Determination 12-25-220022

Extent of insurer's liability for remediation of storm and contractor-caused damage, including tree removal and replacement, and non-financial loss

FirmHollard
Decided2025-05-26
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$82,495
Non-financial loss$6,300
Amount claimed$825,577
SourceAFCA PDF

Summary

After storm damage and further damage by the insurer's trades, the parties could not agree on the final settlement. AFCA preferred the complainants' remediation method, ordered payments for remediation, tree removal and invoices with interest, a process for tree replacement costs, and $6,300 non-financial loss.

The insurer's obligation is to return the complainants to their pre-damage position, and the complainants' arborist evidence was preferred over the insurer's uncertain desktop report, with delays by the insurer justifying maximum non-financial loss.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interestpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-220022 | Financial firm | Hollard Insurance Partners Limited Case number: 12-25-220022 22 May 2025 Determination overview Complaint The original claim arises following a storm on 27 July 2022, causing damage to the house and some trees on the property. The insurer accepted that claim and commenced repairs. It is accepted that further damage was caused by the insurer’s trades, to a dam wall, during the initial repairs. The issues arising from this complaint have been the subject of a previous Determination (dated 3 April 2024) and a Supplementary Determination (dated 6 September 2024), both were issued under complaint number 963884. The parties have been unable to agree on the extent of the insurer’s liability to the complainants, regarding the claim. Issues and key findings The insurer is required to meet its obligations to the complainants by complying with the provisions of this determination. Is the insurer liable to pay compensation for non-financial loss? Yes. The insurer is to pay $6,300 in compensation for non-financial loss. Why is the outcome fair? The outcome is fair as it is consistent with the exchanged information and the obligations of the insurer under the policy, regarding the claim. Determination This determination is in favour of the complainants. The insurer is to comply with the provisions of this determination. Reasons for determination What is the insurer’s liability for the damage? The Supplementary Determination detailed: Both parties are to review their positions and unless there is a compromise: The insurer is required to pay the complainant the full sum of the scope of works they commissioned plus a 20% uplift, a total of $112,485.53. The insurer‘s offer in this amount was received by AFCA on 1 August 2024. I acknowledge the offer includes an uplift of 20% for contingencies. This is fair and appropriate. This payment is to be made within 7 days of acceptance by the complainant. I am satisfied that the $112,485.53 is the minimum amount the insurer is prepared to pay to resolve this complaint. The insurer is required, within 21 days of the complainant accepting this determination, to re-attend and re-assess the property for all outstanding damage and provide a new scope of works and quote for repairs. I am satisfied that this requirement accords with the previous determination. The complainant may provide any independent quote, scope of works or estimate for repairs within 21 days of the update from the insurer regarding the scope of works and/or any offer of settlement. If the parties cannot reach an agreement as to the final amount of payment, the complainant is required to lodge a new complaint with AFCA or pursue any issues in another forum they may think appropriate. This is the full and final determination of AFCA complaint 12-00-963884. The parties have not reached agreement as to a final amount of payment. The complainants have provided an updated settlement statement in the amount of $825,577 (from which $112,485.53 is to be deducted – being the amount paid by the insurer in accordance with the Supplementary Determination). The complainants’ settlement statement includes $175,824, being the quotation (dated 12/09/2024) for the scope of works for remediation, $4,345, being the invoice for preparation of the Scope of Works and quotation, $633,188, being the valuation of the four trees requiring replacement, $2,310, being the invoices for tree valuation and $8,910, being the quotation (dated 18 September 2024) for tree removal. While the Scope of Works quotation does not account for the removal or replacement of trees, the report confirms the requirement for the removal of four trees in the work zone. The Scope of Works also confirms that the complainants will remove the trees prior to the repair work commencing. The insurer says that its final assessment is based upon a revised method of remediation, which includes hand digging and labour, and does not involve heavy machinery or the need to remove trees. The final Scope of Works relied upon by the insurer, dated 25/02/2025, is $131,400. This amount does not account for the removal of trees given the revised method of repair now proposed by the insurer. The insurer’s view is that the correct full settlement amount is $181,735, which includes: $112,485.53, already paid following the Supplementary Determination, A 35% contingency, added to