Home / QBE / Determination 12-25-216638
Determination 12-25-216638
Alleged unreasonable repair delays after storm claim, business interruption underinsurance, and non-renewal of policy
Summary
A roadhouse operator complained about repair delays after a storm claim, underinsurance for business interruption and non-renewal of her policy. AFCA found in favour of the insurer on all issues and required no action.
Delays were mostly due to the complexity and remote location of the repairs with no proven additional loss, the insurer owed no duty to advise on sum insured, and non-renewal was consistent with underwriting guidelines.
Issues
- Delay primary · not upheld“Most delays resulted from the nature and complexity of the claim, not unreasonable conduct by the insurer or its agents.”
- Claim amount dispute secondary · not upheld“There is no basis to alter the indemnity period or the business interruption calculations.”
- Complaint handling failure secondary · not upheld“While the IDR process could have been more consultative, the substantive outcomes were not unreasonable.”
- Inappropriate advice secondary · not upheld“The insurer did not owe a duty to advise on the scope of business interruption cover.”
- Policy cancellation or underwriting secondary · not upheld“The insurer's decision not to renew the policy was reasonable and consistent with its underwriting guidelines.”
- Repairs or contractors secondary · upheld“discrete errors: fuel system works addressed late and shade sail ordered late, pushing timeline back by about one month; no material loss shown”
Subjects and remedies
broker or intermediarybusiness interruptionhome or building damagenatural disastersmall businessno remedy
Related
Text of the determination
Determination
|
Case number
|
12-25-216638
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-25-216638 13 March 2026
1 Determination overview
1.1 Complaint
The complainant operates a petrol station and roadhouse in a remote Queensland town. They hold business insurance with the financial firm (insurer) covering the property and the business.
In April 2022 the complainant claimed for storm damage. The insurer accepted the claim, appointed a builder to repair the premises, and paid $44,318 for business interruption.
The complainant says the repairs were unreasonably delayed, causing additional financial loss including deterioration of petrol bowsers and unsellable fuel. They also say the insurer failed to advise them on an appropriate sum insured for business interruption, leaving them significantly underinsured. They say the insurer's decision not to renew their policy was unfair.
1.2 Issues and key findings
Is the complainant entitled to compensation for the way the claim was handled?
No. Most delays resulted from the nature and complexity of the claim, not unreasonable conduct by the insurer or its agents. The complainant has not shown the insurer's actions caused additional financial loss.
Is the insurer responsible for the revenue underinsurance?
No. The insurer did not owe a duty to advise on the scope of business interruption cover. The complainant was responsible for ensuring adequate insurance. The insurer's agent's conduct did not shift this responsibility.
Did the insurer unfairly refuse insurance?
No. The insurer's decision not to renew the policy was reasonable and consistent with its underwriting guidelines.
Why is the outcome fair?
The insurer handled the claim reasonably overall. Its agents were not responsible for the underinsurance. The non-renewal decision was fair.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action.
2 Reasons for determination
2.1 Is the complainant entitled to compensation for the way the claim was handled?
No. Most delays resulted from the nature and complexity of the claim, not unreasonable conduct by the insurer or its agents. The complainant has not shown the insurer's actions caused additional financial loss.
Complainant says unreasonable delays caused loss
The complainant says the insurer and its agents caused significant, avoidable delay in repairing the premises. They point to problems with the scope of works, materials that were mis-ordered or not ordered, and weeks where no work occurred. They say this extended the period the business could not trade normally, causing continued revenue loss and deterioration of the petrol bowsers and fuel.
The insurer accepts repairs took longer than first anticipated. It says this was because of the complexity of the works and the remote location, not unreasonable conduct.
I have considered the timeline as a whole and the specific periods the complainant identifies.
Overall timeframe mostly due to nature of claim
The storm occurred in March 2022. Within about two and a half months, the insurer's building consultant inspected the premises and issued a scope of works. Over the next three to four months, the loss adjuster obtained a builder's quote, had it reviewed, and authorised the builder to proceed. Given the structural damage, asbestos, and the need for engineered solutions, I consider these assessments and tender stages were within a reasonable timeframe.
The builder then took several months to arrange trades and materials from distant locations. Demolition and rebuild works started on site in late January 2023. From then until around June 2023 the builder completed major structural and roofing works and progressed internal repairs.
This is a remote regional town. Multiple trades had to travel long distances and stay for extended periods. I do not consider this overall period was clearly outside what could reasonably be expected for a project of this nature. There is no independent expert opinion addressing whether the repair timeline was reasonable by industry standards.
Scope of works changes not unreasonable
The complainant says the initial scope of works was inadequate, causing avoidable changes and delays as work progressed.
I accept the scope changed after the initial assessment. As the builder opened up the structure and obtained engineering input, additional items emerged. This included structural changes to the kitchen and storage roof, and upgrades to electrical, plumbing and mechanical services to meet current standards. These added time to the project.
