Determination 12-25-198267
Insurer accepted only 30% of the claim for property damage from broken stormwater pipes and refused the rest
Summary
The insurer accepted 30% of the repair cost for damage to the home from broken stormwater pipes. AFCA found the 30% apportionment fair but required a new complete quote with a 20% uplift, and $4,495 towards professional fees.
Differential settlement on a cut and fill site was the proximate cause with leaking pipes only exacerbating it, so the 30% apportionment based on the insurer's engineer was fair.
Issues
- Claim amount dispute primary · upheld“Insurer should obtain a new actionable, current and complete quote... liable for 30% of this revised quote plus an uplift of 20%”
- Claim denial secondary · not upheld“Differential settlement in cut-and-fill is the proximate cause... exacerbated by liquid escaping; 30% offer fair”
- Inadequate claim investigation secondary · not upheld“Responsibility rests with the complainant to show other areas where the stormwater pipes had broken”
- Product terms interpretation secondary · not upheld“Policy covers escape of liquid and subsidence within 72 hours; earth movement not covered”
Subjects and remedies
home or building damagepay claimpay compensation
Related
Text of the determination
Determination
|
Case number
|
12-25-198267
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-25-198267 11 February 2026
1 Determination overview
1.1 Complaint
The complainant lodged a claim with the financial firm (insurer) under his home and contents insurance policy on 19 May 2023. Liquid escaping from broken stormwater pipes had damaged the property. The complainant incepted the policy in January 2022.
The insurer accepted the claim partially (30% of the total repair cost) for the damage caused by the broken stormwater pipes. It refused liability for any damage caused by other factors.
The complainant is represented by a paid claim advocate (PR). For ease of reference, the complainant and PR will be referred to as ‘the complainant’ in this determination, unless specified otherwise.
The complainant seeks the insurer to accept the claim and pay the full cost of repairs. He says the broken stormwater pipes caused all the damage to the property.
1.2 Issues and key findings
Is the insurer’s settlement offer fair?
Yes, partially. There was cracking identified throughout the property in 2020. This was before the complainant incepted the policy. The original builder (F) added an expansion joint to fix the issue in January 2021. The complainant’s engineer M concluded the liquid escaping from the broken stormwater pipes was the primary cause of the property damage. However, M did not explain the other factors which contributed to the damage.
The insurer’s engineer EI considered all the factors contributing to the damage observed. EI concluded 30% of the property damage arose from the broken stormwater pipes. It is fair the insurer’s settlement is based on a current, complete and actionable builder’s repair quote based on EI’s scope of works. The insurer is not liable for the cost of repairing or replacing the broken stormwater pipes and other works required to improve the property’s drainage.
Is the insurer required to pay professional fees?
Yes, mostly. M’s investigations included soil testing and DCP testing which assisted EI’s supplementary submissions. PR’s submissions partially assisted the complainant.
Why is the outcome fair?
The parties are bound by the policy terms and conditions. It would be unfair to require the insurer to cover a loss which does not fall within the scope of the policy.
1.3 Determination
This determination is substantially in favour of the insurer.
Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to settle the claim as detailed in section 2.1 of this determination and pay $4,495 towards professional fees incurred.
2 Reasons for determination
2.1 Is the insurer’s settlement offer fair?
Yes, partially. There was cracking identified throughout the property in 2020. This was before the complainant incepted the policy. The original builder (F) added an expansion joint to fix the issue in January 2021. The complainant’s engineer M concluded the liquid escaping from the broken stormwater pipes was the primary cause of the property damage. However, M did not explain the other factors which contributed to the damage.
The insurer’s engineer EI considered all the factors contributing to the damage observed. EI concluded 30% of the property damage arose from the broken stormwater pipes. It is fair the insurer’s settlement is based on a current, complete and actionable builder’s repair quote based on EI’s scope of works. The insurer is not liable for the cost of repairing or replacing the broken stormwater pipes and other works required to improve the property’s drainage.
