Scope and amount of cash settlement for storm damage repairs

FirmBlue Zebra
Decided2026-06-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$89,799
Non-financial loss—
Amount claimed$198,573
SourceAFCA PDF

Summary

The complainant's home was storm damaged and he sought $198,573.21 for repairs he had completed. AFCA found the insurer's cash settlement mostly fair, increased it for roof area and mould tests to $89,798.97 plus interest, and refused non-financial loss.

The insurer is liable only for storm-related damage, and the complainant did not show the extra works were claim-related; a cash settlement must be based on reasonable quotes for claim-related repairs, plus an uplift.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Blue Zebra determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-217311 | Financial firm | Blue Zebra Insurance Pty Ltd Case number: 12-25-217311 28 May 2026 1 Determination overview 1.1 Complaint The complainant has home and contents insurance (policy) with the financial firm (insurer). In September 2024, the complainant’s home was damaged in a storm. The complainant lodged a claim in October 2024. The insurer accepted the claim and assessed the damage from the storm. The complainants undertook repairs to the property. The insurer says that much of the repairs were to fix damage not caused by the storm. Therefore, the insurer offered a cash settlement based on the quotes it obtained to repair the storm damage. The complainant seeks payment of all of the costs he incurred to repair the property. 1.2 Issues and key findings Is the insurer’s offer fair? The complainant has not shown that his claim for repairs related only to damage caused by the storm. The insurer has shown that its offer of settlement was based on quotes to repair the damage caused by the storm. The insurer has shown that the quotes were reasonable and actionable. The insurer‘s cash settlement offer is fair and reasonable aside from an amount for additional mould testing and to address the amount under quoted to repair the damaged roof. Is the complainant entitled to compensation for non-financial loss? No. The insurer did not mishandle or unreasonably delay the claim. The complainant has not shown that it is fair that the insurer compensate him for non-financial loss. Why is the outcome fair? The outcome is fair because the insurer is only liable for claim-related damage. The insurer is not obliged to cover the cost of non-claim related damage and works. The insurer’s offer is fair and in accordance with the terms of the policy. 1.3 Determination The determination is substantially in favour of the insurer. If the complainant accepts this determination then, within 14 days of being notified of the complainant’s acceptance, the insurer must pay the complainant the sum of $89,798.97, plus interest calculated in accordance with the comments in section 2.1. 2 Reasons for determination 2.1 Is the insurer’s offer fair? The complainant has not shown that his claim for repairs related only to damage caused by the storm. The insurer has shown that its offer of settlement was based on quotes to repair the damage caused by the storm. The insurer has shown that the quotes were reasonable and actionable. The insurer‘s cash settlement offer is fair and reasonable aside from an amount for additional mould testing and to address the amount under quoted to repair the damaged roof. Policy covers accidental damage The terms of the policy are set out in the policy schedule and the product disclosure statement. There is no suggestion that those documents were not provided to the complainant and I accept that the insurer can rely on the terms of the policy. Subject to exclusions, the policy covers the complainant for accidental damage to the building. The complainant has the onus of establishing he suffered a loss from an event covered by the policy. If a claimable loss is established, the insurer then has the onus of establishing the application of any exclusion or condition it relies on to deny or reduce its liability. For both the complainant and the insurer, the onus of proof is the balance of probabilities (that is, it is more likely than not). Scope of determination Both parties accept that the storm has caused damage to the complainant’s property. Accordingly, the complainants have established a claimable loss. During the course of the complaint, the parties also raised issues about water entering into the ground floor of the property around the front door, and in the rumpus room. The complainant also seeks cover for damage caused to the contents at the property. The claim regarding these issues is still ongoing. Those issues do not form part of this complaint before AFCA. This determination is limited to considering the damage to the roof, and the top floor of the property. Damage caused by storm to the roof and solar panels The issue in dispute concerns the scope of the repairs that the insurer has agreed to cover. The complainant says that the insurer’s offer is inadequate. The insurer says that the work undertaken by the complainant exceeds the damage caused