Determination 12-25-220896

Amount of cash settlement for outstanding storm repairs, defective repairs and delays

FirmRACQ
Decided2026-02-24
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$5,000
Amount claimed$300,000
SourceAFCA PDF

Summary

A storm damaged the complainant's home and the insurer's builder left repairs incomplete. AFCA found the repairs were not defective, but required a new quote including extra items plus a 20% uplift and $5,000 for non-financial loss from delays.

The insurer must cash settle outstanding repairs at a fair cost including omitted items, and its delays from 26 June 2024 to 19 March 2025 caused unusual stress and inconvenience, while defects and potential liability were not shown.

Issues

Subjects and remedies

disabilityhome or building damagenatural disasterpay claimpay non financial loss

Related

All RACQ determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-220896 | Financial firm | RACQ Insurance Limited Case number: 12-25-220896 28 January 2026 1 Determination overview 1.1 Complaint ​The complainant holds a home insurance policy with the financial firm (the insurer). She lodged a claim after her home was damaged by a storm on 25 December 2023. The insurer appointed a builder to carry out repairs. The repairs were not completed. The complainant says the repairs that were completed were defective. On 29 January 2025, the insurer’s builder quoted $52,903.47 for the outstanding repairs. The insurer has offered to settle the claim by paying $63,484.16 ($52,903.47, plus a 20% uplift). The complainant says the insurer should pay about $150,000 to $300,000, being: · $40,000 to $50,000 to rectify defective repairs · $70,000 to $80,000 to finish incomplete repairs · $50,000 to $130,000 for potential legal liability (due to incomplete repairs leaving the property in a dilapidated and dangerous condition) · $6,300 (the most AFCA can award) for indirect financial loss · $6,300 (the most AFCA can award) for non-financial loss (stress and inconvenience). 1.2 Issues and key findings Are the insurer’s repairs defective? No. The complainant has not shown the insurer's repairs are defective. The insurer is not required to pay for rectification work. Is the insurer required to increase its offer? Yes. The insurer’s offer should be increased to allow the cost of additional work to the pool patio, the installation of flashing over a gable roll, and supervision. Is the insurer required to pay other compensation? Yes. The insurer caused delays from 26 June 2024 to 19 March 2025. The complainant has not shown these delays caused any financial loss. However, the delays caused stress and inconvenience. The insurer must pay $5,000 compensation for non-financial loss. Why is the outcome fair? The parties have agreed that the insurer will settle the remainder of the claim by paying a cash settlement (rather than by arranging further repairs). I am satisfied that the method set out in this determination is the best way to determine a fair settlement sum. 1.3 Determination This determination is partly in favour of the complainant. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer must obtain a new quote for the fair and reasonable cost of the outstanding repairs. The quote must include the work included in the insurer’s builder’s quote of 29 January 2025, plus the following work: · pool patio > repair timber framing and bracing > remove and reinstate heater > reclad/paint/stain wall where downpipe was disconnected > replace light disconnected by roofers · house roof > install flashing over gable roll at back of house · general > supervision. The insurer must pay the complainant the amount of the quote, plus a 20% uplift for contingencies and the transfer of risk due to cash settlement. The insurer must pay the complainant $5,000 compensation for non-financial loss. 2 Reasons for determination 2.1 Are the insurer’s repairs defective? No. The complainant has not shown the insurer's repairs are defective. The insurer is not required to pay for rectification work. Insurer appointed builder to repair storm damage The complainant’s home was damaged by a storm on 25 December 2023. She lodged a claim for the damage on 26 December 2023. The complainant had builders working on the property before the storm. The parties discussed whether the storm damage would be repaired by the complainant’s builders or the insurer’s builders. In March 2024, the parties agreed to have repairs done by the insurer’s builders. The insurer appointed a builder which carried out repairs between August 2024 and November 2024. The insurer’s builder did not complete the repairs as originally agreed. The insurer has agreed to pay the cost of the outstanding repairs. This is discussed in more detail in section 2.2 of this determination. The complainant says the work completed by the insurer’s builder had the following defects: · roof sheets laid incorrectly · shade sail leaking · solar system online monitoring no longer working. The complainant says the insurer should pay the cost of rectifying these defects. The insurer does not admit its builder’s work was defective. Complainant has not shown defect in roof sheet installation The insurer’s builder installed new roof sheets on the house. The complainant says the new roof sheets are correctly aligned