Home / Auto & General / Determination 12-25-203533

Determination 12-25-203533

Cash settlement amount and scope of repairs for storm and mould damage, temporary accommodation, contents and compensation for claim handling

FirmAuto & General
Decided2026-02-24
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted storm and mould damage after initially declining it, and the parties disputed the cash settlement scope and cost, temporary accommodation, contents and compensation. AFCA required a joint independent assessment to set the cash settlement, a reassessment of accommodation and contents, and $3,000 for non-financial loss.

The policy lets the insurer settle at what it would cost it to repair, the scope and cost are uncertain, so an independent assessment is fair, while claims handling shortcomings warrant non-financial loss compensation.

Issues

Subjects and remedies

criminal recordhealth or medicalhome or building damagenatural disasterpay claimpay non financial lossreassess claimrefund fees or charges

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-203533 | Financial firm | Auto & General Services Pty Ltd Case number: 12-25-203533 19 February 2026 1 Determination overview 1.1 Complaint The complainant holds a home and contents policy with the financial firm (insurer) and lodged a claim for extensive storm damage. The insurer initially accepted only flooring damage in several rooms and declined most mould-related damage as pre-existing or maintenance-related. It later reversed that decision and accepted mould and mould-related damage under the policy. The complainant has requested a cash settlement. The parties now disagree about the fair scope and cost of repairs, temporary accommodation, contents, and whether the complainant is entitled to additional compensation for the insurer’s handling of the claim. 1.2 Issues and key findings What is the fair and reasonable cost of repairs? Neither party’s current repair figure is a reliable basis for a cash settlement. The insurer must pay for a further joint assessment using an agreed independent building consultant to set the repair scope and cost. If the complainant does not allow this, the insurer may cash settle using its existing offer. Is the complainant entitled to more for temporary accommodation and contents? On the present evidence the complainant has not shown that further temporary accommodation or contents payments are immediately payable. But these claims must be revisited after the joint assessment clarifies the repair timeframe and the complainant provides any outstanding invoices and inventories. Is the complainant entitled to compensation? Yes. The insurer has already paid $1,800 for concerns about its investigation process. It should also pay a further $3,000 for non-financial loss for other claims handling shortcomings, and reimburse certain costs incurred subject to proof. Why is the outcome fair? The assessment process proposed is balanced and independent. It balances the rights and obligations of the parties under the policy and at law, in the context of evidentiary uncertainties about the scope of works. I have also awarded compensation for non-financial loss that fairly reflects the insurer’s claims handling shortcomings. 1.3 Determination This determination is mostly in favour of the insurer. If the complainant accepts this determination, then within 14 days of being notified, the insurer is to pay the complainant $3,000 in non-financial loss compensation and the parties are to take the steps outlined in section 2.1 below. 2 Reasons for determination 2.1 What is the fair and reasonable cost of repairs? Neither party’s current repair figure is a reliable basis for a cash settlement. The insurer must pay for a further joint assessment using an agreed independent building consultant to set the repair scope and cost. If the complainant does not allow this, the insurer may cash settle using its existing offer. Scope of works and cost of repairs in dispute The insurer initially partially declined the claim, but eventually accepted some building damage. Following a review by the engineer GD and a hygienist, the insurer agreed to include mould and mould-related damage. The insurer suggested a final dual assessment to establish an actionable scope of works, but the complainant refused. Following the breakdown of the parties’ relationship in early 2025, the complainant requested a cash settlement. The insurer has agreed to cash settle, although its preference is to do the repairs. Parties’ positions differ significantly There is a significant difference between the parties’ positions. The insurer relies on a liability quote from its panel builder (BB) dated June 2025, totalling about $181,209. The complainant relies primarily on a scope and quote from a restoration and building consultant (PP) totalling $506,118. The complainant has also obtained later quotes from a second builder (BM) of about $232,104 for restoration and $268,756 for building repairs. A further joint assessment is required I consider the fairest course is to require a further joint assessment to establish a single, independent scope of works for the accepted damage. I have reached this view for the following reasons. Insurer is entitled under policy and at law to verify damage The insurer has a policy entitlement to conduct comprehensive physical damage assessments. While this right is not unfettered, I am satisfied the insurer is entitled