Dispute over ensuite and bathroom repair costs, further temporary accommodation and compensation after sewage escape claim

FirmStrata Community Insurance Agencies Pty Ltd
Decided2026-03-16
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A strata unit owner claimed for sewage damage and disputed the insurer's requirement to renovate the ensuite, further temporary accommodation and compensation. AFCA found for the insurer on all points.

The insurer reasonably required the leak source fixed first, the bathroom works and other items were not insured damage, the property was not uninhabitable under the policy, and delays were outside the insurer's control.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Strata Community Insurance Agencies Pty Ltd determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-192529 | Financial firm | Strata Community Insurance Agencies Pty Ltd Case number: 12-25-192529 16 March 2026 1 Determination overview 1.1 Complaint The complainant, who is a beneficiary under a residential strata insurance policy, lodged a claim with the financial firm (insurer). This is for the damage and the contamination to her unit caused by escape of raw sewage that flooded part of her unit. The complainant was placed in temporary accommodation while the restoration and decontamination work commenced. In October 2024, the insurer advised her that it would not fund any further temporary accommodation, as it considered the decontamination to be complete. The complainant is dissatisfied with the insurer’s handling of the claim and says: · in October 2024, the property remained uninhabitable and she was entitled to further temporary accommodation · the insurer incorrectly advised her that she needed to replace the ensuite and incurred unreasonable costs as a result · the insurer handled the claim poorly. 1.2 Issues and key findings Is the insurer liable for the disputed damage? No. This is because: · the insurer acted reasonably in requiring the source of the ensuite leak to be rectified before commencing the insurable repairs · the main bathroom was not affected by the event, and its renovation was a personal choice · there is no evidence the insurer provided incorrect advice or that the complainant relied on this to her detriment · there is no causal link between the insurer’s actions and the additional disputed items. Is the insurer liable for additional accommodation costs? No. The insurer is not liable for any temporary accommodation costs beyond 20 October 2024. This is because the property was liveable for the purposes of the policy. Is the complainant entitled to compensation? No. The insurer handled the claim reasonably overall. 1.3 Determination This determination is in favour of the insurer. The insurer has fulfilled its obligations under the policy and is not required to take further action. 2 Reasons for determination 2.1 Is the insurer liable for the disputed damage? No. This is because: · the insurer acted reasonably in requiring the source of the ensuite leak to be rectified before commencing the insurable repairs · the main bathroom was not affected by the event, and its renovation was a personal choice · there is no evidence the insurer provided incorrect advice or that the complainant relied on this to her detriment · there is no causal link between the insurer’s actions and the additional disputed items. Parties dispute the ensuite and bathroom repairs Amongst other things, the complainant says: · she was pressured into undertaking complete bathrooms renovations rather than waterproofing the showers · the full bathrooms renovations were unnecessary, and the insurer should contribute to these costs · the tiles in the ensuite were affected by the sewerage, and the insurer should be liable for this portion · she renovated both bathrooms rather than the ensuite only, to avoid any devaluation of the property. The complainant says it was a minor and long-standing leak, which was only discovered when the wall cavities were exposed. The complainant says the applicable standards indicate that repairing the waterproofing within the fully enclosed shower space alone would have been sufficient and compliant. The insurer says for its repairs to proceed, the ensuite leak had to be addressed first. It further states that the policy only responds to damage caused by the escape of liquid, and does not cover any consequential loss. On balance, ensuite leak needed to be addressed prior to the insurable repairs The policy states the insurer will pay up to the sum insured against loss or damage to the insured property. The policy defines ‘Loss or Damage’ as direct physical loss of, destruction of, or damage to property from, any sudden and accidental cause. The insurer’s loss adjuster (EX) initially identified resultant damage from the escape of liquid to the: · built in cabinetry of bedroom 1 and the lounge room · kickboards of the ensuite vanity · gyprock walls and skirting boards in bedroom 1 · skirting board and the gyprock wall lining up to 600mm in the lounge. EX noted that the contaminated water tracked down to the lower level through a penetration in the slab, rather than through the slab itself. EX stated that he could not proceed with repairs to the resultant damage until plumbing repairs addressing the source of the leak were completed. I accept this was reasonable in the circumstances. The insurer’s restorer (PI) identified long-term rusting to the metal framing between the ensuite shower and the built in robe. This is indicative of a failed waterproofing membrane in the ensuite shower. The complainant’s plumber (PA) conducted a spray test to the shower wall. PA observed water entering the wall cavity and leaking onto the floor. I accept addressing the source of the leak before undertaking any repairs is logical and necessary. In his reports dated 12 October 2024 and 17 December 2024, EX stated that the preferred methodology of permanent repair would be to strip out and renovate the ensuite, as the waterproofing cannot be patch- repaired. The waterproofing system must be continuous, and any patch repair, such as the method proposed by the complainant through (MS), would be temporary and would not constitute a permanent or satisfactory repair. The exchanged information shows the complainant fully renovated the ensuite. This aligns with EX’s recommendations to prevent