Text of the determination
Determination
|
Case number
|
12-25-209279
|
Financial firm
|
Allianz Australia Insurance Limited
Case number: 12-25-209279 28 November 2025
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents insurance policy covering insured events and accidental damage (policy) with the financial firm (insurer). On 3 January 2024, he lodged a claim for water damage caused by a fridge filter failure on 31 December 2023.
The insurer accepted the claim and, at the complainant’s request, offered a cash settlement in the amount of $37,109 (after $800 excess) based on its builder’s (AC) quote, for repairs. The cash settlement offer was increased to $39,485 in December 2024.
The complainant rejected both options, arguing the scope of works (SOW) is incomplete and the amount inadequate. He submitted quotes of $101,240 (WW) and $143,276 (TC), which the insurer deemed excessive, noting he had not adequately specified SOW deficiencies.
The complainant seeks $170,000, including $20,000 for temporary accommodation (TA), $1,500 for make-safe work, and $5,000 compensation for non-financial loss (NFL) for his claims experience.
The insurer proposed a dual on-site assessment on 28 January 2025. However, the complainant has not pursued the offer, which remains open for acceptance.
Is the cash settlement offer fair?
No. This is because on the balance of probabilities (that is more likely than not), the cash settlement offer excludes risks like unforeseen damage or extra work and does not cover TA, despite the insurer acknowledging it will be needed.
While the complainant has failed to adequately specify what items are missing from the SOW, I am not satisfied the SOW is complete. I am satisfied a joint assessment is a pathway to a fair cash settlement.
Did the insurer mishandle the claim?
Yes. The insurer relied on an incomplete SOW and issued cash settlement offers despite acknowledging omissions. Communication was poor, with delays and failure to act on agreed steps. The insurer is required to pay the complainant $1,500 NFL.
Why is the outcome fair?
A joint assessment for a fair cash settlement is reasonable in the circumstances. It corrects prior shortcomings, preserves choice, and ensures the insurer meets obligations without forcing an incomplete settlement. The insurer’s mishandling caused delays and inconvenience; $1,500 NFL fairly compensates the complainant for the claim experience.
1.2 Determination
This determination is substantially in favour of the insurer.
Within 14 days of receiving confirmation the complainant accepts this determination the insurer is required to act in accordance with sections 2.1 and 2.2 below.
2 Reasons for determination
2.1 Is the cash settlement offer fair?
No. This is because, on balance, the cash settlement offer excludes risks like unforeseen damage or extra work and does not cover temporary accommodation, despite the insurer acknowledging it will be needed.
While the complainant has failed to adequately specify what items are missing from the SOW, I am not satisfied the SOW is complete. I am satisfied a joint assessment is a pathway to a fair cash settlement.
Policy cover is subject to terms, conditions, and exclusions
The policy covers the period from 12 June 2023 to 12 June 2024. Coverage is defined in the product disclosure statement (PDS) and certificate of insurance (COI), which must be read together. Relevant policy terms are outlined in section 3.2.
There is no dispute the complainant received a copy of the policy documents. The insurer is entitled to rely on the terms of the policy in assessing the claim.
The insurer accepts the claim. However, the parties disagree on the adequacy of the SOW and cash settlement offer.
Insurer makes settlement offers
The leak damage includes flooring beneath the fridge, adjacent panelling, filler panel, and kicker. While leak damage is minor, the room’s construction requires extensive work, including removing benches and skirting.
Flooring removal will damage the yellow tongue, necessitating new subfloor installation. Benchtops will likely break during removal, so their replacement is also included.
The insurer obtained quotes from two builders, RC ($41,373) and AC ($37,909), awarding the tender to AC as its quote was deemed more competitive. The insurer considers AC’s quote actionable and is prepared to complete repairs accordingly.
Based on AC’s quote, and at the complainant’s request, the insurer made a cash settlement offer of $37,109 (AC’s quote less $800 excess) in February 2024. This was declined by the complainant.
On 12 December 2024, the insurer offered $39,485 (AC’s revised quote less $800 excess), which the complainant also declined. The insurer proposed a joint onsite assessment to address concerns and confirm scope.
While this offer has not been pursued, the insurer remains open to this assessment to resolve the complaint.