to exercise it in the current circumstances. The complainant must allow this to occur as part of his duty to co-operate under the policy and his duty of utmost good faith as per section 13 of the Insurance Contracts Act 1984 (Cth). Insurer entitled to settle for the amount it would have cost it to do the repairs The policy allows the insurer to settle a claim either by repairing or rebuilding the home, or by paying the complainant what it would have cost the insurer: If we are able to repair or rebuild, but we agree to your request to pay you a cash settlement, we will pay you the amount it would have cost us to repair or rebuild, plus any applicable Additional Benefits stated in this PDS. I consider it fair that the insurer can rely on this provision in circumstances where it is prepared to authorise repairs but the complainant has asked for a cash settlement. Amount it would have cost insurer is not clear BB’s current quote is a liability quote only. It is also incomplete because the insurer has not comprehensively scoped the damage. Further, uncertainty about the mould damage compounds uncertainty about the building damage. Given the complexity of the job (including asbestos and mould remediation) and the time that has passed since the quote was prepared, a further assessment is needed. In other words, without an assessment, the insurer cannot accurately determine what it would cost it to do the repairs, and this goes against its policy entitlement. While the complainant has provided his own detailed critique of BB’s quote, I note he is not independent and his submission is not supported by expert commentary. In any event, even if I were to accept BB’s quote is incomplete or unrealistic, this only adds weight to the suggestion the insurer needs to re-assess its liability. Insurer has not had adequate opportunity to assess scope of works The insurer reversed its partial decline in around mid-2025. Before that, it had denied the mould claim and its assessments focused more on triage, causation investigation, and assessment of damage the insurer was in the process of declining. Since the reversal, the complainant has not allowed a further assessment. While I understand his frustration, the insurer’s earlier denial does not mean it has forfeited the right to properly scope the now-accepted damage. I accept that the insurer's panel restorer and hygienist assessed mould damage at the property before the partial decline. But both assessments were conducted for the purpose of investigating causation, not scoping accepted repairs. The restorer's scope was set aside when the insurer declined the mould claim. The hygienist's report was directed at contamination levels and causation, not at producing a comprehensive building repair scope. And the complainant himself says those assessments significantly understated the damage. If correct, this reinforces rather than undermines the need for a fresh independent assessment. Complainant’s quotes not fair basis for settlement Both parties have made legitimate criticisms of the other’s scope and costings. There is real uncertainty about the scope and quantum and the complainants’ quotes are not a reasonable basis for settlement. In this regard, I note: · as explained above, the complainant’s critique of BB is plausible but not supported by independent expert commentary · the complainant provided a scope of works from BM with highlighting (supposedly done by BM) outlining what BB missed, but there is no commentary directly from BM · the complainant has not refuted the insurer’s assessor’s review of PP’s scope of works. The assessor identified items he says go beyond the storm-related damage or duplicate work already in BB’s scope. These include large allowances for contents inventory and storage, HVAC replacement, roof-cavity remediation, project management at a daily rate, home warranty premiums and builder’s margin, in circumstances where the insurer has already allowed separate restoration and asbestos removal costs. The assessor concluded that PP's total of $506,118 includes very substantial amounts he considers not fair and reasonable. The assessor also says multiple other quoted items are excessively priced. The assessor is qualified to provide this opinion. I also note BM’s quotes are in the range of PP’s, raising the question of whether BM’s figures may also be over-priced. Current causation evidence is conflicting The current causation evidence is conflicting and not compelling on either side. This underscores the fact that the extent of storm-related damage is not entirely clear. Discrepancy between parties’ positions favours further assessment The gap between the parties’ positions is more than $300,000. A discrepancy of that size reinforces the need for an independent assessment rather than adopting either party’s figure. Complainant’s argument does not assist his position I acknowledge the complainant's frustration with the insurer’s process. The insurer denied mould damage for several months before reversing that decision. During that time, the complainant was living in a mould-affected home with his family, including a young child. He reasonably feels the insurer should not benefit from its own delay. I have taken this into account in my assessment of non-financial loss below. But the question here is different: it is whether, now that the insurer has accepted the mould claim, the complainant can fairly prevent it from assessing