further damage from occurring. I acknowledge the complainant’s argument that she was led to believe if she does not renovate the ensuite, future claims are not going to be covered. EX states that he has explained to the complainant that if an adequate repair was not completed and a future event were to occur, the policy might not fully respond to a new claim due to inadequate repairs. I consider this explanation reasonable and consistent with the need to remediate the underlying defect before insurable repairs could proceed. Further, the insurer’s builder (AD) states that the decision to defer the commencement of the insurable repairs was based on evidence of water damage to the steel framework behind the shower. Proceeding with repair works before resolving the source of the leak would not have addressed the underlying issue and would likely have led to ongoing damage, rendering the repairs ineffective. I accept it was reasonable for the source of the leak to be addressed before the insurer commenced its repairs. Further, I am not satisfied the complainant established that a patch repair to the waterproofing membrane would have been adequate in the circumstances. I am not satisfied that there is persuasive evidence that the insurer erred in its assessment. The insurer is not liable for any maintenance repairs to the ensuite or bathroom I acknowledge that complainant’s argument that the tiles in the ensuite were stained even after PI completed its cleaning. However, EX notes the moisture readings underneath the ties in the ensuite were consistent with those beneath the bathroom tiles, which were unaffected by the escape of liquid event. The moisture readings ranged between 1.8% and 3.1%, which are below the target benchmark requirements. PI observed discoloration in the grout in both the ensuite and the bathroom. There is no evidence that the bathroom was affected by the event. On balance, I accept the tile discolouration in the ensuite is not related to the escape of liquid event. PI concluded that the ensuite’s tiles, tile bed, and underlying concrete were all dry and showed no signs of damage or adhesive failure caused by the insured event. On this basis, PI advised there was no need to strip out the ensuite due to the event. I am not satisfied there is persuasive evidence that the insurer misled the complainant regarding the extent of the maintenance related repairs to the ensuite. The complainant says she was required to renovate the bathroom because a real estate agent advised that upgrading both bathrooms would be preferable if she decided to sell the property. She says the agent told her that prospective buyers would question why only one bathroom had been renovated. The complainant states she therefore chose to renovate the bathroom in line with what she describes as the ‘forced upgrade’ to the ensuite. There is no persuasive evidence the main bathroom was affected by the event. Therefore, I am satisfied the bathroom renovations were not a part of the claim repairs. Conversely, I consider the complainant made a financial decision based on a real estate agent’s advice, not because the policy required or responded to that work. There is no evidence the main bathroom sustained any damage as defined by the policy. In other words, there is no evidence the second bathroom suffered damage from a sudden and accidental cause. Further, I am not satisfied the complainant has established the insurer provided incorrect advice or that she has relied on any error by the insurer to her detriment. Accordingly, I accept the insurer is not required to contribute to or cover the cost of renovating either the ensuite or the bathroom. Insurer is not liable for the other disputed items The complainant submits the insurer is liable for damage for the following items: · broken door to cupboard storing the hot water unit · hot water unit · kitchen tap. The complainant states these items were damaged during the repairs completed by the insurer’s contractors. PA noted that when he attended, the hot water system was removed so he can gain access. On balance, the hot water system was removed prior to the insurer’s attendance. EX states that the hot water system was removed by the body corporate’s preferred trades to facilitate the rectification works. There is no causal link between either the insured event or the insurer’s actions and the resultant issues with the hot water system. The complainant also states the kitchen tap, which was recently installed prior to the event, was damaged as a result of the repairs. She says PI used the kitchen sink to assist with the drying process. EX states that a water extraction line for the dehumidifier was installed in the kitchen. However, this was not near the kitchen tap. Based on the information provided, I am satisfied these items were not damaged by the insurer’s contractors. Therefore, the insurer is not liable for these rectification costs. 2.2 Is the insurer liable for additional accommodation costs? No. The insurer is not liable for any temporary accommodation costs beyond 20 October 2024. This is because the property was liveable for the purposes of the policy. The policy covers temporary accommodation The policy states: (b) Temporary accommodation When a Lot Owner occupies their Lot We will pay the reasonable cost of Temporary Accommodation they necessarily incur if their Lot is made unfit to be occupied for its intended purpose by: (i) Loss or Damage that is admitted as a claim under Section 1; or (ii) reasonable access to or occupancy of their Lot is prevented by damage from an Event claimable under Section 1 happening to other property in the immediate vicinity. I accept the insurer is required to pay the reasonable cost of temporary accommodation if the lot is rendered unfit to be occupied for its intended purpose by loss or damage cover under the terms and conditions of the policy. The insurer is not liable for any further accommodation costs The insurer accepted the claim for the escape of liquid at the complainant’s property. It determined the property was unfit to be occupied for its intended purpose from 27 August 2024 to 20 October 2024 to allow for sanitisation to be completed. The complainant submits the property remained unfit to be occupied after 20 October 2024. This is because the flooring had been stripped, the concrete slab was exposed, sections