by the storm. The insurer says that, on the roof, 44m2 of the roof (six sheets) and two solar panels were damaged by the storm. It relies on the report provided by its roof plumber, SP, and a roofer ER, to support this. In an undated report, ER recommends that a roofing plumber be appointed to inspect the roof. ER also comments that the condition of the property is excellent and that the flashings are in ‘very good’ condition. The undated report of SP says, in summary: · a solar panel on the roof impacted the roof sheets causing damage on the roof · they recommended the damaged roofing material be removed and replaced · there is 44m2 of roofing that needs to be replaced · that two solar panels need to be replaced The SP report contains photos showing several significant creases to the metal roof, and holes to the roof which had been sealed with silicone. The reports of SP and ER contain photographs. Relevantly, those photos do not show any damage to the roof other than the obvious dents in the roof and holes that had been temporarily repaired with silicone. The complainant has provided an invoice from GG, a builder, for the works undertaken to repair the property. GG has also provided an undated letter which says that the roofing works were to replace 55.52m2 more than the 44m2 the insurer accepted. GG says that the additional roofing material and ridging flashing needed to be replaced: Due to minor scratches and dents caused by the storm event that would cause premature rusting if not replaced. The complainant has also provided a report by TB, who was appointed to inspect the water damage caused by the storm. TB’s report, dated 6 September 2024, contains several photographs showing significant holes and dents to the roof. Some of the holes have been sealed with silicone. TB also recommends replacement of the roof to prevent water ingress. The complainant has provided a letter from RP, a roofer. In an undated report, RP says that the works and flashing replacements were necessary as there were scratched flashings and sheets on the replaced panels and flashings. Having carefully considered the reports and materials, I am not persuaded that more than 44m2 of roofing was damaged, nor am I persuaded that flashing needed to be replaced. I am of this view as: · there is no photographic evidence of minor scratches and minor dents to the roof · the solar panel that came off was large and caused significant damage to the roof, if the solar panel was moved over the roof, it would have caused significant damage, not merely minor scratches · ER’s report includes photographs showing the majority of the solar panels remained intact on the roof. These intact solar panels should have protected the roof sheets to some extent and there is no evidence to the contrary. The complainant bears the onus of showing that damage to the roof was caused by the storm. Given the above, I am not persuaded that, on balance, more than 44m2 of the roof or more than two solar panels were damaged. Internal damage to the property Water entered the property through the damaged roof. The water damaged the walls, ceilings and flooring. The insurer accepted liability for this damage. The dispute is about the works needed to repair the damage to the property. The complainant’s builder GG has charged to replace 132m2 of flooring and charged for other works including straightening of walls and ceilings. The insurer says that such works did not repair damage caused by the storm and that only 29m2 of flooring needed to be replaced. The exchanged information included reports from the insurer’s loss adjuster CA. Those reports and the reports from TB shows the flooring that was damaged by the storm includes part of a bedroom and the hallway. The total area of flooring damaged looks no more than one or two square meters. The insurer’s scope of works allowed for the removal and installation of 29m2 of hybrid flooring and rubber underlay. That area is for repair of the hallway and the bedroom. The complainants’ invoice was for the removal, supply and installation of 132m2 of hardwood flooring and soundproof underlay for the hallway, bedroom and playroom. The insurer says the complainant’s decision to replace undamaged flooring was for aesthetic reasons and the policy does not respond to this. The complainant says all the flooring needed to be replaced because the type of interlocking floorboards meant a patch repair was not possible, and re-using boards would not be warrantable. The exchanged material includes letters from the original flooring supplier and the new flooring installer in support of this. Despite this, I am not persuaded that the whole flooring needed to be replaced. This is because: · the damaged area of the floor constitutes a bedroom and a hall. It is common for a timber floor to meet a carpet floor. Without more, I understand the letters from the experts to say that within a room, the whole floor needs to be replaced. This does not mean that the whole floor on a given level of the property needs to be replaced · the insurer allowed for 29m2, which allows for the removal and replacement