the damage it has accepted. In my view, he cannot. The insurer's earlier error on liability does not mean the complainant is entitled to a cash settlement based on an unverified scope. If anything, the insurer's reversal shows it is now trying to get the claim right, and a proper assessment is a necessary part of that. Assessment should follow this process If the complainant accepts this determination, then within 14 days of being notified, the parties are to take the steps outlined below. The parties should agree on an independent engineer or suitably qualified building consultant who is independent of both BB and PP. To facilitate this, the insurer should provide a list of two or three candidates, and the complainant should choose one from that list. The expert should inspect the property with both parties or their representatives present and prepare a written scope of works describing the repairs required to address the storm-related damage, having regard to the previous reports and scopes already obtained. Once the scope is available, each party may obtain up to two actionable building quotes based on that scope. An actionable quote is one where the builder confirms it is prepared to perform the works for the complainant at the quoted price. If only one actionable quote is obtained, the insurer should cash settle the building claim using that quote plus a 15% contingency. If more than one actionable quote is obtained, the insurer should cash settle using the average of those quotes plus a 15% contingency. The contingency addresses the likely variances in a complex job involving asbestos and mould remediation and the fact that the risk of the works passes to the complainant in a cash settlement. Any amount payable is limited by the applicable building sum insured. No interest is payable, because the settlement will be based on current market rates at the time of quoting rather than a historical figure requiring adjustment. In the context of the further additional assessment, the insurer is also to re-assess the claims for temporary accommodation and contents, as noted below. If the complainant does not co-operate with the insurer and allow reasonable access for this further assessment, I consider it fair for the insurer to cash settle the building claim using its existing offer, being BB’s liability quote plus a 20% contingency. The insurer will have been prevented from updating its assessment in line with this determination, and the complainant cannot benefit from blocking the process this determination requires. If the parties are unable to agree on the final quantum after completing this process, they may return to AFCA for a decision on that point. 2.2 Is the complainant entitled to more for temporary accommodation and contents? On the present evidence the complainant has not shown that further temporary accommodation or contents payments are immediately payable. But these claims must be revisited after the joint assessment clarifies the repair timeframe and the complainant provides any outstanding invoices and inventories. Policy includes temporary accommodation benefit The policy provides that if the home becomes unliveable following an insured event and a claim is accepted, the insurer will pay the cost of reasonable and appropriate temporary accommodation for the complainant and his family, up to 10% of the relevant sum insured and for a maximum period of 12 months. The insurer has already paid some emergency and temporary accommodation amounts. Quantum of costs cannot be determined on the current material I accept the evidence raises serious questions about the liveability of the residence. However, the complainant seeks a specific further amount of temporary accommodation and the evidence does not support calculating that figure now. The complainant estimates a 16 to 20 week repair program. The insurer’s builder initially estimated about six weeks of works plus a two-week contingency. Those estimates are far apart, and the right answer depends on the scope of works, which is the thing this determination requires to be independently assessed. In relation to the period already elapsed, I note the policy functions to cover costs actually incurred. The complainant has not provided substantive evidence of costs incurred for temporary accommodation beyond that already reimbursed by the insurer. I also note the experts do not fully agree on the extent of uninhabitability. The insurer’s restorer initially reported only the master bedroom as uninhabitable, with other areas habitable subject to air filtration. PP and the insurer’s hygienist MP described a more widespread problem. Some accommodation the insurer arranged was not taken up by the complainant. And the insurer’s own approach to temporary accommodation was piecemeal, providing short stays of a few days at a time, with no repairs arranged during those periods. In these circumstances, I am not satisfied the complainant has discharged his onus to show that a specific additional amount of temporary accommodation is currently owing. However, the insurer has said it will re-assess this matter if the complainant provides invoices. Insurer must reassess temporary accommodation after the joint assessment Once the joint assessment produces an agreed repair scope and estimated timeframe, the insurer must promptly reassess the temporary accommodation claim. That reassessment should address both: · (a) past accommodation costs: The