1 Determination overview
1.1 Complaint
The complainants hold home building insurance with the financial firm (insurer). They lodged a claim after their home was damaged in a weather event on 7 March 2025. The insurer accepted the claim, but the complainants are dissatisfied with its claim handling.
The complainants say the insurer’s miscommunications, delays and inadequate make safe repairs have resulted in their policy entitlement to temporary accommodation (TA) being exhausted before repairs have been completed and led to their contents becoming mould affected. Also, that the insurer’s conduct has caused them major stress and inconvenience.
The insurer accepts that there have been delays but says it is not responsible for most of them. Further, that the complainants were on notice from the outset of the extent of TA cover available and that the policy does not include cover for contents. The insurer says payments it has made and offered outside the policy terms sufficiently compensates the complainants.
1.2 Issues and key findings
Is the insurer required to cover further TA costs?
No. Based on the exchanged information, it is more likely than not that the TA cover would have been exhausted before repair completion even if the claim had run smoothly.
Is the insurer required to cover the contents?
No. The complainants did not take out cover for contents and I am not satisfied that the insurer advised them to leave the contents unprotected in the home.
Is more non-financial loss compensation payable?
Yes. The insurer has contributed to the delays and on occasions communicated poorly. Those matters have caused both complainants notable stress and inconvenience. Allowing for the insurer’s prior compensation payments, it is to pay each of them a further $2,000.
Why is the outcome fair?
It would be unfair to require the insurer to pay for TA outside the policy when the TA cover would likely have run out before repair completion in any event. The policy does not cover contents, and the insurer is not responsible for the contents damage so it would be unfair to require the insurer to pay for that damage. However, it is fair that it pays more compensation.
1.3 Determination
This determination is partially in favour of the complainants. Within 14 days of the complainants accepting this determination, the insurer is to pay each of them $2,000 ($4,000 in total) as non-financial loss compensation. The insurer is otherwise not required to take any further action in relation to the matters the subject of this complaint.
2 Reasons for determination
This determination does not affect the complainants’ right to lodge a further complaint about the repairs to be undertaken/cash settlement to be paid, or the insurer’s future claim handling.
2.1 Is the insurer required to cover further TA costs?
No. Based on the exchanged information, it is more likely than not that the TA cover would have been exhausted before repair completion even if the claim had run smoothly.
Background
Subject to the terms and conditions set out in the certificate of insurance (COI) and the product disclosure statement (PDS), the policy covers the complainants for loss or damage to their home caused by a listed insured event. Those events include ‘Storm’.
On 11 March 2025, the complainants notified the insurer that on 7 March 2025, their home had been damaged by ex-tropical cyclone Alfred. The damage included impact damage to the roof from a falling tree, leading to water ingress.
On 13 March 2025, at the complainants’ request, roofer F installed a temporary make safe tarp over the damaged roof area. The insurer’s builder J also contacted the complainants that day to arrange make safe works to the roof but was told by them that was no longer required.
On 18 March 2025, J inspected the home. It said there was water ingress damage throughout the kitchen (including collapsed ceiling), lounge room, living room, rumpus room, hallway, bedrooms and bathroom. Externally, there was damage to the garage ceiling, fencing, garden shed and roofing. J initially estimated a 2.5-month repair period. It appears that J also installed additional roof tarps at the time.
On 19 March 2025, the insurer’s internal assessor, P, inspected the home. In essence, P confirmed to the insurer that the claim related damage was as J had reported.
On 22 March 2025, restorer R inspected the home. R noted that ceilings, wall linings and flooring throughout the property had been damaged and returned elevated moisture readings. Drying equipment was installed and a make safe was performed by treating all exposed mould and plastic sealing affected areas.
On 28 March 2025, R returned. R noted continuing elevated moisture readings and further water damage and mould growth. It recommended TA be arranged.
The insurer accepted the claim on 24 March 2025.
Policy covers TA in specified circumstances
The TA costs coverage is set out on page 42 of the PDS. If the insured home becomes unliveable due to an insured event and the insurer agrees to pay the resulting claim, it will also pay for reasonable TA. The insurer will also pay reasonable costs to store contents in a commercial storage facility if they cannot be stored at the TA or remain in the home.
The maximum amount payable is 10% of the home building sum insured. The COI confirms the home building sum insured is $750,000, so the TA costs limit is $75,000. The maximum TA period is 12 months from the date the damage to the home occurred.
Insurer has paid out TA limit
On 17 March 2025, the complainants informed the insurer that the kitchen and bathroom ceilings had collapsed. The insurer offered the complainants TA for two weeks pending the claim being accepted.
In the next three weeks, the parties discussed the types of TA that could be provided (e.g. short or long term), the needs of the complainants’ family (two adults, three children, two dogs), reasonable rental costs, and available rental properties.
The complainants wanted payout of the TA limit. Whilst it originally considered this, on 31 March 2025, the insurer said it would not do so as it had received builder B’s scope of works (SOW). This estimated four months as the required repair period rather than the 6-9 month estimate J had provided. B’s quote for the works was $194,485.