However, I am not satisfied these variations resulted from a careless initial scope. The original scope focused on resultant storm damage. For older buildings, it is not uncommon for further issues and code-driven requirements to emerge once works begin. I am not persuaded the consultant ought to have foreseen all later variation items at the first inspection.
The complainant has not identified a clear period where works stalled solely because the scope needed revision. Assessment, scoping, builder engagement and variations were part of an ongoing process. While the variations contributed to some delay, I do not consider it was unreasonable or the result of a negligent initial scope.
Other periods of delay not clearly unreasonable
Between early June and July 2022, the loss adjuster prepared the scope and offered a cash settlement based on a repair estimate. On 14 July 2022 the complainant rejected this and asked the insurer to manage repairs. By 26 September 2022, the adjuster had obtained and authorised an actionable building quote.
I accept that after the complainant rejected the cash settlement, it took time to obtain a quote. However, the available information does not clearly show that:
· the builder could or would have started materially earlier than late January 2023 if appointed in mid-August rather than late September, or
· any substantial part of the initial delay was solely because the insurer offered a cash settlement first.
The most significant factor in the commencement timeline was builder scheduling and logistics leading into the busy end-of-year period.
The complainant also points to delay between mid-August 2023, when handover was being discussed, and May 2024, when she signed a certificate of satisfaction.
The information does not clearly establish whether the premises was unavailable for trading throughout that entire period. Email correspondence from August 2023 suggests some outstanding items could be completed after handover while the business traded. In the absence of clearer evidence, I am not prepared to find this whole period amounts to unreasonable delay by the insurer.
More generally, some elasticity in the timeline is explained by the nature of the damage, engineering changes to the scope, and the challenges of coordinating multiple trades in a remote location. I am not satisfied that every period of inactivity or slippage was unreasonable or entirely within the insurer's control.
Builder made some errors, but they did not extend timeline unreasonably
While the overall timeline was not unreasonable, I am satisfied there were discrete errors. The two clearest examples concern the fuel system reinstatement and the shade sail.
Demolition and rebuild works began in late January 2023. However, the evidence shows that key issues about fuel system reconnection, regulatory compliance and fuel quality were not actively addressed until mid-July 2023, when trades were already on site for the specialised fuel work. This was not good practice. The need to plan fuel system works should have been apparent much earlier.
However, the fuel work was planned and carried out largely in parallel with the building works. The fuel system could not have been reconnected before the building was substantially rebuilt. The late escalation was poor practice, but it did not independently extend the overall rebuild timeline to any material degree.
The shade sail formed part of the original scope of works dated 2 June 2022. Yet it was ordered late enough that its supply, along with painter availability, became a reason for extending the expected completion date from late June into July 2023. Ordering a known item this late was within the insurer's control. I consider this pushed the timeline back by about one month, noting that the earlier months in 2023 were occupied with structural and internal works that had to occur regardless.
Delays did not cause fuel loss
The complainant says the repair delays caused the petrol bowsers to fail because they did not receive usual maintenance. She also says she had to dispose of stored fuel that had been sitting in tanks for many months.
I do not consider the available information establishes this claim.
The bowsers and fuel were first rendered unusable by the March 2022 storm and the resulting disconnection of the system. The main delay factor was the structural rebuild itself, which would have occurred regardless of whether fuel reconnection was managed promptly. The only evidence the fuel became unsellable is the complainant's own account, without supporting expert opinion on long-term fuel storage effects or causation of later motherboard failures.
The late escalation of fuel system issues from January to July 2023 arguably extended the period by a small margin, but I cannot isolate what part of any degradation is attributable to that incremental delay versus the rebuild itself. The complainant bears the onus to prove her claim. The information is insufficient to discharge that onus.
The fuel bowser claims in January and November 2024 appear to be separate storm or power surge events. The insurer accepted those claims. The loss adjuster for the November 2024 event identified no connection to the 2022 claim.
No basis to alter business interruption settlement
The complainant says the indemnity period and the insurer's business interruption calculation do not account for repair delays, meaning losses beyond 12 months have not been compensated.
The policy limits business interruption cover to 12 months from the date of damage. The insurer says the indemnity period runs from 12 March 2022 to 12 March 2023. The loss adjuster already excluded March–April 2022 in favour of the complainant. Underinsurance applies to any claim within that period.
There is no alternative expert calculation quantifying additional loss from delay beyond the indemnity period. For the reasons above, I do not accept the insurer unreasonably delayed the claim. There is no basis to alter the indemnity period or the business interruption calculations.
Insurer otherwise handled claim reasonably
The complainant also says the insurer's Internal Dispute Resolution (IDR) reviews lacked meaningful consultation and did not properly address the core complaints. She felt blamed despite being transparent.
While the IDR process could have been more consultative, the substantive outcomes were not unreasonable. This does not warrant compensation. The insurer handled the claim reasonably overall.
