Determination 12-25-215845

Claim declined for sinking and cracking damage; insurer found cause was gradual deterioration, not storm or rainwater

FirmAuto & General
Decided2025-10-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed for sinking and cracking damage to his home which he said was caused by a storm on 12 October 2024. AFCA found the damage was not shown to be caused by the storm and that the insurer could decline the claim and issue a maintenance letter.

The complainant did not establish on the balance of probabilities that an insured storm or rainwater event caused the damage, as expert reports pointed to long-term causes, and the policy's good condition term entitled the insurer to require rectification.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-215845 | Financial firm | Auto & General Services Pty Ltd Case number: 12-25-215845 16 October 2025 1 Determination overview 1.1 Complaint The complainant holds a home building insurance policy underwritten by the financial firm (insurer). The policy covers loss or damage to the insured property caused by listed insured events, including storms and rainwater. The complainant lodged a claim with the insurer in October 2024 for sinking and cracking damage to the insured property. The complainant says this was caused by a heavy rainfall or storm event, and runoff from this, that occurred on 12 October 2024. The insurer denied the claim on the basis the damage was not caused by the rainwater or storm event, and was rather caused by gradual deterioration and the home not being in good condition, which are both excluded from cover under the policy. The complainant disagrees. He seeks cover under the terms of the policy. He also disagrees with the insurer’s requests to undertake rectification works to the property so it is in ‘good condition’, which is a condition of cover. 1.2 Issues and key findings Is the damage covered under the policy? No. It has not been established that a storm or rainwater event caused damage to the complainant’s property. As the complainant has not established a claimable loss under the policy, the insurer is entitled to decline the claim. Is the complainant required to make repairs to the insured property? Yes. It is a term and condition of the policy that cover may be affected if the home is not in good condition. The complainant has not provided any specific or contemporaneous information or persuasive evidence to demonstrate the faults and defects identified by the insurer do not exist, or that they are not required to be rectified to ensure the home is in good condition. Why is the outcome fair? I am not satisfied the complainant has established a claimable loss under the policy caused by an insured event. It would not be fair in the circumstances to require the insurer to cover the claim. It is also fair that the insurer is entitled to issue a maintenance letter to ensure that the insured property is in good condition and is therefore an acceptable risk under the terms of the policy. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to deny the claim and is not required to take any further action in relation to this complaint. 2 Reasons for determination 2.1 Is the damage covered under the policy? No. It has not been established that a storm or rainwater event caused damage to the complainant’s property. As the complainant has not established a claimable loss under the policy, the insurer is entitled to decline the claim. Complainant has onus to establish a claimable loss It is established insurance law that the complainant first has the onus to establish the claimed loss is a result of an event covered under the policy that occurred during the period of insurance. This must be established on the balance of probabilities, meaning that it is more likely than not. This is sometimes called a claimable loss. ​If the complainant is able to establish a claimable loss, the onus shifts to the insurer to show, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to decline the claim. ​The terms and conditions of the policy are set out in the policy documents, including the Product Disclosure Statement (PDS) and the Insurance Certificate. The parties agree the insurer provided a copy of the policy documents to the complainant. It follows the insurer is entitled to rely upon the contents of the documents. There is damage to the property The insured home building is a single-storey house on stumps with a tiled roof and was constructed in or about 1970. It is built on a slope from the rear to the front and from the right to the left. There is no dispute there is damage to the building, comprising sinking, cracking, sloping and/or subsidence affecting the house, driveway and deck area. Complainant says damage was caused by storm or rainwater The policy covers loss or damage to the home building caused by an insured event, being the incidents listed in the PDS. These incidents include storms and rainwater. The PDS states at page 37: You are covered for Loss or damage caused by storms and rainwater, including from: · earth movement that occurs within 72 hours of a storm or heavy rain, and as a result of that storm or heavy rain · surface run-off rainwater from surrounding areas that occurs within 24 hours of a storm or heavy rain · the escape of rainwater from any water pipe, drain, or gutter · wind damage caused by storms or heavy rain. On 12 October 2024, and on at least some of the preceding days, there was a rain event at the property (the storm). The insurer has accepted and acknowledged that the storm occurred. The complainant states that a sudden ingress of rainwater occurring during and immediately after the storm caused the damage. He states this is also supported by the spray test conducted by the insurer’s plumber, AC, and AC’s report. The report stated: Spray testing confirmed that water was pooling in these areas and tracking toward the home. Additional spray testing revealed water runoff into the subfloor…Future precipitation events may lead to water entry through the external wall cladding, exacerbating existing damages and that: the predominant cause of damage to the affected area is water runoff from the external perimeter of the home. The complainant also says that the insurer has not shown that the damage was caused by ‘gradual deterioration’ or the home ‘not [being] in good condition’, both of which are policy exclusions. On this point, the complainant notes the reports prepared by his appointed engineer, AB, and the insurer’s engineer, GD, both refer to the ‘good condition’ of the property and the absence of any major structural defects. Insurer says damage was not caused by storm or rainwater Whilst the insurer has acknowledged the storm occurred, it states this was not the cause of the damage to the property. The insurer says: · the storm was insufficient to cause damage to the structure, as it was ‘less than a 1 in 1-year event’ which is ‘considered to be insufficient to be the causal mechanism of damage’; and · the cause of the damage was due to other factors, such as deterioration and the condition of the property. The insurer states that the reports of its builder, BB, and its engineer, GD, show that the damage was caused by factors other than the storm. In particular: · Photographs of the property taken by GD, which GD states show long term moisture damage in a number of areas; · GD’s analysis of the soil, vegetation, level survey results and site inspection, which concludes that: long-term ground movement has occurred on site, and seepage has contributed to the subsidence