Home / Hollard / Determination 12-25-219086
Determination 12-25-219086
Cash settlement amount for water damage repairs and compensation for claim delays
Summary
The insurer initially denied a shower drain water damage claim, then accepted it and offered a cash settlement of $15,938.95 plus $2,000 compensation. AFCA increased the uplift to 40%, requiring payment of $17,165 plus $2,000 non-financial loss.
Cash settlement must reflect the reasonable cost of repair, so the insurer's correctly scoped quote was the base with a 40% uplift for location, age and risk, while the $2,000 offered for delays was fair.
Issues
- Claim amount dispute primary · upheld“insurer's quote is reasonable starting place but an uplift of 40% is justified; pay $17,165”
- Claim denial secondary · upheld“insurer initially denied the claim as long-term seepage, then overturned its decision after AFCA preliminary assessment”
- Delay secondary · upheld“there were unreasonable delays in the assessment process (including the provision of the reports)”
- Poor communication secondary · upheld“communication from the insurer's agents was not always clear or consistent”
Subjects and remedies
home or building damagepay claimpay non financial loss
Related
Text of the determination
Determination
|
Case number
|
12-25-219086
|
Financial firm
|
Hollard Insurance Partners Limited
Case number: 12-25-219086 29 October 2025
1 Determination overview
1.1 Complaint
The complainant lodged a claim for water damage caused when his shower drain became blocked in January 2025. The insurer initially denied the claim, saying the damage was caused by long-term seepage and wear and tear, not a sudden escape of liquid.
Following the AFCA preliminary assessment, the insurer overturned its decision and accepted the claim. The insurer offered to settle for $15,938.95 (being the builder's quote of $12,260.73 plus 30% uplift). It also offered $2,000 for non-financial loss compensation on account of claim delays.
The complainant rejected this offer. He says his builder's quote is $23,000, which reflects current Alice Springs pricing, and the insurer's offer (based on a Queensland builder's quote) does not account for the higher costs in the remote location.
1.2 Issues and key findings
Must the insurer increase its settlement offer?
Yes. The insurer’s quote is a reasonable starting place for determining liability. It most accurately sets out the proper scope of works. The complainant’s quote includes the cost of matching flooring in different rooms, which is not covered by the policy. The insurer’s quote is also more transparent.
However, the insurer’s quote is not actionable and not based on a physical inspection of the property. The insurer says it cannot authorise repairs. The quote does not account for the likelihood of increased costs in Alice Springs. It is also aged. In cash settling, the complainant takes on risks of increased costs. For these reasons, an uplift of 40% is justified.
Is the complainant entitled to additional compensation?
No. The insurer was responsible for unreasonable delays and communication issues during the claim. However, its offer of $2,000 is fair compensation in the circumstances.
Why is the outcome fair?
The insurer’s quote is the most reasonable starting place for determining the extent of the insurer’s liability, but the actual costs of carrying out the repairs at the complainant’s location will probably be significantly higher. The final amount awarded fairly accounts for this.
1.3 Determination
This determination is substantially in favour of the insurer. If the complainant accepts the determination, then, within 14 days of being notified, the insurer must:
· pay the complainant $17,165 (being: $12,260.73 for the builder’s quote, plus $4,904.29 for the 40% uplift)
· pay the complainant $2,000 in compensation for non-financial loss.
2 Reasons for determination
2.1 Must the insurer increase its settlement offer?
Cash settlement must reflect reasonable cost of repairs
The insurer has elected not to authorise repairs. It has decided to cash settle its liability.
Under the terms of the policy, the insurer may settle a claim for damage to the complainant’s property by:
· repairing the damage, or
· paying the complainant the reasonable cost of doing so.
Where a claim is to be settled by a cash settlement, the insurer is required to pay the complainant the reasonable cost of repairing the damage to the property. This means the cash settlement amount should be sufficient to ensure that the complainant is able to engage his own contractors to complete the necessary repairs.