On 9 April 2025, the complainants told the insurer they had secured a property at $2,000/week but could not afford the $8,000 bond. The insurer noted the policy did not cover the bond as it is returned to the lessee at the end of the lease. However, it offered to pay the complainants in advance eight weeks of rent. On 11 April 2025, a $16,000 payment was raised.
On 14 April 2025, the complainants told the insurer that its four-month repair period estimate (three months plus a month for contingencies) was based on out-of-date information as additional damage had occurred due to continuing water ingress and mould growth.
On 14 May 2025, P reinspected the home. He reported that:
· further water ingress had occurred ‘due to what presents as failed make safes’
· the ingress had caused damage to rooms that had not previously been damaged, most notably to the master bedroom’s ensuite, and there were visible mould patches
· builder B would check the rear tarping was watertight and look to replace tiles over the ensuite. This was because, due to the roof’s steep grade, the previously installed tarping was not the best option over the ensuite
· B advised to allow about 16 weeks from strip out and drying before an accurate building repair SOW could be prepared. At that point in time, B estimated the building repairs would take about 16 weeks
· accordingly, 32 weeks of further TA would be required.
B attended the following day, removed the damaged roof section, and installed new battens and roof tiles.
On or about 28 July 2025, the insurer reimbursed the complainants $3,850 for removalist costs they had incurred. The reimbursement was paid out of the TA limit.
The insurer continued to pay for the complainants’ TA. As of 31 August 2025, $31,150 of the TA limit remained available. The insurer paid the complainants that amount as a lump sum.
Parties disagree on whether TA beyond policy limit is payable
The complainants say the insurer should continue to pay for TA until the required repairs are complete because:
· it failed to provide adequate care and support to them and their family as vulnerable consumers, meaning they were forced to stay in an unhealthy and uninhabitable environment for longer than they should have done.
· it has caused extensive delay, including by appointing B to take over from J
· it’s make safe works failed on several occasions, leading to additional damage
· it agreed to cover the $8,000 bond only to subsequently say it would not do so
· it failed to provide adequate support in identifying suitable long-term TA
· it’s refusal to pay out the TA limit at an early stage limited their ability to secure stable accommodation until their home is repaired
· it was repeatedly late in covering rent, which caused them financial and emotional stress.
The insurer says:
· the complainants were not informed that the bond would be covered but in recognition of their situation, it made an initial advance payment of eight weeks’ rent
· delays have been experienced, but that most of them were not caused by it
· the extent of damage meant from the outset the repair period would be lengthy
· the initial roof make safe was performed by the complainants’ trade
· if an element of make safe work fails, that is not reflective of the builder’s oversight or poor workmanship, but due to an unforeseen circumstance
· the replacement of J with B was in large part prompted by the complainants’ dissatisfaction with J
· the complainants elected to stay in the home rather than take up emergency TA as they wanted to maximise the period over which they would have TA
· it provided all reasonable assistance to the complainants to obtain TA
· overall, it was not late in covering rent.
Insurer is not required to cover further TA costs
Based on the exchanged information, I am not satisfied it would be reasonable to require the insurer to pay for TA outside the policy terms. That is primarily because it is more likely than not that the TA cover would have been exhausted before repair completion even if the claim had run smoothly.
In reaching that conclusion, I have taken the following into account:
· based on a $2,000/week rent, the $75,000 TA costs limit covers 37.5 weeks
· J’s initial assessment of the home occurred a week after the storm event. At that time, it was identified that there was extensive water damage throughout the home
· four days later, R confirmed there were elevated moisture readings throughout the home and that mould was already present
· between 18 and 31 March 2025, J provided a repair period estimate of 24 to 36 weeks
· while on 31 March 2025, B provided a repair period estimate of only 16 weeks, that appears to have been ambitious given the amount it quoted for repairs at the same time
· from an early stage of the claim, the complainants raised concerns that the TA limit would be exhausted before the claim was finalised
· it appears that water ingress was an ongoing issue from when F installed roof tarps on 13 March 2025. The insurer is not responsible for F’s work
· I acknowledge that subsequent attempts by J to address the ongoing water ingress were also unsuccessful. However, I agree with the insurer that make safe is intended to be a temporary solution only, and that lack of success is not necessarily indicative of negligence
· by 14 May 2025, P confirmed a further 32 weeks of TA would likely be required on top of the four weeks already incurred
· the insurer legitimately paid $3,850 for removalist costs out of the TA limit
· I am not satisfied that the insurer ever agreed to cover the bond, and accept a rental bond is not payable under the policy terms.
I acknowledge that complainants’ concerns that the insurer did not provide them enough support in identifying suitable long-term TA and caused them stress through late payments. Even if established, such issues are relevant to the extent to which they may be entitled to further non-financial loss compensation, not to whether TA above the limit should be paid.
2.2 Is the insurer required to cover the contents?
No. The complainants did not take out cover for contents and I am not satisfied that the insurer advised them to leave the contents unprotected in the home.
Complainants say the insurer’s advice caused contents damage
It is not in dispute that the complainants did not include contents cover on the policy.