Complainant must establish a claimable loss
When making a claim, the complainant has the initial onus of establishing he suffered a loss for which the insurance policy provides cover. The complainant must establish this on the balance of probabilities (i.e. that it is more likely than not).
If a claimable loss is established, the insurer has the onus of establishing, on the balance of probabilities, the application of any exclusion it relies on to reduce its liability or deny the claim.
Policy cover is subject to terms and conditions
The policy covers damage caused by water or other liquid which suddenly and unexpectedly escapes from various sources including:
· a plumbing system
· a water main or pipe
The policy also covers damage caused by landslide and/or subsidence that happens within 72 hours of, and as a direct result of, the escape of water or other liquid.
The policy does not cover damage caused by earth movement (except as above). Earth movement is defined as landslide, landslip, mudslide, subsidence and the heaving, collapsing, vibration, erosion, settlement, shrinkage of earth but not earthquake.
If the insurer has agreed to pay the claim for damage caused by escape of water or other liquid, the policy says it will also pay the reasonable cost of a qualified and properly equipped supplier to:
· find the source of the escaped water or other liquid; and
· repair any damage that was necessary in order to find the source.
The policy does not cover the costs to:
· fix leaks;
· repair or replace defective parts or items that caused the damage; or
· fix defects in the design or construction of a system.
Parties provided different views on scope of cover under the policy
The complainant says:
· all damage to the building is the result of the escape of liquid from the broken stormwater pipes. These caused subsidence due to the heavy saturation of the highly reactive soils
· the following information from EI’s report support him:
> if the plumbing damage had not occurred, the amount of settlement would not have reached the level of structural foundation movement measured onsite
> the level of crack damage indicates the differential settlement exceeds the serviceable limits expected from normal consolidation settlement
· the insurer’s scope of works is inadequate and will not repair all damage attributed to the leaks from stormwater pipes. It excludes underpinning costs
· there has been no commitment by the insurer to find the source of the leak
· M confirms the stormwater leak is the proximate cause of the damage to the house.
The insurer says:
· it did not have EI’s supplementary report nor M’s report at the time it decided to partially accept the claim. It should not have accepted any liability for the claim
· EI says the damage is consistent with occurring incrementally and without a sudden drop of the footings
· the available information supports the claimed damage caused by earth movement/subsidence is not consistent with the damage occurring within 72 hours of an escape of water or other liquid event and is not as a direct result of escape of water or other liquid
· in the Google street view, some of the identified damages can be seen present in August 2022
· the available information does not verify there was a sudden and unexpected escape of water from the crushed stormwater pipes.
Complainant responsible to show other sources of escape of liquid
The complainant says the insurer should conduct further investigations to identify the source of escape of liquid. The insurer says it had conducted adequate investigations to identify the source(s) of the damage.
The responsibility rests with the complainant to show there are other areas where the stormwater pipes had broken contributing to the property damage. That has not occurred here.
Experts say escape of liquid from broken pipes contributed to the damage
The policy was incepted in January 2022. The responsibility remains with the complainant to show that during the period of insurance, the damage to the property was caused directly by the escaped liquid and/or from earth movement that occurred within 72 hours as a direct result of an escape of liquid.
The complainant provided the following information when he lodged the claim with the insurer on 19 May 2023:
Cracking to walls and ceiling from what may be heaving from the footings. Damage to the walls in ceiling across the entire centre of the house where the cut/fill line is on the block. This includes warping to the brick work on the outside.
Plumber AQ’s report dated 30 June 2023 concluded there was no evidence of any leak from the main drain. Hot and cold water supply also held pressure indicating no leaks in the pipe(s). However, AQ found two areas where the stormwater pipes were broken:
Ran camera up from outlet on street and ran up only around 2.7m to find drain to be broken. This is in line with the outlet on the street and is next to or just under front retaining wall. Could not go any further upstream from this point...
Came to the other side of house, where the house is not being affected and ran the camera down other stormwater drains. Found a stormwater drain near downpipe next to kitchen to be broken. Could not continue through stormwater drain under garage and driveway as drain was to badly broken at this section.