Complainant says cash settlement offer is inadequate
The complainant says the insurer’s cash settlement offer is inadequate as it does not represent a reasonable assessment of the cost of repairing the claimed damage. He has provided two builders quotes and wants the insurer to base the cash settlement on TC’s quote, plus TA, and make safe reimbursement.
This is because:
· the insurer’s SOW is incomplete and inaccurate, excluding key items (stone materials, accommodation, offsite storage, underfloor heating, 2-pac doors, metal door jambs)
· SOWs are often prepared by inexperienced assessors, making them unreliable and more like general guides
· with extensive insurance repair experience, he knows both builders. He lacks confidence in their ability to perform the works to an acceptable standard in a timely manner
· the insurer’s quote is flawed due to assessor’s lack of qualifications, limited information, and superficial inspection
· he prefers a cash settlement based on a complete SOW; current offers undervalue repairs due to flawed SOW
· insurer rejected complainant’s quotes as ‘too high’ without justification; complainant sees this as underquoting or incompetence
· the insurer deliberately continued offering the same cash settlement despite acknowledging SOW errors.
On balance, cash settlement is inadequate
I have carefully considered the exchanged information. On balance, I am not satisfied AC’s quote is adequate.
The quote is strong in terms of completeness, offering a detailed, itemised breakdown across multiple trades. It includes complex tasks, and provides transparent pricing with builder’s margin, insurance premium, and GST.
However, the quote has notable weaknesses:
· certain preliminary charges lack detailed justification
· it does not explicitly include stone materials or accommodation
· it lacks a contingency allowance for unforeseen damage or additional works required to facilitate repairs.
On balance, complainants’ quote is excessive
TC’s quote provides a full SOW across all phases, site preparation, demolition, rectification, and reinstatement. It includes premium finishes such as stone benchtops, 2-pac cabinetry, and LED lighting.
However, it:
· appears expensive ($143,276.52) compared to the insurer’s builders, with large preliminaries ($31,050)
· offers limited cost transparency
· uses lump sums instead of unit rates
· does not include a contingency allowance despite acknowledging possible extra works
· the timeline depends on external factors, and accommodation costs are not addressed.
Joint assessment for a fair cash settlement
Under policy terms, if a claim is covered the insurer will either repair or rebuild the home to its original condition or pay the reasonable cost in cash or equivalent. The complainant says he does not want the insurer’s builder to perform the works.
I acknowledge the complainant’s lack of trust in the insurer, its assessors, and builder, which is an obstacle to progressing the claim. To address these concerns, I consider a fair and reasonable pathway to resolution is a joint assessment to agree the SOW and determine costs for a cash settlement, between:
· a building consultant (insurer appointed):
> provide a balanced view on what is required to restore the property to its pre-loss condition:
‒ including reasonable contingencies (such as removal and storage for complainants’ contents and any undamaged items to facilitate the works)
‒ agree reasonable allowances for any unforeseen works more than likely to be required to complete the repairs.
· the complainant’s preferred builder:
> assess constructability and sequencing of works including appropriate repair duration.
· the complainant:
> review and discuss proposed SOW, provide input, and identify corrections. In the event of a disagreement, the building consultant will have the final say on the SOW.
· a quantity surveyor (insurer appointed)
> independently cost the agreed SOW based on current market rates and a perform reasonable quantification of the TA claim
> will be the final arbiter on a fair and reasonable cash settlement amount.
I acknowledge the complainant’s concerns about the independence of the insurer-appointed building consultant (BC) and quantity surveyor (QS). However, these concerns do not demonstrate actual bias or prevent reliance on their assessments.
Appointment by an insurer does not negate independence, as professional obligations require objective, evidence-based evaluations. The BC and QS will be suitably qualified, share findings transparently, and the complainant will have an opportunity to inform any concerns relating to the SOW and costings as part of the joint assessment process for the experts’ consideration.
I am satisfied they can act independently and that the process is fair.
On receipt of notification the complainant accepts this determination, the insurer is required to:
· within 21 days of acceptance - appoint a suitably qualified BC and QS, notify the complainant, and agree a time and date for the joint assessment with the parties
· within 14 days of receiving the final costed SOW and TA claim calculation from the QS:
> cash settle the complainant the repair costs and TA claim in accordance with the QS calculations, less policy excess, plus a 10% uplift for the transfer of risk of performing the repairs
> on receipt of proof of payment, assess any make safe costs incurred by the complainant in accordance with policy terms. Reimburse reasonable costs plus interest calculated in accordance with s. 57 of the Insurance Contracts Act (1984) from the date of payment to the settlement date.
