Dispute over the cash settlement amount for hail damage to the main roof, shed roof and patio, plus non-financial loss claim for delay
Text of the determination
Determination
|
Case number
|
12-25-198917
|
Financial firm
|
Allianz Australia Insurance Limited
Case number: 12-25-198917 24 November 2025
1 Determination overview
1.1 Complaint
The complainants hold a home and contents insurance policy with the financial firm (insurer). On 28 August 2024, the complainants lodged a claim for hail damage to the main roof (including the patio) and shed roof of their property following a hailstorm in December 2023. The insurer accepted the claim and offered:
· to cash settle the damage to the rear patio roof for $3,979.60, as it says its builder (builder A) could not warrant the works, and
· to cash settle the damage for $33,212.97 or arrange for the repair of the main roof and shed roof.
The complainants are seeking:
· a total cash settlement of $41,447.32, and
· non-financial loss compensation for the unnecessary delays and stress the insurer’s conduct caused them.
1.2 Issues and key findings
Is the insurer’s cash settlement offer fair and reasonable?
No. Builder A’s scope of works (SOW):
· for the main roof and shed repairs does not include installation of tie downs, and
· contains inconsistent pricing for the installation of metal battens in the roof, shed and patio.
The insurer must increase its cash settlement offer for:
· the main roof and shed repairs to $36,403.09, and
· patio repairs to $4,766.29.
Are the complainants entitled to non-financial loss compensation?
No. An award of non-financial loss compensation is not warranted.
Why is the outcome fair?
The outcome is fair because the complainants have shown the insurer’s cash settlement offers are not fair and reasonable. It is fair for the insurer to increase its cash settlement offers.
As I am not persuaded any delay in substantive repairs to the roof was caused by the insurer, the insurer is not required to pay the complainants non-financial loss compensation for the claimed delay.
1.3 Determination
This determination is partially in favour of the complainant. If the complainants accept this determination, within 14 days of receiving the complainant’s acceptance, the insurer is to pay the complainants $41,169.38, less any excess or applicable policy deductions.
2 Reasons for determination
The complainants are represented in this complaint. Unless otherwise stated, I have referred to the complainants and the representative as ‘the complainants’ in this determination.
2.1 Is the insurer’s offer fair and reasonable?
No. Builder A’s scope of works (SOW):
· for the main roof and shed repairs does not include installation of tie downs, and
· contains inconsistent pricing for the installation of metal battens in the roof, shed and patio.
The insurer must increase its cash settlement offer for:
· the main roof and shed repairs to $36,403.09, and
· patio repairs to $4,766.29.
Parties disagree about the cash settlement amount
The insurer provided a SOW for the repairs to the main roof, the shed roof and the patio from builder A.
It is not in dispute builder A was (and is) willing and able to undertake the repairs to the main roof and the shed. Alternatively, the insurer has offered the complainants a cash settlement amount of $33,312.97. The insurer has not applied an uplift to this amount, as its repairer is able to complete the repairs.
It is also not in dispute builder A cannot warrant the repairs to the patio because the roof is underpitched and non-compliant. The insurer offered to cash settle those repairs for $3,979.60, plus a 15% uplift for contingencies (totalling $4,576.54).
The complainants are seeking a greater cash settlement from the insurer and provided a SOW from builder B. The cost of the repairs set out in the builder B’s SOW is $41,447.32. It is unclear from builder B’s SOW whether the repairs to patio are included.
However, considering the complainants say it is a comprehensive quote, and they are seeking to settle the damage based on this quote, I accept it includes all the claimed damage.
The complainants say:
· builder A’s SOW does not include necessary compliance items, such as tie down upgrades, sarking and gutter replacement
· they obtained SOWs from other builders and builder A’s pricing is not fair, reasonable, or within the market rate (based on these alternate quotes)
· builder A’s SOW contains inconsistencies, which support that the SOW is fundamentally flawed
· builder A proposed the use of Zincalume to replace the main roof, which is not their preferred material (which is Colourbond)
· the replacement of the roof with Colourbond means the galvanised gutters will need to be replaced as they are not compatible with Colourbond sheeting, and
· replacing the main roof with Zincalume would also necessitate the gutter replacement, to avoid galvanic corrosion.