of the undamaged floorboards within the bedroom and the hall · the complainants have not explained why 132m2 of undamaged underlay needed to be replaced. I understand the house, and therefore the underlay, was relatively new. I understand that the complainants wished to have matching flooring across the whole of the first floor. AFCA’s usual approach when matching flooring is that it will allow the costs up to the nearest architectural break. In this complaint, that is the hall and the bedroom. Therefore, the insurer’s offer to repair 29m2 of flooring which replaced the floor within the hall and bedroom was fair. The complainants’ invoice included allowances to straighten walls and ceilings in preparation for new wall sheeting. The insurer says this is an example of the complainant authorising improvement works rather than repairs. The letter from the complainant’s builder GG says the straightening of the walls is ‘non-negotiable’ as any new framing rectification requires a pack and straighten process. However, he does not explain how this work is connected to repairing claim-related damage. The damaged wall and ceiling were a relatively small area, one corner wall (bedroom and hallway) and adjacent ceiling area. GG’s invoice did not specify whether the works conducted were limited to the affected area, or whether it was for works to undamaged areas. For example, GG’s invoice includes $3,465 for stripping out and disposing plaster from walls and ceilings in the hallway/landing/playroom, hallway to bedrooms, and bedroom. However, the exchanged information shows TB removed plasterboard from the affected wall and ceiling areas. This suggests GG’s work involved non-storm damaged areas. For these reasons, I am not persuaded that GG’s invoice for internal works was solely for the repairing damage covered by the policy. The insurer is not obliged to pay these costs. Mould testing The complainants engaged EB to conduct mould testing after TB’s remediation work. EB’s report says the following samples were taken: · first floor – remediated area noggin, hallway, bedrooms 1-4 · ground floor – lower rumpus, kitchen/dining, guest bedroom, master bedroom · outdoor reference sample. The complainant seeks reimbursement for the cost of 10 mould samples (all samples excluding the rumpus room). The complainant provided a letter from building biologist EB, which explained samples were taken from the remediated area, adjacent areas, and downstairs as TB would have removed materials through the front entrance. This was to ensure no cross contamination occurred. An outdoor reference sample was also taken to compare indoor results. The insurer’s cash settlement offer is for six samples – 1st floor kids’ bedrooms 1 and 2, bedrooms 3 and 4, 1st floor remediated hallway, and lower rumpus. The insurer based this on the scope and location of water ingress and removal of mould/moisture-damaged materials by TB. It says further testing of adjacent areas requires ‘evidence of significant cross contamination risks’ and there is none in this case. I am not persuaded it is necessary for the insurer to cover the cost of additional ground floor mould samples. The information available shows TB remediated mould and moisture affected areas. EB’s report says the remediated area was well contained and there was good containment in place at the doors of the adjacent bedrooms. There is nothing to suggest TB failed to take appropriate care to prevent cross-contamination when removing affected materials from the house. Given this, I accept the insurer’s position that there is nothing show significant cross contamination occurred, and therefore no need for additional samples. However, I accept the surface sample from the remediated noggin, and the outdoor sample to obtain a baseline reference were necessary. It follows that the insurer should cover the cost of eight samples – the six it has accepted, the surface noggin sample and outdoor air sample. Insurer’s offer is mostly fair The insurer accepted the claim and offered to cash settle for $67,762.09. This consisted of repairs (roof and solar panels $25,714.04, internal $33,186.52), remediation works ($13,147.74) and mould testing ($2,490), less GST ($6,776.21) and excess ($1,000). The insurer subsequently offered a 20% uplift to resolve the complaint. The complainants rejected the cash settlement offer and uplift. They seek payment of $198,573.21 (builder’s invoice of $181,190.47, remediation $13,147.74, post-remediation mould testing $4,235). As discussed above, GG’s invoice included the costs to repair items not damaged by the storm. The invoice also includes $4,620 for accommodation and travel expenses and a further $3,100 to build packing crates for transport of PV panels to site. I accept that GG’s invoice includes costs that do not relate to damage caused by the storm. I am not persuaded that the costs set out in GG’s invoice are reasonable. The insurer’s quote to repair the roof was prepared by a builder, SG. SG’s quote to repair the roof was for $25,714.04 and included replacing ‘30m3’ of roofing panels. I assume this is a typo and should be