of walls had been cut out, the toilet was disconnected, there was no furniture, and built‑in cabinetry had been removed. It is not in dispute that the complainant’s contents insurer covered the temporary accommodation costs from October 2024 through to March 2025, and that the insurer’s repairs to the property were completed on 17 April 2025. The complainant now seeks temporary accommodation costs for the period 1 April 2025 to 17 April 2025. While the contents insurer covered the majority of the accommodation period; I will make the following comments for completeness. The insurer says it has relied on the assessment reports and the policy in determining the extent of its liability for temporary accommodation costs. In a report dated 5 November 2024, EX determined the property to be habitable, and the complainant’s contents insurer would step in regarding the temporary accommodation. This is on the basis that the property was adequately cleaned from the sewerage contamination and the repairs could proceed. The evidence exchanged in October 2024 shows that the property had no flooring and the lower sections of the internal walls had been cut out. I have carefully reviewed AD’s scope of works, including the subsequent variations. The required repairs largely involved reinstating plasterboard and painting. Although these works would have caused inconvenience, particularly the absence of flooring, the nature and extent of the damage did not, in my view, render the property uninhabitable. For the purposes of the policy, the threshold for temporary accommodation is higher than discomfort or reduced amenity. Accordingly, I am not satisfied that the insurer was liable to provide temporary accommodation in October 2024, nor that any further liability arose from the later variations. There is no dispute that undertaking the bathroom renovations meant the complainant did not have washing facilities. I accept this would have affected the property’s liveability. However, I am not satisfied the insurer was required to pay temporary accommodation costs arising from the unavailability of cleaning facilities. This is because that was not loss or damage covered by the policy. Based on the evidence before me, including the scope and extent of the outstanding works for the insurable loss, I am not satisfied that the property was uninhabitable or otherwise unable to be occupied within the meaning of the policy. Accordingly, I am not satisfied that the insurer was liable to provide temporary accommodation between 1 April and 17 April 2025. This is because I accept one of the main factors prolonging the repair process was the renovation works to the ensuite and the bathroom. These works, and any associated delays with them, fall outside the scope of the policy. This also applies to the floor replacement, as this was the responsibility of the complainant’s contents insurer. 2.3 Is the complainant entitled to compensation? No. The insurer handled the claim reasonably overall. AFCA takes a conservative approach to compensation AFCA takes a conservation approach to compensation and expects a complainant to bear a normal degree of inconvenience during a claim or when a problem occurs. Under our Rules, AFCA may award compensation for non-financial loss when there has been an unusual amount of: · physical inconvenience · time taken to resolve the situation · interference with a complainant’s expectation of enjoyment or peace of mind. AFCA may reduce the amount of compensation we award if the loss was partially caused by the complainant’s own actions, or by factors outside the insurer’s control. The insurer’s claim’s handling does not warrant compensation The complainant is seeking non-financial loss compensation due to delays in the repairs and the handling of the claim. Amongst other things, she says the initial restorer (FE) was stood down. She states that FE had to chase her for his invoice, and she followed up the insurer on multiple occasions. Both EX and PI stated that FE’s initial restoration were insufficient and PI had to undertake further restoration. It is not in dispute the body corporate, and not the insurer, engaged FE. I accept the insurer was required to assess the reasonableness of FE’s costs. The exchanged information shows the insurer eventually reimbursed the body corporate for FE’s fees. The exchanged information shows: · PI finalised the restoration by October 2024 · the insurer’s repairer (AD) scheduled the repairs between 12 and 17 December 2024 · the repairs were delayed due to the complainant’s private renovation works. By January 2025, the complainant had contracted AD to carry out the maintenance-related repairs before the resultant insurable damage could be addressed. As outlined above, I accept it was reasonable for the insurer to carry out the repairs after the complainant finalised the maintenance related repairs EX advised there were some initial delays, with restoration not commencing until a month after the event. However, this delay occurred because restoration could not begin until the complainant’s contents insurer removed the flooring. This delay was outside the insurer’s control. The exchanged information shows there was a further delay in the bathroom works. However, as noted above, these were private works undertaken by the complainant and were not part of the insured damage. While I acknowledge the claim process was stressful and interfered with the complainant’s peace of mind, the delays were outside the insurer’s control. Therefore, I am satisfied there is no award of compensation warranted in the circumstances. 2.4 Why is the outcome fair? The insurer acted consistently with the policy, responded reasonably to the insurable loss and completed the repairs accordingly. The delays in restoring the property were largely caused by the private renovations undertaken by the complainant, as well as works required by the contents insurer, all of which fall outside the policy. The insurer was not responsible for these delays and was not required to fund temporary accommodation beyond the period during which the property was unfit to be occupied due to contamination. There is no persuasive evidence the insurer acted unreasonably or caused unnecessary delay. Accordingly, no compensation for non‑financial loss is warranted. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.