Insurer is not required to settle roof repairs for Colourbond quote
The complainants say their preferred roof material is Colourbond. The insurer says the complainants are not entitled to a roof upgrade under the policy.
The policy sets out, when settling building claims:
If we agree to cover your claim for loss of or damage to your buildings, we will pay the reasonable cost of repairing or rebuilding the damaged part of your buildings to the same condition as when it was new.
At our discretion (acting reasonably), we may:
· enter into a contract with a builder to repair or rebuild your home, or
· pay you the reasonable cost of repairing or rebuilding your home in cash or cash equivalent.
When it is not possible to use original materials during the repair or rebuilding process, we will make best efforts to use the nearest available equivalent to the original materials.
It is not in dispute:
· the damaged roof is Zincalume, and
· Colourbond sheeting is merely the complainants’ preference for the roof replacement.
Notably, builder B’s SOW also includes the replacement of the roof using Zincalume. It is unclear why the complainants dispute builder A’s SOW on the basis that the replacement is not for Colourbond sheeting.
In any event, considering the exchanged information, I am not persuaded the complainants have shown the insurer’s settlement for a Zincalume replacement roof is unfair, unreasonable or inconsistent with the policy.
The insurer is not required to settle the claim on the basis that the roof be replaced using Colourbond sheeting.
In relation to the replacement of the gutters, the complainants have not provided any information to show the current gutters are incompatible with Zincalume (noting that is the material the current roof is made from).
I am therefore not persuaded the gutters are incompatible with Zincalume. The insurer is not liable for the replacement of the gutters.
The insurer is also not required to replace the gutters on the basis that they are not compatible with Colourbond sheeting, because the insurer is not required to facilitate the installation of a Colourbond roof.
If the complainants choose to install a Colourbond roof, they will be responsible for the replacement of any incompatible gutters.
Builder A’s SOW should be amended
In support of their position that builder A’s SOW is incorrect, the complainants have provided:
· alternate SOWs from builder A and builder C, and
· their commentary on why builder A’s SOW is inaccurate and unreliable.
Builder C’s SOWs quote the cost of the repairs as being:
· $50,876.96 for the main roof and shed, and
· $7,480.97 for the patio.
The complainants say the alternate SOWs show builder A’s SOW is outside of the market rate. It is unclear exactly how the complainants calculated the market rate.
I acknowledge builder C’s quotes are higher than builder A’s (and builder B’s, for that matter). However, I do not consider this, in itself, shows builder A’s SOW is:
· unreliable, or
· outside of the market rate.
The complainants’ observation that builder A’s SOW does not include tie down upgrades and sarking is incorrect. The SOW clearly includes:
· the supply of tie down upgrades for the main roof and shed, and
· replacement of the sarking in the main roof.
Builder A’s alternate SOW is for a different property, not the complainants’ property. The complainants say this SOW shows builder A’s pricing for the repairs at their property is unreliable. The complainants have specifically referred to the following line items in the alternate SOW:
Labour AND Materials for the following description: - to Install and supply all new Metal roof battens to best match existing as required – rate $17.00
Labour AND Materials for the following description: - to Install and supply all new tie downs as required – rate $14.00
Labour AND Materials for the following description: - to Install and supply new metal corrugated roofing to best match existing including all required flashing – rate $65.00
Builder A’s SOW for the complainants’ property includes the supply of tie down upgrades at a rate of $6. However, there does not appear to be any provision for labour/installation. The insurer has not commented on this. However, considering the tie downs are being supplied, it makes sense that they would also need to be installed.
In relation to the metal battens and roofing for the main roof, I do not accept builder A’s alternate SOW shows the amount quoted for the supply and installation of either item is incorrect.