the cost of remediation, and An invoice for Central Coast retaining walls, $4345. The exchanged material confirms that the insurer was prepared to increase its offer to a final payment of $73,549.47. This includes a further payment of Non-Financial Loss Compensation, of $4,300. It is clear to me that the fair and reasonable settlement amount depends upon the appropriate repair method. Expert Reports The complainants have submitted a report from a Tree Consultant (AIA), who has qualifications in Horticulture and Arboriculture. AIA attended on site on 17 September 2024 and has provided a report (dated September 2024) which includes his methodology and helpful diagrams, charts and photographs. In assessing the excavation required to replace the existing retaining wall, AIA relied upon a Scope of Works prepared by the insurer’s building consultant (SE), dated 24 July 2024. The conclusion of AIA was that four trees would be impacted, given the proposed repairs would result in a major encroachment (≥35%) into the Tree Protection Zone (TPZ) and Structural Root Zone (SRZ). TPZ is the area that protects the above and below ground parts of a tree. The SRZ is the area required for tree stability. AIA says according to the Australian Standard Protection of trees on development sites (AS 4970), encroachments of less than 10% are considered minor and acceptable. AIA says that no specifications are provided within AS4970 for encroachments greater than 10% and it is the consulting arborist that must investigate if the tree will remain stable and viable. In AIA’s view, the required excavation will represent a major encroachment (≥35%) into the TPZ & SRZ of all four trees. AIA considers this a significant level of impact that is not tolerable for the species, trees stability and viability will be compromised. The volume of root mass lost would result in the trees being assessed as a high probability of failure and an unacceptable risk of harm to people or structures. AIA recommends the four trees for removal as part of the repair process and replacement of the trees following completion of repairs. At an earlier stage of the claim, the insurer engaged an arborist (TW) but I am satisfied that he did not address (through no fault of his) all the issues which are now under consideration. The insurer engaged a qualified senior consulting arborist (AN), who conducted a desk top assessment and provided a detailed report dated 19 February 2025, which includes several helpful photographs of examples of work done at other locations. I accept that the insurer requested permission for AN to attend on site. I also accept that the on-site assessment was refused as the complainants felt enough time had passed since the storm loss event (27 July 2022) and given their ongoing concern of further damage, in the absence of proper repairs, they wanted the insurer to make a decision based on the exchanged information available at that time. I note that this was not the first time the complainants had expressed concern about delay. Within their email of 4 April 2024, to the insurer, the complainants raised issues with the delay, the need for a proper Scope of Works and their intention to have an arborist reattend on site. Within their email of 16 June 2024, to the insurer, the complainants expressed concern that nobody had attended on site to prepare a Scope of Works. Within this email, the complainants spelt out the ongoing difficulties with the site and their ongoing availability to accommodate an attendance. Importantly, the complainants spelt out what they saw as the purpose of the site visit, that is, to properly identify all challenges the site raises. Within its Scope of Works dated 24 July 2024, prepared at the request of the insurer, and relied upon by AIA, SE confirmed the need to remove four trees. Whilst the insurer, within an email of 30 September 2024, says that the need to remove trees is newly presented information, that statement is not supported by SE’s Scope of Works. The complainants confirms that they provided the insurer with a copy of the AIA report, their Scope of Works, quotation, tree guide, valuations and settlement documents, when the insurer’s various representatives attended onsite on 26 September 2024. I am satisfied that likely as early as July 2024 (and potentially earlier) and certainly no later than 26 September 2024, the insurer was aware of the complainants’ proposals for remediation. The insurer was also aware of the complainants’ engagement of an arborist, well prior to those dates. However, the exchanged material confirms that the insurer only first requested permission for the onsite attendance of an arborist on 23 December 2024. I am satisfied that generally an expert report based upon an onsite attendance, is preferable to a desk top review. However, this does not mean that it is appropriate to simply dismiss the report of AN and its conclusions. The conclusions of AN must be considered together with all other available information. As in all AFCA complaints, it becomes a question of what weight to give to a particular piece of evidence and reach a conclusion on the balance of probabilities. The extended delays created by the insurer lead me to the conclusion that it would not be fair to now allow the insurer to arrange an onsite inspection by its arborist. On the other hand, I have carefully reviewed AN’s desk top