AQ did not identify any other issues with the plumbing at the property during its attendance.
The parties’ appointed engineers EI and M attended the property and shared their observations on the cause of the cracking and movement damage to the property:
EI concluded:
In our professional opinion, the damage to the residence is the result of differential rates of settlement as a result of a cut and fill site causing crack damage in the building. Plumbing defects identified by [AQ] are considered to be exacerbating factors.
The damage is not the result of a singularly defined event but there has been incremental ongoing damage. If the plumbing damage had not occurred, the amount of settlement would not have reached the level of structural foundation movement measured onsite.
M concluded:
the subsidence of the north-western corner of the slab is due to a fractured stormwater pipe that was located ~4m north from the north-western corner of the house. Stormwater discharging from the fracture is within range of the north-western corner of the house where calcareous, limey and sandy soils are located, this would cause the soils to collapse and the north-western area of the footing to subside.
Original builder’s (F) letter dated 20 November 2023 included comments from the F’s engineer TK:
F - As discussed on site, it is clear that the movement observed on your property is caused by moisture due to broken stormwater pipes. F does not take responsibility of the movement due to damage from an external source. i.e. Broken stormwater pipes. We suggest you engage your own engineer to conduct a brick course level survey to determine the movement accurately of the footing system.
TK observed:
· this is a black earth site with an estimated soil differential movement under normal seasonal soil moisture variations of approximately 120 mm i.e. this is a class 'E' site
· TK has designed footings stiff enough and strong enough to cater for this movement
· abnormal soil moisture variation such as poor drainage or leaking pipes will result in differential soil movement greater than that estimated
· TK has not designed footings to cater for this abnormal soil moisture variation
· abnormal moisture variations have been established on this site due to the crushed/broken stormwater pipe adjacent to the kitchen garage area. This is the area with the most extensive damage
· it is likely that the pipe had been damaged during its construction i.e. water would be escaping from this pipe network since its construction and possibly finding its way under the building either via the natural slope of the site or through service trenches
· the water inundation of the founding soils would result in "heave'.
While TK indicated the stormwater pipes may have been crushed/broken at the time of construction, he did not provide information to support his view.
EI shared rainfall data which do not show the insured property experienced heavy rains in May 2023. It is unclear when the stormwater pipe broke or the property damage commenced. However, both EI and M concluded one of the causes of the property damage was water escaping the broken stormwater pipes.
It would also be difficult to show the sudden escaped liquid did not exacerbate the movement and cracking to the property within 72 hours discharging from the broken pipes. This could have occurred any time there was sufficient rainfall.
EI initially indicated the soil at the property was moderately reactive. However, M’s comprehensive soil investigations revealed the soil was highly reactive.
M’s detailed soil investigations assisted both parties in analysing the extent of property damage contributed by the claimed event. However, I prefer EI’s analysis and conclusions over M’s outcome. This is because M did not fairly consider all the factors that contributed to the property damage including the cause(s) of the cracking damage identified in 2020. I find EI’s analysis to be logical, thorough and adequate in assessing the likely causes of the damage observed to the property.
The floor level surveys by EI and M show similar movements. M’s floor level performed months after EI’s assessment revealed the foundation movement had worsened over time. EI observed the contours shows a pattern of settlement toward the northern elevation with an isolated heave about the southeast corner of the garage. A total of 135mm of movement was recorded over the length of the residence. The exchanged information shows the foundation movement is not localised to the claimed escape of liquid. This indicates the water escaping from the broken stormwater pipes was not the sole cause of the property damage.
I accept EI’s explanation that differential rates of consolidation settlement can occur on a cut and fill site. This is due to variations in the properties of the soil layers resulting from the excavation and placement processes. This appears to have been a primary cause of the cracking damage observed throughout the property in 2020. F installed an expansion joint across the hallway adjacent to the kitchen in January 2021. There is no information on the extent of cracking observed in 2020 and if the installation of the expansion joint was effective.