due to drainage deficiencies directing runoff and moisture to the subfloor. The vegetation and filled ground onsite have also contributed to the damage observed. · BB’s report following its site inspection states the damage is ‘consistent with long term movement issues to the property’ and not a ‘single insurable event’. Satisfied that damage was not caused by a storm or rainwater Based on the exchanged material, I am not satisfied the complainant has established a claimable loss under the policy. On balance, the complainant has not shown that the damage to the property was caused by a storm or rainwater runoff within 24 hours of a storm or heavy rain, nor any of the other listed events under the policy (such as earth movement resulting from and occurring within 72 hours of a storm or heavy rain). None of the expert reports submitted by the insurer or the complainant conclude that the damage was caused by the storm. I acknowledge and accept that the policy does not require a minimum amount of rainwater, nor is there any threshold as to severity, for cover to triggered. However, this does not change the findings or conclusions of the various experts that the damage was caused by other factors. Notably: · Both BB and GD observe in their reports damage which they conclude is long term, not recent, and caused by factors other than a storm or rainwater event · The complainant’s engineer, AB, also attributes the damage to other causes such as: > accumulation of stormwater and elevation in soil moisture levels over time causing structural movement > there being ‘no clear evidence of the surrounding finished ground levels being adequately graded away from the house to ensure effective surface drainage. This may contribute to water ingress into the subfloor’; and > prolonged exposure to moisture over time · Moreover, AB does not state that the damage was caused by a storm or rainwater runoff event occurring within 24 hours of a storm or heavy rain. I note that the insurer’s plumber, AC, conducted spray testing which resulted in water pooling and water runoff into the affected area being observed. AC concluded from this that water runoff caused the damage. However, this spray test does necessarily prove that the storm was the proximate, dominant or effective cause of the damage. Whilst the spray testing undertaken by AC may have resulted in water pooling and ingress, this does not mean that rainwater runoff also entered the property in this way and caused the damage. I am not persuaded that the short-term pressurised water spraying conducted by AC replicates the volume, consistency, force and direction of the rain or any runoff from the storm as the cause or likely cause of the damage. Moreover, AC does not comment on whether the damage was recent or long-term, nor does AC consider the timing and details of the October 2024 storm. In addition, AC’s report does not assess the soil, vegetation or topography of the site. By contrast, the engineering and building reports are consistent and thorough in their evaluation of the cause and their observations as to its duration. I have also considered whether the exchanged material demonstrates that a number of rainfall or storm events could be a cumulative cause of the damage. I am not persuaded that the material shows this. None of the reports refer to this as a possible cause and, moreover, the complainant has not provided any persuasive evidence to support this as the cause. I am therefore not satisfied that a claimable loss has been established by the complainant that the damage to the insured property was caused by a storm or rainwater event listed in the policy. 2.2 Is the complainant required to make repairs to the insured property? Yes. It is a term and condition of the policy that cover may be affected if the home is not in good condition. The complainant has not provided any specific or contemporaneous information or persuasive evidence to demonstrate the faults and defects identified by the insurer do not exist, nor that they are not required to be rectified to ensure the home is in good condition. Identification of defects by the insurer In its assessment of the claim and the site reports by BB, GD and its claims assessor, the insurer identified a number of defects, faults and damage to the insured property. Some of the items identified were unrelated to the claimed event. The insurer then issued the complainant with a maintenance letter requiring the complainant to rectify the listed defects, faults and damage. This letter advised the complainant: Your obligations and the conditions of your cover confirm that you need to keep the home and contents in good condition. This includes fixing existing defects, faults or damage to your home or contents, as this may affect your cover. We recommend you appoint a qualified tradesperson to rectify the identified item(s). We may ask for proof of the repairs so that we can update your policy, so please retain these documents. Until the repairs are completed, any further claims related to the identified existing defects, faults or damage will require review. Page 15 of the PDS states that cover may be affected if a home is not in good condition at the time of the loss. The PDS further states that: Good condition includes but is not limited to the home having: · no leaks, holes, damage, rust, or wood rot in the roof, gutters, windows, floors, fences, or other parts of your home · a sound and solid structure with no damage to foundations, walls, steps, flooring, ceilings, gates, and fences · no damage from or infestation of termites, ants, vermin, or other creatures · no broken or boarded-up windows. Complainant states the property is in good condition The complainant says the rectification works listed by the insurer are not required because the home is in ‘good condition’. The complainant says this is evidenced by: · comments in AB’s report that ‘no major structural defects were found in the property’ · comments in AB and AC’s reports that variously refer to the condition of the property as ‘reasonably good and serviceable’ and ‘good’ · the pre-purchase building inspection report that he obtained when purchasing the property in December 2023 did not identify any visible defects, and stated that site drainage ‘appears to be adequate’. The complainant has not provided more specific information or evidence in relation to the individual items listed by the insurer as requiring maintenance or rectification. Insurer entitled to issue maintenance letter I am not persuaded that the generic ‘good condition’ comments in the documents relied on by the complainant indicate that the defects and damage listed by the insurer are not present and do not require rectification. They do not need to be major nor significant. I also note the limitations noted in the pre-purchase building report, and the limited nature of the assessment undertaken. I am not persuaded this demonstrates that these defects do not exist. I am therefore satisfied the insurer is entitled to issue the maintenance letter requiring rectification and maintenance as listed. 2.3 Why is the outcome fair? I am not satisfied the complainant has established a claimable loss under the policy caused by an insured event. It would not be fair in the circumstances to require the insurer to cover the claim. It is also fair that the insurer is entitled to issue a maintenance letter to ensure that the insured property is in good condition and is therefore an acceptable risk under the terms of the policy. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.