assessment. In my view, RN’s report is full of uncertainties and possibilities (all highlighting is my own): While it should be obvious that Tree 6 is unlikely to have its health significantly impacted by the proposed works.... It means that the loss of a third of all the roots all the way to the trunk is unlikely to result in any real or perceivable impact on a tree other than perhaps the formation of a basal cavity. (from a quotation) Growth reduction and unacceptable appearance from root severance can be of relatively short duration if the tree has strong vigour and vitality.... Based on the information provided, it appears that taking reasonable steps to retain and care for the two Ironbarks is more appropriate than removing them. It is within the capacity of the trees to tolerate the root loss described. In addition, there are options available to ensure that the trees do not pose a risk as a result of the work. If the trees are removed, their survival is impossible. However, if they are retained, the worst-case scenario is their gradual decline, potentially requiring removal in the future.... In the event that something arises and Tree 2 or 4 needs to be removed, I cannot accept the planting recommendations contained in 6.2.5. Regardless of the ecological status of the site, the ideal tree to replace either of these trees with is a tree of the same species. If space is a concern, then the next choice would be another Cabbage Palm (Livistona australis). Because the two Ironbarks can’t be replaced, a valuation may be required if these trees need to be removed.... Having carefully reviewed its report, I cannot be confident of AN’s conclusion that the four trees do not require removal as part of the remediation process. There is far too much uncertainty within AN’s report to reach that conclusion on the balance of probabilities. In this regard, RN notes AIA’s comment that, “the situation is too complex”. I also note that AIA confirmed a high probability of failure of the trees and an unacceptable risk of harm to people and structures. Given the exchanged information, I prefer the conclusions of AIA as to the method of remediation and that the four trees require removal. The result is that I prefer the complainants’ estimate for remediation ($175,824, albeit that it is now out of date), together with the estimate for tree removal (which is also out of date). Replacement of the four trees The complainants have presented tree valuation worksheets from AIA, for the four trees that require removal: Tree 2 (T2), $174,943, (dated 19 December 2022), Tree 4 (T4), $175,871, (dated 12 August 2024), Tree 5 (T5), $141,187, (dated September 2024) and Tree 6 (T6), $141,187, (dated September 2024). Total $633,188. I note the original determination, (963884 – 3 April 2024) detailed: TW (the insurer’s appointed arborist) agreed that the Thyer Tree Valuation Worksheet used for the eucalyptus tree (T2) is fair and reasonable, based on the data collected by MVM of BTC (the complainants’ arborist), also a level 5 arborist. The panel therefore accepts that the tree has been correctly valued at $174,943. AIA has used what is known as the Thyer method of valuation, but RN says that this method is inappropriate and was not intended for use with palms (trees, T5 and T6). Further, RN says that AIA has made substantial errors in using the Thyer valuation method, importantly not informing of how the tree dimensions were determined. Within its report RN, advises that several valuation options exist, and these include the use of the “net present value” or the “Trunk Formula Technique.” RN prefers these valuation methods. RN says that the cost of buying and planting a replacement palm is only a fraction of the valuation provided. RN expresses similar and other concerns regarding the gum trees (trees, T2 and T4). The issue to be resolved is what is the basis on which the complainants’ claim for the four trees is to be resolved? The complainants’ Home Insurance policy details: How we settle a claim Building, Contents and Portable Contents claims If we pay your claim we will, in consultation with you: • repair your damaged property where it is practicable and economical to do so; • replace your lost or damaged property where it is not practicable and/or economical to repair it; or • pay you the value that fairly represents your loss, in the form of cash or a pre-paid store card*, up to the relevant sum insured stated on your current Certificate of Insurance. However, the insurer’s obligations to the complainants arises not from the policy terms and conditions, but from the damage caused by the insurer’s trades, when they were carrying out work required because of the insurer’s obligations under the policy. This means that the insurer’s obligations are not limited to the terms and conditions of the policy. Rather, the insurer is required to return the complainants to the position they were in prior to the damage caused by the insurer’s trades. Whilst the policy terms and conditions are not technically applicable, I am satisfied that it is fair and reasonable that the insurer is required to cash settle the complainants the amount that fairly represents the loss, being the cost to replace the four trees. I am not convinced that the valuations for the trees presented by AIS, represents the value of the loss, which in my view is the cost to the complainants