This is because there is no information about the type of metal battens or roofing material quoted for in the alternate SOW. I cannot be satisfied this is a comparable quote for the replacement of the metal battens or the roof.
Builder A’s SOW includes the following line item for the roof repairs:
Labour AND Materials for the following description: Supply and install Metal roof battens (Im) – rate $8.50.
I acknowledge the complainants say the battens in builder A’s SOW are measured in square metres, not linear metres. However, it is clear from the above this observation is incorrect.
Notably, the line item for the installation of the metal battens in the shed lists the rate as $11. The insurer has not responded to the complainants’ allegation about this inconsistency.
Considering this, I accept there is an inconsistency in the pricing of this specific item in builder A’s SOW.
However, I do not accept this shows the entire SOW in unreliable or inaccurate, particularly where the itemised repairs to the main roof and shed set out in builder B’s SOW are comparable to builder A’s SOW.
Insurer should increase its cash settlement offer
Considering the above, I consider it fair for the rate for the supply and installation of:
· the metal battens to be set at $11, in line with the rate quoted for the shed repairs, and
· the tie down upgrades to be set at $14, in line with the alternate SOW which includes installation.
Including the 20% builder’s margin, this would see the repair quote for:
· the tie downs to the roof increased by $1,632 (from $1,224 to $2,856)
· the tie downs to the shed increased by $259.20 (from $194.40 to $453.60)
· the metal battens for the roof increased by $918 (from $3,121.20 to $4,039.20), and
· the metal battens for the patio increased by $150 (from $510 to $660).
The total increase to the quoted repairs is $3,255.12 (including GST) (noting $165 is for the patio repairs that cannot be warranted).
Therefore, the cash settlement for:
· the main roof and shed repairs is $36,403.09, and
· the patio is $4,766.29 (including the 15% uplift).
For completeness, I acknowledge the insurer has not offered an uplift on the cash settlement for the main roof and shed repairs.
I accept this is fair and reasonable because:
· builder A has always been willing and able to complete the repairs
· it is the complainants’ choice to cash settle the repairs and, in doing so, accept the risk transfers to them
· the itemised repairs in builder B’s SOW do not substantially differ from builder A’s SOW
· while I accept the cash settlement should be increased, I do not consider this would affect builder A’s ability to complete the repairs, and
· the amended total cash settlement is comparable to what the complainants are seeking in line with builder B’s SOW.
2.2 Is the complainant entitled to non-financial loss compensation?
No. An award of non-financial loss compensation is not warranted.
AFCA may award non-financial loss compensation
In this case, the complainants are claiming non-financial loss compensation for the insurer’s unnecessary claim delays.
Under the AFCA Rules, we may award up to $6,300 compensation for non-financial loss (for complaints lodged on or after 1 January 2024).
AFCA takes a conservative approach to awarding this compensation. We will only award this compensation if the complainant has suffered an unusual degree of stress, inconvenience or delay due the insurer’s conduct (e.g. unreasonably handling the claim).
The complainants say:
[We] just want our roof fixed. We have found the whole process lengthy and a little stressful. We are worried that there may have been more damage to our home since the first storm damage due to any leaks etc, that we don't know about. We would like the repairs completed soon as possible.
It is not in dispute builder A has always been ready and willing to undertake the repairs. While I accept the SOW contains some minor errors/inconsistencies, the complainants could have had the main roof and shed repairs completed by builder A if their concern was having the repairs completed as soon as possible.
While I accept the complainants (via their representative) were entitled to query/dispute builder A’s SOW, doing so does not entitle them to non-financial loss compensation for any settlement/repair delays the dispute may have caused.
2.3 Why is the outcome fair?
Outcome is fair
The outcome is fair because the complainants have shown the insurer’s cash settlement offers are not fair and reasonable. It is fair for the insurer to increase its cash settlement offers.
As I am not persuaded any delay in substantive repairs to the roof was caused by the insurer, the insurer is not required to pay the complainants non-financial loss compensation for the claimed delay.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.