at the front of the house (where the builder started), but misaligned at the back of the house. Because of this, the gable roll at the back of the house is not sitting tight and flush. The complainant originally suggested installing flashing over the gable roll, which the insurer agreed to do. However, she now says she does not want flashing installed over the gable roll. She says the roof sheets should be removed and relaid. The insurer’s builder says the roof is out of square, and this is an issue that pre-dated the storm. It says it correctly installed the new roof sheets parallel with the fascia. The complainant does not accept that the roof is out of square. She says the insurer’s builder did not measure the roof correctly, and did not provide photographs showing how they measured the roof. However, she has not provided her own measurements, photographs, or expert reports showing the roof is square. The insurer says removing and relaying the roof sheets would not rectify the issue because the sheets have to be installed parallel with the existing structure, which is not square. The complainant says that even if the roof is not square, the roof sheets could be ‘crept as they went along’ to keep them lined up with each side of the roof. However, the builder says creeping roof sheets can cause leaks. Having considered the information provided by both parties, I am not satisfied the insurer’s builder’s work in laying the roof sheets was defective. I am satisfied installing flashing over the gable roll is the most appropriate solution. The insurer is required to pay the cost of installing flashing over the gable roll. It is not required to pay the cost of removing and relaying the roof sheets. Shade sail equivalent to previous shade sail The insurer’s builder replaced a damaged shade sail attached to the back of the house. The complainant says the new shade sail is leaking. The insurer’s builder says the old sail was made of material that was not waterproof. It says it replaced the old sail with a new sail made of similar material. The complainant says the old sail and the new sail were made of waterproof material, but the new sail is leaking at the seams. Photographs of the old sail show it was made of a mesh fabric which did not look waterproof. The complainant provided a video and photographs showing rainwater pouring through the new shade sail. The photos also show rainwater pouring through a similar shade sail in the back yard, which was not damaged by the storm or replaced by the insurer’s builder. The complainant has not shown there is any defect in the new shade sail. The insurer is not required to pay the cost of installing another new shade sail. Complainant has not shown builder damaged solar system The insurer’s builder removed and reinstated solar panels. The complainant says the solar system’s online monitoring is no longer working. The insurer appointed an electrician, who inspected the solar system on 17 July 2025. The electrician said the solar analytics device was controlled by a third-party application which they could not access. The insurer’s builder said the complainant would need to contact the solar system company’s tech support to get the system working. The builder said they could do this for the complainant if she provided her account login and password. The complainant has not said whether she tried to contact the solar system company’s tech support after the builder suggested this. The complainant has not shown the insurer’s builder damaged the solar system. The insurer is not required to take any further action in relation to the solar system. 2.2 Is the insurer required to increase its offer? Yes. The insurer’s offer should be increased to allow the cost of additional work to the pool patio, the installation of flashing over a gable roll, and supervision. Insurer has provided quote for outstanding repairs The insurer’s builder prepared a quote for outstanding repairs totalling $46,693.67. On 9 January 2025, the insurer offered to settle the claim by paying $56,032.40 ($46,693.67, plus a 20% uplift). The complainant said the insurer’s builder’s assessment was missing some items that should have been included. The insurer’s builder prepared an amended quote for outstanding repairs totalling $52,903.47. On 24 February 2025, the insurer offered to settle the claim by paying $63,484.16 ($52,903.47, plus a 20% uplift). The complainant said the prices of items in the builder’s latest quote (dated 29 January 2025) were lower than in one of the builder’s previous quotes (dated 20 December 2024). The prices were the same, but the quotes were formatted differently. In the quote of 20 December 2024, a builder’s margin of 16% was included in each item. In the quote of 29 January 2025, the builder’s margin of 16% was added at the end of the quote. Insurer has agreed to pay 20% uplift When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. AFCA considers that if an insurer cash settles a claim, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs. Both parties have proposed that the insurer add a 20% uplift to its settlement payment for the outstanding repairs. In my view, it is fair for the insurer to pay a 20% contingency for the transfer of risk on the settlement payment for the outstanding repairs. Insurer must