of replacing the four trees. In addition, having considered the exchanged information, I am not satisfied I am able to accurately say what the cost is for the replacement of the trees. Whilst I am reluctant, I think it necessary that there be further exchange. Outcome Within 14 days of notification of the complainants’ acceptance of this determination, the insurer is to: Pay the complainants $63,338.47, being the difference between the complainants; quotation ($175,824) and the payment already made by the insurer ($112,485.53), Pay the complainants an additional amount of $22,168.47, which represents a 35% uplift for contingencies, on the balance of the complainants’ scope of works for remediation ($63,338.47), Pay interest, in accordance with the Insurance Contracts Act,1984, (the Act) on $84,506 (being the balance of $63,338.47, plus the uplift of $21,168.47), from the date the $112,485.53 was paid, until the payment of the balance, Pay the complainants $6,655 for the invoices claimed, together with interest in accordance with the Act, on the $6,655, from the date the invoices were paid until the date of payment (the complainants are to provide evidence of payment of the invoices), Pay the complainants the tree removal quotation in the amount of $8,190, plus a 35% uplift for contingencies, making a total of $11,056.50, together with interest on this amount, in accordance with the Act, from 18 September 2024, until the date of payment. I note that within its final offer, the insurer included an uplift of 35% for contingencies. In normal circumstances, I would not include an uplift of this amount. However, I note that the insurer says that 15% of the uplift is for tree bracing during works, not yet costed. Given the passage of time and the fact that this is the third determination, whilst I am reluctant, I feel I must request further steps, to reach a fair and reasonable conclusion. I ask the parties to actively engage with each other to comply with the terms of this determination. Within fourteen days of acceptance of this determination, by the complainants, the insurer is to provide a list of three suitably qualified experts, who have not previously been involved in the claim or complaint(s). The complainants are to select one from the list. Within 14 days of notification of the complainants’ selection, the insurer is to arrange for the suitably qualified expert to attend on site at the insurer’s expense and provide an actionable quotation for the replacement cost of the four trees, including transport, planting and associated costs. I acknowledge that it is unlikely the four trees can be replaced like for like. The expert must factor in and account for any differences from like for like, such as age, height, width and other relevant dimensions. The complainants are to cooperate with the site attendance of the appointed expert, at what is a convenient date and time for both parties. On receipt of the quotations, the insurer is to cash settle the complainants the quotation amount, together with a 15% uplift for contingencies. Is the insurer liable to pay compensation for non-financial loss? AFCA can award compensation for non-financial loss Under AFCA’s Rules, we may award compensation (capped at $6,300) for non-financial loss where complainants have suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, we adopt a conservative approach to the award of compensation for non-financial loss. We expect complainants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. Moreover, non-financial loss is not intended to be a punishment for any wrongdoing on the part of the insurer The insurer previously paid the complainants non-financial loss compensation of $2,000, in accordance with the Supplementary Determination. As part of its final offer, the insurer says because of the inconvenience suffered by the complainants, it has included an additional $4,300 non-financial loss compensation “to align with AFCA’s jurisdictional limit (a total of $6,300).” If the insurer is saying that the $2,000 non-financial loss compensation paid for the previous complaint, forms part of the jurisdictional limit of this complaint, I do not agree. This is a new complaint, and my consideration of non-financial loss compensation will be regarding the events that have occurred since the Supplementary Determination and will have its own separate jurisdictional limit of $6,300. Complainants suffered stress and inconvenience I have detailed above my concern regarding delays created by the insurer. I do not intend to repeat those concerns here. That said, I am satisfied that the complainants have suffered significant stress and inconvenience because of these delays. The exchanged material confirms that the insurer agrees. As stated, the insurer has offered the complainants an additional $4,300 by way of non-financial loss compensation. Having reviewed the exchanged material, I am satisfied that is fair and reasonable and within 14 days of the complainants’ acceptance of this determination, the insurer is to pay $6,300 to the complainants, being the maximum payable within AFCA’s jurisdiction. Why is the outcome fair? The outcome is fair as it is consistent with the exchanged information and obligations of the insurer under the policy, regarding the claim. Supporting information The AFCA process AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.