonable to compel the insurer to pay non-financial loss compensation in this instance.
AFCA Can award non-financial loss compensation in certain circumstances
CC says the insurer should pay the complainant $1,000 in non-financial loss compensation ‘for the unnecessary delays incurred on this file’.
Under the AFCA rules, non-financial loss compensation (capped at $6,300) may be awarded in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind.
However, complainants should note that non-financial loss is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Moreover, non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer.
Compensation not warranted in this instance
I am not satisfied the complainant in this matter has suffered adversely because of unavoidable delays brought about by the insurer. The exchanged material shows CC submitted the variation request for the relocation of the POA on 30 January 2025, following by the FF providing the declinature of this variation request on 28 February 2025.
CC then expressed dissatisfaction with the variation request outcome, and a complaint was recorded on 28 February 2025. The insurer undertook a review of the complaint and issued a final internal dispute resolution (IDR) decision on 7 March 2025.
Whilst the IDR decision provided details of AFCA; and the ability to lodge a complaint, CC did not take that next step until 8 April 2025.
The above timeline shows the insurer managed the claim for the variation in a reasonable and timely manner. Indeed, if time was of the essence, it is reasonable to assume that CC would have lodged the AFCA complaint sooner.
Moreover, I am not satisfied the complainant in this matter has suffered an unusual degree of physical inconvenience and interference with his expectation of enjoyment and peace of mind. I note CC claims that a specific sum of non-financial loss compensation should be awarded (that is, $1,000). However, CC has not provided any persuasive or detailed description of the upset, inconvenience and stress suffered by the complainant which would justify an award of non-financial loss compensation in that amount.
Given the matters set out above, I am of the opinion an award of non-financial loss compensation would not be fair or reasonable in this instance.
2.3 Why is the outcome fair?
The outcome is fair in all the circumstances because:
· the exchanged material shows the variation is not required to complete the storm-related repairs
· an award of non-financial loss compensation would not be reasonable and appropriate in this instance.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.