pay for addition work on patio The insurer’s builder’s quote includes $11,130.55 ($8,723, plus 16% builder’s margin and 10% GST) for repairs to patio roofing. It includes the following work: · replace Colorbond roofing · supply and install insulated panel · replace PVC downpipe. The complainant says the quote is missing the following items for the patio roofing: · replace beam for roof structure · remove and reinstate heater to allow replacement of beam · reclad/paint/stain wall where downpipe was disconnected · replace light disconnected by roofers. The insurer’s builder first inspected the complainant’s property on 11 January 2024. The builder’s first report said a tree had fallen on the rear pool patio. The report included the following work under ‘Recommended Insurable Repairs’: ‘Remove roof sheeting to pool patio - repair timber framing and bracing and re-roof’. The builder’s quote includes the replacement of roof sheeting, but not the repair of timber framing. The builder’s initial report indicated the framing was damaged by the storm, and the insurer has not provided information showing this is not the case. The insurer should pay for the repair of the framing. The insurer has not commented on the other items the complainant says are necessary to repair the patio. It has not provided information showing they are not necessary. I am satisfied it is fair for the insurer to pay for these items. The insurer’s offer should be increased to allow the cost of the additional work on the patio. Insurer not required to pay for further electrical work The complainant says the builder’s quote is missing the labour to lay the conduit for an underground power line. The builder’s quote includes $1,684.32 ($1,320, plus 16% builder’s margin and 10% GST) for electrical work, including running a power cable underground. The complainant has not provided information showing further electrical work is necessary. The insurer is not required to pay for further electrical work. Insurer must pay for project management The complainant says the builder’s quote is missing an allowance for project management. One of the builder’s earlier scopes of work (undated) included an allowance for supervision (four hours, cost not stated). The insurer has not explained why the builder’s latest quote does not include an allowance for project management or supervision. The insurer’s offer should be increased to allow the cost of supervision. Insurer must pay for flashing over gable roll As stated above, the insurer agreed to install flashing over the gable roll at the back of the house. The insurer’s offer should be increased to allow the cost of this work. Insurer must obtain new quote for outstanding work The insurer’s offer should be increased to allow the cost of the following work: · pool patio > repair timber framing and bracing > remove and reinstate heater > reclad/paint/stain wall where downpipe was disconnected > replace light disconnected by roofers · house roof > install flashing over gable roll at back of house · general > supervision. Neither party has provided an estimate of the cost of this work. Therefore, the insurer must obtain a new quote to determine the cost of this work. The insurer should obtain an updated quote for the cost of the outstanding repairs. The quote should include the work included in the insurer’s builder’s quote of 29 January 2025, plus the above work. The insurer should pay the complainant the amount of the quote, plus a 20% uplift for the transfer of risk due to cash settlement. 2.3 Is the insurer required to pay other compensation? Yes. The insurer caused delays from 26 June 2024 to 19 March 2025. The complainant has not shown these delays caused any financial loss. However, the delays caused stress and inconvenience. The insurer must pay $5,000 compensation for non-financial loss. Insurer responsible for delays from 26 June 2024 The complainant had her own builders working on the property before the storm on 25 December 2023. According to the insurer’s notes, and the insurer’s builder’s first report, the complainant initially said she wanted the insurer to pay a cash settlement so she could get her own builders to repair the storm damage. On 23 February 2024, the complainant emailed the insurer saying she had not decided whether she wanted the insurer to pay a cash settlement or repair the storm damage. On 18 March 2024, the complainant said she wanted the insurer’s builder to repair the storm damage. On 10 April 2024, the complainant said she did not want repairs to start until she arranged NDIS (National Disability Insurance Scheme) upgrades to the house. On 28 May 2024, the complainant emailed the insurer and said: ‘we would like the repairs to start now as the NDIS is most likely going to take too long to get started’. The insurer’s builder said it would start repairs on 26 June 2024. This was delayed to 26 August 2024. The insurer did not explain this delay. On 26 August 2024, the builder said it could not repair the pool house and patio roofs because they were underpitched. The builder said these aspects of the claim would have to be cash settled. There is no record of the insurer informing the complainant of this, despite the complainant repeatedly asking when the work would be finished. On 20 November 2024, the insurer