Complainant’s quote goes beyond the required repairs
The complainant’s builder’s quote goes beyond the scope of works necessary to address the damage due to the insured event. It includes work of removing, disposing and replacing flooring in the main bedroom, the hallway and the living area. Only the main bedroom was damaged by the insured event, but the builder says the flooring in the other rooms is to be replaced in order to achieve a match.
The policy does not cover the matching of flooring in the additional rooms. In this regard, the insurer has correctly referred to page 43 of the product disclosure statement (PDS), which says:
Matching Benefit
What is covered
This benefit can only be used to match materials in the immediate area where the damage occurred. It does not extend to other rooms or areas of the home that are undamaged.
There is no dispute the main bedroom is the immediate area where the damage occurred and that the other rooms are separate and undamaged. The complainant has not provided information to establish otherwise.
I also note the builder’s quote does not include an itemised breakdown of costs for labour and materials.
The builder’s costs are not transparent. And they include substantial work not covered by the policy.
For these reasons, I do not consider the quote a reliable reflection of the fair repair costs.
Insurer to base settlement on its quote, but include 40% uplift
I need to be satisfied the proposed cash settlement is sufficient to repair the damage for which the insurer is liable under the policy.
The insurer’s quote is itemised and based on the correct scope of works. It is a reasonable starting point for determining liability.
However, there are a number of things about it that strongly suggest it is not, as it stands, a fair representation of the actual cost of repairs. In particular:
· it is not actionable for the complainant at his location in Alice Springs
· the insurer is not prepared to authorise repairs based on the quote
· it is unclear whether the amounts for labour and materials reflect actual market rates available to consumers or discounted rates available to the insurer
· it is not based on a comprehensive physical inspection of the property
· the quote does not account for the likelihood of increased costs in Alice Springs. The complainant submits the costs are likely to be substantial, and the insurer has not refuted this
· the quote is dated 19 March 2025, now over 7 months old.
I also note that, in cash settling the claim, the insurer transfers to the complainant the risk of any necessary variations in the work, and the complainant loses the benefit of the insurer-backed lifetime guarantee on repairs.
To account for these matters, I consider it fair in the circumstances the insurer adds an uplift of 40% to its builder’s quote to settle the claim.
If the complainant accepts the determination, the insurer must pay the complainant $17,165 for the building repairs under the claim (being: $12,260.73 for the builder’s quote, plus $4,904.29 for the 40% uplift).
The insurer is not required to pay interest on the settlement sum. This is because the complainant has not yet incurred the repair cost and the uplift I have awarded accounts for any likely increase in costs since the quote was originally drafted.
2.2 Is the complainant entitled to additional compensation?
No. The insurer was responsible for unreasonable delays and communication issues during the claim. However, its offer of $2,000 is fair compensation in the circumstances.
AFCA can award compensation for non-financial loss
Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim.
We will not award compensation for the usual amount of inconvenience involved in making a claim. We will not award compensation for delays caused by a complainant, or other factors outside the insurer’s control.
Insurer mishandled the claim, but its compensation offer is fair
The complainant says the insurer mishandled the claim, including by unreasonable delays and communication issues.
Having reviewed the available information, including the claim file notes and submissions, I note the following:
· there were unreasonable delays in the assessment process (including the provision of the reports)
· the insurer’s agents were not proactive or consistently responsive in their communications with the complainant
· the insurer’s builder did not physically attend the property, which the complainant was frustrated with
· the communication from the insurer’s agents was not always clear or consistent.
However, other delays in the claim were reasonable, given the nature of the claim and the location of the property.
I am satisfied the insurer mishandled the claim and this caused the complainant undue stress and inconvenience. However, I consider the $2,000 offered by the insurer is fair in the circumstances. No further compensation is warranted.
2.3 Why is the outcome fair?
The insurer’s quote is the most reasonable starting place for determining the extent of the insurer’s liability, but the actual costs of carrying out the repairs at the complainant’s location will probably be significantly higher. The final amount awarded fairly accounts for this.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.