2.2 Did the insurer mishandle the claim?
Yes. The insurer relied on an incomplete SOW and issued cash settlement offers despite acknowledging omissions. Communication was poor, with delays and failure to act on agreed steps. The insurer is required to pay the complainant $1,500 NFL.
AFCA approach to non-financial loss
Under the AFCA Rules, AFCA can award up to $6,300 compensation for non-financial loss. We will only award this type of compensation if a complainant suffers an unusual degree of stress, inconvenience, or delay because the insurer mishandled the claim.
We recognise making a claim can be stressful and time-consuming, even if the insurer handles the claim correctly. We will not award compensation for the ordinary degree of inconvenience that comes with making a claim.
We may reduce the amount of compensation we award if the loss was partially caused by the actions of the complainant, or by factors outside the insurer’s control.
Complainant entitled to NFL
The claim was lodged on 3 January 2024. However, the insurer did not act until 18 January 2024. Further delays occurred throughout early 2024, with slow SOW coordination and poor communication.
Cash settlement offers in February 2024, and December 2024 were based on incomplete SOW’s, despite internal acknowledgment of omissions. The insurer also attempted a site inspection in June 2024 – July 2024 while the complainant was overseas, escalating the dispute.
The insurer proposed a joint assessment involving a building consultant and an independent quantity surveyor on 28 January 2025. However, it never occurred. On 26 February 2025, the complainant refused site access until returning from overseas as he wanted to appoint his own quantity surveyor. The AFCA complaint was lodged on 1 March 2025.
I have carefully considered the case notes. I am not satisfied all the delays can be attributed to the insurer. The complainant contributed by taking three months to provide quotes and refusing insurer-appointed builders. Overseas travel delayed inspections. The joint assessment process stalled, and no inspection occurred.
Both parties remained entrenched in a dispute over SOW and costs from March 2024 to April 2025, extending the complaint for over 15 months. These delays significantly impacted fairness and efficiency, leaving the complainant without timely resolution.
Given the above, I am satisfied $1,500 fairly compensates the complainant for his claims experience. Within 14 days of receiving notice the complainant accepts this determination, the insurer is required to pay the complainant $1,500 NFL.
2.3 Why is the outcome fair?
A joint assessment for a fair cash settlement is reasonable in the circumstances. It corrects prior shortcomings, preserves choice, and ensures the insurer meets obligations without forcing an incomplete settlement. The insurer’s mishandling caused delays and inconvenience; $1,500 NFL fairly compensates the complainant for the claim experience.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Policy terms
|
Page
|
Description
|
60
|
Your responsibilities
During the claims process you need to take reasonable steps to co-operate with us,
this may include;
· giving us access to your home at reasonable times and frequency so that a repairer or any other representative we choose can assess loss or damage to your home and contents
· providing us with information we reasonably request (which may include being
interviewed by our representatives)
· providing us with documents we reasonably request to assist with the assessment of your claim – for example, bank statements, phone records, proof of ownership, notices or court documents
If you do not take reasonable steps to co-operate with us we may not be able to progress or approve your claim, to the extent we are prejudiced by your failure to cooperate
|
61
|
How we settle your claims
Buildings claims
If we agree to cover your claim for loss of or damage to your buildings, we will pay the reasonable cost of repairing or rebuilding the damaged part of your buildings to the same condition as when it was new.
At our discretion (acting reasonably), we may:
· enter into a contract with a builder to repair or rebuild your home, or
· pay you the reasonable cost of repairing or rebuilding your home in cash or cash equivalent.
When it is not possible to use original materials during the repair or rebuilding process, we will make best efforts to use the nearest available equivalent to the original materials.
Unless we have agreed in writing, repair or rebuilding of your buildings must commence within six months of the loss or damage. If not, we will not be liable for any costs beyond the repair or rebuilding costs as at the date the loss or damage occurred. We will extend the six month period to the extent we caused or contributed to the delay in repairing or rebuilding your buildings