called the complainant. According to the insurer’s notes, the insurer told the complainant about ‘the LQ [liability quote; a quote for cash settlement] for the pool house and patio’. This means the insurer said it was offering a cash settlement for the pool house and patio. However, it is not clear whether the insurer said it was insisting on a cash settlement for these items (i.e. refusing to repair the items). In my view, the insurer and/or its builder were responsible for delays from 26 June 2024 because they: · delayed the start of repairs from 26 June 2024 to 26 August 2024 without explanation · did not realise before 26 August 2024 that the pool house and patio roofs were underpitched · did not tell the complainant that they would not repair the pool house and patio roofs. Insurer not responsible for delays from 19 March 2025 On 9 January 2025 and 24 February 2025, the insurer offered to pay the cost of the outstanding repairs (including repairs to the pool house and patio roofs). It did not say it was refusing to complete the repairs. On 14 March 2025, the complainant wrote to the insurer demanding a ‘lump sum settlement’ of $310,000. On 19 March 2025, according to the insurer’s notes, the complainant said she was seeking a cash settlement and was not seeking to have the insurer complete further repairs. On 1 April 2025, the complainant lodged this AFCA complaint. In her submissions to AFCA, the complainant sought a cash settlement and did not seek to have the insurer complete further repairs. On 21 August 2025, the complainant said she did not want the insurer’s builder to return to her property, either to complete further repairs or to perform inspections. From at least 19 March 2025, the complainant knew, or should have known, that the insurer was not going to complete any further repairs. From this point, arranging repairs was the complainant’s responsibility, not the insurer’s. The insurer is not responsible for any delays in repairs from 19 March 2025. Insurer not required to pay for potential liability On 10 December 2024, the local Council issued the complainant a ‘show cause notice’ saying the boundary fence and adjacent pool house were in a dilapidated condition. The notice said the Council believed the complainant should be issued an enforcement notice, and contravening an enforcement notice could result in legal costs and fines. On 31 July 2025, the Council emailed the complainant saying it intended to issue an enforcement notice. On 3 November 2025, the complainant said the boundary fence was still not repaired and the Council had not taken any enforcement action. The complainant says she is at risk of receiving enforcement notices and fines from the Council due to the insurer’s delay in repairing the property. She says the insurer should pay compensation of $50,000 to $130,000 for the potential costs of being issued with enforcement notices. She says she is also at risk of being sued if someone is injured by the dilapidated structures on her property. The insurer is not required to pay compensation for any liability incurred by the complainant due to the delay in repairs, because: · the complainant has only said she is at risk of incurring liability. She has not provided information showing she has actually incurred any liability or cost · as stated above, the insurer is not responsible for any delays in repairs from 19 March 2025. Settlement covers increases in building costs Under the AFCA Rules, we can award up to $6,300 compensation for indirect financial loss. The complainant says the delay in repairing the property will increase the cost of repairs because building costs have risen over time. She says this is an indirect financial loss the insurer should compensate her for. This determination requires the insurer to obtain a new quote and pay a settlement based on that quote. Therefore, the settlement will be based on current building costs. The insurer is not required to pay compensation for any increase in building costs over time. Insurer must pay compensation for non-financial loss Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. The complainant says she suffered stress due to the insurer’s lack of communication and delays in repairing her property. She says the delays have been particularly stressful because her partner is disabled. The delays in repairing the property have prevented him using the pool and sauna for physiotherapy, severely impacting his physical and mental health. The insurer admitted it was responsible for some delays, and this caused the complainant an unusual degree of inconvenience because she was unable to use parts of her property. As stated above, there were delays the insurer was not responsible for. However, the insurer was responsible for delays from 26 June 2024 to 19 March 2025. I am satisfied these delays caused the complainant to suffer an unusual degree of stress and inconvenience. In my view, this warrants compensation of $5,000. 2.4 Why is the outcome fair? The parties have agreed that the insurer will settle the remainder of the claim by paying a cash settlement (rather than by arranging further repairs). I am satisfied that the method set out in this determination is the best way to determine a fair settlement sum. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.