2.2 Is the insurer responsible for the revenue underinsurance?
No. The insurer did not owe a duty to advise on the scope of cover. The complainant was responsible for ensuring adequate insurance. The agent's conduct did not shift this responsibility.
Complainant was significantly underinsured
The complainant was significantly underinsured for business interruption. In the year before the storm, the business had a turnover of over $1.4 million. The business interruption sum insured was $75,000.
Both parties were aware the sum insured needed to increase. The complainant says the insurer set up the policy incorrectly, communicated poorly and negligently failed to increase cover. She says applying co-insurance is unfair where the underinsurance resulted from the insurer's failure to update the policy.
Insurer not responsible for the underinsurance
An insured is normally responsible for their own insurance needs. An insurer does not owe a duty to advise on policy coverage. Its duty is generally to provide the policy and administer it, including by assessing claims in line with its terms.
This can change in particular circumstances, such as where an insurer clearly misleads an insured. This is not such a case.
It is not in dispute that:
· the insurer provided the certificate of insurance and product disclosure statement when the policy was incepted
· the policy renewed over four years between 2018 and 2022, and some renewals contained express encouragement to review cover levels
· the complainant was aware the business was likely underinsured
· the insurer's agents assisted with policy matters but were not the complainant's broker or advisor.
The $75,000 figure originated as a landlord's loss-of-rent figure
The correspondence shows the policy was set up in March 2018, when the complainant inherited the property. At that time, the business was leased to a tenant. The complainant instructed the insurer to arrange landlord's protection insurance with loss of rent at $75,000 per year. When the tenant left and the complainant began operating the business herself through a company (from about March 2020), turnover grew to over $1 million. But the $75,000 business interruption figure was never updated. It was a landlord's rental income figure, not a figure appropriate for an operating roadhouse.
March 2021 emails did not amount to instructions to increase cover
On about 4 March 2021 the complainant sent a liability renewal questionnaire to the insurer's agent, noting turnover was well over $1 million. She asked for help with a "proper insurance quote to make sure we are fully covered."
The complainant says this amounted to clear instructions regarding business interruption cover. I disagree. In context, this was one step in an information-gathering process that had not concluded before the storm occurred.
On 5 March 2021 the agent responded with detailed advice and a list of actions for the complainant to complete. Relevantly, the agent wrote:
We should have a separate Business Interruption for the actual business – say there was a fire and you lost the building – you loose your income. That should really be protected. I can email you a Business Interruption calculator for the business that either yourself or your accountant can complete to ensure that the figure is correct. So critical to have this right as Underinsurance applies if its not 80% of the correct amount.
The complainant says the agent never sent the calculator. The insurer says she did. I do not need to resolve this dispute, because regardless of whether it was sent, neither party followed through on the business interruption issue after this exchange.
Complainant had over 12 months to act but did not follow through
The next relevant exchange occurred between 29 September and 1 October 2021. The complainant emailed that turnover was increasing and insurance "needs to be re-evaluated," adding: "Next time you are in [town] we will go through it all." The agent replied: "Most definitely – I have your name on my whiteboard TO DO."
In February 2022 the complainant added a vehicle to the policy. The storm occurred on 12 March 2022.
The complainant had over 12 months between the agent's detailed March 2021 email and the storm to follow up or act independently. During this period she made other changes to the policy. She understood the business interruption cover needed attention. She did not pursue it.
I accept the complainant was relying on the agent to some extent. However, the agent did not mislead the complainant, did not assume the role of insurance advisor, and did not fail to follow instructions. While the agent could have been more proactive, that does not shift the responsibility for cover to the insurer. There is no record of the complainant giving a clear instruction to increase the sum insured.
Confusion at policy inception did not cause the underinsurance
The complainant also argues the policy was set up incorrectly when the property transferred via inheritance. I accept the emails show some confusion about business structure and ownership. The policy was originally structured as a landlord's risk, and the business interruption sum insured was not updated when the complainant began trading.
However, this confusion did not cause the underinsurance. Both the insurer and the complainant identified the issue well before the loss. The complainant was responsible for her own insurance and could have acted to increase the cover at any point.
2.3 Did the insurer unfairly refuse insurance?
No. The insurer's decision not to renew the policy was reasonable and consistent with its underwriting guidelines.
No evidence refusal was unfair or in bad faith
The complainant says the insurer's decision not to renew from 29 March 2025 was unfair and retaliatory because she made a large claim and complained to AFCA.
The insurer says it declined renewal because of the complainant's claims history, including frequent and high-value claims and a 900% loss ratio over five years. It provided underwriting guidelines and claims history to support this.
I have reviewed this information. The insurer acted consistently with its underwriting guidelines, which require a subjective assessment of future profitability where multiple claims have been reported. There is no evidence the decision was retaliatory or in bad faith.
2.4 Why is the outcome fair?
The insurer handled the claim reasonably overall. Its agents were not responsible for the underinsurance. The non-renewal decision was fair.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.