complainant should provide any invoices or evidence of accommodation costs already incurred. The insurer has said it will review these for fair and reasonable reimbursement, and it must honour that commitment · (b) accommodation during repairs: If the independent expert confirms that the home is unliveable, the insurer must arrange or pay for temporary accommodation for the repair period without waiting for the full cash settlement to be finalised. The family should not remain in a mould-affected home indefinitely while the settlement process is completed. The temporary accommodation must be reasonable and appropriate for the complainant’s family. Amounts already paid not to count towards the maximum Any temporary accommodation payments for the repair period are subject to the policy cap of 10% of the sum insured and the 12-month maximum period. However, it is fair that the amounts already paid by the insurer are not subtracted from the 12-month cap. This is because, at the time the costs were incurred, the insurer held an incorrect position on the claim and those losses mainly arose because of that. Contents: the insurer’s current position is fair pending further information The insurer has accepted liability for a number of contents items based on the information it received. It offered a settlement using baseline pricing because the complainant did not provide specific contents details. The complainant says extensive contents were damaged or contaminated by mould and water, and that the insurer failed to properly assess them during its early attendances. The insurer says it requested a detailed inventory and supporting documents on several occasions and did not receive a completed list. I accept the insurer cannot be expected to pay for additional contents without adequate information. I also accept that the complainant’s concerns about early contents assessment may have been exacerbated by the initial partial decline, which meant contents were not a priority at the time. Once the joint assessment and repair scope are available, the complainant should provide a complete inventory of any remaining disputed contents, with invoices, photographs or other supporting material where available. The insurer must then reassess those items under the policy, explaining any further denials. 2.3 Is the complainant entitled to compensation? Yes. The insurer has already paid $1,800 for concerns about its investigation process. It should also pay a further $3,000 for non-financial loss for other claims handling shortcomings, and consider reimbursement of certain costs incurred subject to proof. Insurer has adequately addressed the investigation concerns The complainant lodged an internal complaint about the way the insurer’s investigation unit handled the claim, including a request for a criminal history check based on a mistaken name-match with court records. The insurer reviewed that complaint, acknowledged the complainant’s concerns and paid $1,800 in compensation for distress and inconvenience. I consider that a payment in this range adequately addresses the specific impact of the investigation request and the way the insurer communicated about it. Delay in accepting mould damage warrants further compensation The insurer initially accepted only limited flooring damage and declined most mould-related damage as pre-existing or maintenance-related. It later reversed that decision and accepted mould as covered damage under the policy. At the time of the initial partial decline, there was conflicting expert evidence about the cause of the mould. The complainant’s engineer supported a storm-related cause. The insurer’s forensic engineer emphasised drainage and maintenance issues, as did its other assessors. The insurer was not acting without any basis when it declined. But when the insurer reversed its decision, it accepted liability under the policy, not on an ex-gratia basis. It has not explained why it did not reach that position earlier. The conflicting evidence meant there was always a reasonable basis supporting the complainant’s position, and the insurer effectively conceded this by accepting the claim under the policy rather than as a commercial gesture. During the period of the partial decline, the complainant was living in a mould-affected home with a young child. The delay in accepting the mould claim left him in a difficult position and contributed to his stress and sense of being treated unfairly. I consider the insurer should have accepted the claim sooner. I also note the insurer has not addressed this matter persuasively, beyond the suggestion that it made a “commercial decision”. Some insurer commentary was not appropriate In its internal notes and AFCA submissions, the insurer recorded concerns that the complainant might have improper ties to PP, the building and restoration firm which provided his preferred scope. The complainant strongly denies any such relationship and says the suggestion was insulting and distressing. The insurer has not provided evidence to substantiate the implication of impropriety or explained why it was necessary to raise it in the terms used. I consider this fell short of the standard of fairness expected in a complex claim and contributed to the complainant’s non-financial loss. Temporary accommodation and vulnerability: more should have been done The complainant says the insurer provided grossly inadequate temporary accommodation: short stays in small