a reference to 30m2. However, the quote was for less than the 44m2 of damaged roof sheeting, this is not fair. SG’s quote for roofing was $6,626.40 for 30m2, which is $220.88 per m2. Therefore, the quote should be increased by $2,208.80 to reflect the 44m2 of roof panels that were damaged. SG also prepared the quote to repair the internal damage to the property. SG was willing to undertake the repairs to the roof and internally. A cash settlement must be based on a reasonable quote for claim-related repairs, actionable by a retail customer. An uplift can be applied to the quoted amount to allow for contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs. The insurer offered a 20% uplift to its quote to resolve the complaint prior to determination. On balance, I accept that this offer is fair. In the circumstances, it is fair that the insurer should pay the sum of $89,798.97 to the complainant, calculated as follows: · $33,186.52 SG’s quote to repair the bedroom and flooring · $25,714.04 SG’s quote to repair the roof sheeting and solar panels · $11,780.11 being a 20% uplift of SG’s quotes · $2,208.80 being the increase to allow SG’s roofing quote to cover the 44m2 · $441.76 being a 20% uplift on the increase to SG’s quote · $3,320 – allowance for 8 tests · $13,147.74 being TB’s invoice Relevantly, when the insurer put forward the offer of settlement, it reduced the offer by GST. One of the insureds is a company and presumably registered for GST. AFCA has not been provided with sufficient information to determine whether the insurer is entitled to reduce the offer for GST. The parties will need to work together to determine if the insurer is acting in accordance with the terms of the policy or not. Any payment made by the insurer in accordance with this determination can be adjusted in accordance with the provisions of the policy to reflect the GST status of the insureds, and any outstanding excess payable. Interest From 18 March 2025, the insurer had sufficient information to settle the claim. In the circumstances it was unreasonable for the insurer to withhold payment of the amount it offered. Pursuant to section 57 of the Insurance Contracts Act 1984 (the Act), the insurer must pay interest on the sum of $77, 577.10 (being the aggregate of the quotes and invoices). Interest is payable from 18 March 2025 until the date of settlement. 2.2 Is the complainant entitled to compensation for non-financial loss? No. The insurer did not mishandle or unreasonably delay the claim. The complainant has not shown that it is fair for the insurer to compensate him for non-financial loss. AFCA can award compensation for non-financial loss in certain circumstances Under the AFCA rules, non-financial loss compensation (capped at $6,300) may be awarded in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, non-financial loss is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer. Insurer did not mishandle the claim The complainant raised concerns about claim delays and poor communication. The complainant says the property was repaired without waiting for insurer approval because of the delays and the need to protect the house from further damage. The complainant seeks compensation for stress and inconvenience, and loss of rent. I have carefully reviewed the exchanged information. I am satisfied, on balance, the insurer did not mishandle or unreasonably delay the claim. The complainants lodged the claim on 17 October 2024. The insurer arranged assessments by roofer ER on 24 October 2024 and by its panel builder on 25 October 2024. The panel builder recommended leak detection tests, which were done by SR on 19 November 2024. The complainants had conducted remediation and make safe before notifying the insurer, so there was no risk of further damage in the meantime. The complainants obtained a quote from GG dated 4 November 2024 (i.e. before SR’s assessment) for over $300,000. A later quote for $254,939.92 was provided to the insurer by 28 November 2024, who advised it would not be approved. The complainants were advised to provide a new quote for claim-related works only. By 11 December 2024, the complainants had authorised works to the property. Overall, the available information does not persuade me that the insurer’s actions inappropriately caused stress to the complainant or delayed the resolution of the claim. In regard to the complainant’s claim for loss of rent, the policy specifically excludes additional, indirect or consequential costs or losses unless these are included under the ‘Additional benefits’ or ‘Additional covers’ sections of the policy. Loss of rent is not included under these sections. Therefore, it is not covered under the policy. The complainant has not shown that it is fair that the insurer cover any claim for loss of rent. 2.3 Why is the outcome fair? The outcome is fair because the insurer is only liable for claim-related damage. The insurer is not obliged to cover the cost of non-claim related damage and works. The insurer’s offer is fair and in accordance with the terms of the policy. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.