The complainants say that the insurer informed them to obtain removalist and storage quotes for their contents, which they did. However, during a telephone conversation on 15 April 2024, claims consultant C told them as they did not have contents cover, they were not entitled to storage. Further that they should place all the contents in specified rooms in the home.
They say they reluctantly did so on about 19 April 2025. However, before that they put the insurer on notice they would hold it responsible for any damage to the contents, particularly as the home was already mould affected.
Further, the complainants say that during a meeting on 13 May 2025, H confirmed it was appropriate to leave the contents in the home.
According to the complainants, in the week before the restoration works were to begin on 10 June 2025, the restoration team attended the home. The team advised them that the contents had to be removed and professionally cleaned, and the works would have to be postponed due to contamination concerns.
The complainants refer to a subsequent email dated 9 June 2025, in which C advised them that the contents would have to be removed due to the increased mould in the home. C also said the complainants would be responsible for the removal, which should be done by the end of the week so the restoration could occur without delay.
The complainants submit that in the circumstances, the insurer should cover the contents damage outside the policy terms.
Insurer says complainants are not entitled to contents cover
The insurer says that a week after claim lodgement and several times after that, the complainants were reminded that they did not hold contents cover. It also refers to a claim note entry dated 26 March 2025 (just over two weeks after lodgement), in which the male complainant said he wanted his contents covered and would force the insurer to cover them.
The insurer accepts that on 14 April 2025, a claims team member unfamiliar with the claim responded to requests made by the complainants, advising they should submit removalist and storage quotes for assessment as to reasonableness.
However the insurer says the next day, C spoke to the complainants and advised that storage was unnecessary as the contents could be stored at the home by its trades. Further, that during that conversation C confirmed that the contents would be moved by the trades.
The insurer also refers to its email dated 17 April 2025 to the complainants which included:
As per our conversation on 15 April, storage costs are not something we would cover as we can store the items in the home. If you wish to move your items, this will not be covered under your home claim.
The insurer advises the intention had been to move the contents to undamaged areas in the home and seal off those areas. However, delays were experienced due to the complainants’ disagreement with the restoration SOW and request that a structural engineer be involved.
The insurer also notes that it was not until 28 April 2025 that the complainants informed it that they had moved the contents and left them in the home (unprotected) when they moved out.
H has confirmed that he told the complainants that he could not make claim decisions.
The insurer submits that it has no liability for the damage to the complainants’ contents.
Insurer is not required to cover contents
The complainants did not take out cover for contents.
Based on the exchanged information, I am not satisfied that the insurer should be obliged to pay for the damaged contents outside the policy terms because:
· having carefully listened to the call recording of the telephone conversation on 15 April 2025, C said the insurer’s trades could move and safely store the contents in the home
· that was confirmed in the insurer’s email dated 17 April 2025, which also in effect put the complainants on notice they should not move the contents
· on 18 April 2025, the complainants moved and left the contents unprotected in the home
· by the time the complainants told the insurer they had done so, on 28 April 2025, the contents were mould affected.
2.3 Is more non-financial loss compensation payable?
Yes. The insurer has contributed to the delays and on occasions communicated poorly. Those matters have caused both complainants notable stress and inconvenience. Allowing for the insurer’s prior compensation payments, it is to pay each of them a further $2,000.
AFCA can award compensation for non-financial loss
Under paragraph D.3.3 of its Rules, AFCA may award up to $6,300 in compensation for non-financial loss where the insurer’s actions have caused an unusual amount of physical inconvenience, time taken to resolve the situation, interference with the complainant’s expectation of enjoyment or peace of mind.
Where there is more than one complainant, and each complainant suffered non-financial loss, each can be awarded compensation.
AFCA takes a conservative approach to awarding compensation for non-financial loss. We expect complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation.
Insurer is to pay non-financial loss compensation to each complainant
The complainants say that the insurer’s delays, miscommunication, lack of compassion, and failure to accommodate their financial and personal vulnerabilities have profound affected their entire family. They refer to major stress and inconvenience, emotional distress, physical and mental harm, and overall disruption of their lives.
The insurer accepts that it contributed to the delays experienced during the initial period of the claim. However, it says it has adequately compensated the complainants by paying on an emergency basis $1,895 for the complainants’ car charger despite it being a contents item, $1,000 in non-financial loss compensation, and offering them a further $1,000.
Having carefully reviewed the exchanged information, I am satisfied that the insurer did contribute to the delays experienced and on occasions communicated poorly. Even though the complainants’ service expectations appear at times to have been unrealistic, I accept that the insurer’s failings have caused each of them notable stress and inconvenience.
Allowing for the insurer’s prior payments, it is to pay each of them a further $2,000.
2.4 Why is the outcome fair?
It would be unfair to require the insurer to pay for TA outside the policy when the TA cover would likely have run out before repair completion in any event. The policy does not cover contents, and the insurer is not responsible for the contents damage so it would be unfair to require the insurer to pay for that damage. However, it is fair that it pays more compensation.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.