units unsuitable for a family of five, including one with cockroach infestation, leaving them in the mould-affected home for over 14 months. He also says the insurer failed to treat him as a vulnerable customer. I have viewed the correspondence between the parties on this matter. For the most part, I consider that the insurer responded appropriately and made good-faith attempts to secure temporary accommodation. However, given the complainant’s vulnerability (including the fact he had a young child) and the degree of mould present, I consider that the insurer should have been more responsive, comprehensive and diligent in dealing with temporary accommodation. I also note the insurer has not addressed this matter persuasively, which does not assist its position. Allegation about slanderous comments not established The complainant also says that an agent of the insurer, Mr B, made slanderous and defamatory comments about him. In his report, Mr B suggested the complainant made threats and attempted to bribe him. The insurer has not engaged with this allegation in detail. Both parties’ allegations on this point are serious. On the material before me, I cannot determine which version of events should be accepted. I make no finding on this issue and it does not form part of my assessment of non-financial loss. A further $3,000 for non-financial loss is fair Considering the above matters, and AFCA’s approach set out at section 3 of this determination, I consider a further $3,000 is a fair amount of compensation for non-financial loss. I have also considered the complainant’s broader concerns about claims handling, including his submission that the insurer delayed the claim, failed to keep him informed, and used biased experts. Having reviewed the claims timeline, I do not accept there were unreasonable general delays, having regard to the complexity of this claim and the conflicting causation evidence which required multiple expert assessments. The amount I have determined addresses the specific matters where the insurer’s handling fell short. Expenses incurred: insurer to consider The insurer has already reimbursed the complainant for some out-of-pocket expenses including expert report costs. I do not consider the complainant is entitled to the costs of BM’s report because, on my analysis, it did not advance the complainant’s position. To the extent it has not already done so, the insurer must reimburse any outstanding costs for PP’s reports, the complainant’s engineer’s reports, and make-safe works. This is subject to the complainant providing invoices to the insurer of expenses incurred. Apart from this, the complainant has provided insufficient invoices or other evidence to substantiate any further out-of-pocket expenses or claims management fees. I do not consider further compensation is payable. 2.4 Why is the outcome fair? The assessment process proposed is balanced and independent. It balances the rights and obligations of the parties under the policy and at law, in the context of evidentiary uncertainties about the scope of works. I have also awarded compensation for non-financial loss that fairly reflects the insurer’s claims handling shortcomings. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. AFCA approach to non-financial loss Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss if a complainant suffered an unusual degree of stress or inconvenience because an insurer mishandled a claim. We will only award this type of compensation if there has been an unusual degree of stress or inconvenience caused by the insurer’s conduct. We take a conservative approach to awarding compensation. We will not award compensation for the usual amount of inconvenience involved in making a claim. We will not award compensation for delays caused by a complainant, or other factors outside the insurer’s control. In awarding compensation, we also take into account the actions of both parties. This includes any compensation already paid or positive actions taken by the financial firm. 3.2 Key policy extracts Temporary accommodation Sometimes damage to your home and contents can mean you can’t stay living at your insured address. If your home becomes unliveable as a result of an insured event at the insured address and we agree to pay your claim, we will pay for temporary accommodation. We pay up to 10% of your home or contents sums insured for temporary accommodation for up to a maximum period of 12 months. This is in addition to your home or contents sum insured. We will pay the costs of reasonable and appropriate accommodation for you, your family, and your pets while your home is being repaired or rebuilt. When assessing the reasonable and appropriate costs, we consider: - your personal circumstances and living situation at the time of the insured event - if you own the home and live in it. Then we will use the weekly long-term rentable value of your home as a guide for the amount we may pay - accommodation options available in your area - if you are renting. Then we will deduct your usual rental expenses from the amount we pay. For example, if you pay $400 per week rent, and your temporary accommodation is $500, we will pay $100. We will also pay the costs of reasonable and appropriate storage of your contents in a commercial storage facility if they cannot reasonably be stored at your temporary accommodation or remain in the home.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.