I accept:
· the property damage was exacerbated by liquid escaping from the broken stormwater pipes
· the localised heave at the rear of the garage and the settlement of the northern wing of the property have transferred stress throughout the building
· the historical information regarding the insertion of an expansion joint in the ceiling between the hallway and kitchen supports the damage to the property has occurred incrementally over an extended period
· if the plumbing damage had not occurred, the amount of settlement would not have reached the level of structural foundation movement measured onsite.
Given the above, I am satisfied the differential settlement in cut-and-fill is the proximate cause of the movement and cracking which was exacerbated by liquid escaping from the stormwater pipes.
Insurer’s settlement not fair
The complainant seeks the insurer to settle the claim based on M’s scope of works and his builder’s repair quote for underpinning and other repairs. He seeks the following to be included to the settlement:
· reinstate front yard landscaping, retaining walls and portico tiling following underpinning
· timber framing structural inspection
· waterproofing and services inspection
· painting of external path and driveway
· re-sealing of window and external door perimeter and eaves
· reinstate downpipes
· council fees.
The policy explains how the insurer would settle buildings claims:
We’ll normally pay our supplier the necessary and reasonable cost to repair, replace or rebuild the damaged parts of the buildings to a condition substantially the same as, but not better than, when new. Where this happens, you’ll receive our Lifetime guarantee on buildings repairs.
EI estimated the escape of liquid from the broken stormwater pipes contributed to 30% of the resultant damage to the property. While the complainant says all the damage should be attributed to the claimed event, the exchange information does not support this for reasons set out above.
Given my findings above, the insurer’s offer to pay 30% of the total repair cost of the cracking and movement damage to the property is fair in all the circumstances. It is however not liable for repairs relating to the replacement of the broken stormwater pipes and other works required to improve drainage at the property.
I have reviewed the quote prepared by the insurer’s builder AI. This was based on EI’s scope of works amounting to $56,142.55. It is unclear if this quote includes preliminaries and an allowance for builder’s margin.
While M recommended underpinning works, EI recommended repairs with resin injection. EI initially allowed all cracks to be repaired but only allowed cracks greater than 2mm in its supplementary report.
Given the time elapsed since obtaining AI’s quote, the insurer should obtain a new actionable, current and complete quote which includes repair of all cracks (as per EI’s initial scope of works), cost of material, preliminaries and builder’s margin. The insurer is liable for 30% of this revised quote plus an uplift of 20% for transfer of risk and contingences.
2.2 Is the insurer required to pay professional fees?
Yes, mostly. M’s investigations included soil testing and DCP testing which assisted EI’s supplementary submissions. PR’s submissions partially assisted the complainant.
Insurer should reimburse the complainant for expert costs incurred
Under the AFCA Rules, we may require an insurer to reimburse a complainant for professional costs incurred regarding their claim. However, we will not require an insurer to contribute more than $5,000 to these costs, unless exceptional circumstances apply.
AFCA provides a service which is free for complainants. It is not usually necessary for them to be represented. We decide whether the insurer should contribute to these kinds of claimed costs by considering what is fair in the circumstances, considering the complexity of the complaint and whether the complainant genuinely required expert assistance.
The complainant seeks the insurer to reimburse M’s professional fees amounting to $3,995. I acknowledge M did not consider the property’s pre-existing condition in arriving at his conclusions. However, the detailed soil investigations supported EI with its supplementary submissions and me in reaching an outcome for this complaint. It is therefore fair the insurer reimburses M’s professional fees.
The complainant’s claim is reasonably complex given the various factors and sources contributing to the damage. PR’s submission helped the complainant somewhat advance his position with the insurer overturning its initial claim denial and accepting 30% of the repair costs.
Given the above, it is fair in all the circumstances the insurer contributes $500 towards PR’s professional fees provided the complainant submits payment confirmation for the insurer’s review.
2.3 Why is the outcome fair?
The parties are bound by the policy terms and conditions. It would be unfair to require the insurer to cover a loss which does not fall within the scope of the policy.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.