Home / Suncorp Group / Determination 12-25-188136

Determination 12-25-188136

Storm damage to driveway: complainant sought full driveway replacement and a higher cash settlement than offered

FirmSuncorp Group
Decided2026-04-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$17,990
SourceAFCA PDF

Summary

A storm-fallen branch damaged the complainant's driveway. He sought full resurfacing, but AFCA found the insurer need only repair the damaged section. It required an updated quote at current retail prices plus a 20% contingency uplift to be paid.

The policy covers only damaged parts, not undamaged areas for uniform appearance, but a cash settlement must reflect current retail prices and an uplift for contingencies and loss of lifetime guarantee.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimreassess claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-188136 | Financial firm | AAI Limited Case number: 12-25-188136 19 March 2026 1 Determination overview 1.1 Complaint The complainant held home building insurance with the financial firm (insurer). He lodged a claim after a large tree branch fell during a storm on 27 August 2024, damaging a part of his driveway as well as other external areas of the home. The insurer accepted the claim and paid a cash settlement for the damage to the other aspects of the home. It also offered $1,402.15 to cash settle the cost to repair the damaged driveway section. The insurer says it will not pay to replace the entire driveway surface as the policy only requires it to repair areas that have been damaged, not undamaged areas. The complainant says the insurer should pay for a full driveway surface replacement because the surface is seamless so a patch repair would be unacceptable. He also says J, the company that installed the driveway in mid-2023, has recommended a full replacement to prevent water from seeping into the sub-base. 1.2 Issues and key findings Is the insurer to pay for a full driveway replacement? No. Under the policy, the insurer is only required to repair areas damaged by an insured event and is not obliged to replace undamaged areas to achieve a uniform finish. I am also not satisfied that the damage to the section of the driveway means water will seep into the sub-base unless a full replacement is undertaken. Is the insurer required to pay a higher cash settlement? Yes. The insurer’s offer is based on a quote builder P prepared over 17 months ago. Also, the insurer did not include in its offer an uplift for contingencies and loss of its lifetime guarantee over repairs. The insurer is to obtain an updated quote from P reflecting current retail prices and pay the complainant that amount plus a 20% contingency uplift. Why is the outcome fair? The outcome is fair as it reflects the insurer’s policy obligations but ensures the cash settlement for the damaged driveway section is based on current prices and allows for contingencies. 1.3 Determination This determination is substantially in favour of the insurer. If the complainant provides written notice that he accepts this determination, the insurer is to: · within 14 days of that notice, ask P to provide an updated quote for repair of the damaged section of the driveway which reflects current retail prices · within 14 days of receiving P’s updated quote, provide a copy of it to the complainant and pay him the quoted amount plus a 20% contingency uplift. 2 Reasons for determination 2.1 Is the insurer to pay for a full driveway replacement? No. Under the policy, the insurer is only required to repair areas damaged by an insured event and is not obliged to replace undamaged areas to achieve a uniform finish. I am also not satisfied that the damage to the section of the driveway means water will seep into the sub-base unless a full replacement is undertaken. Background ​​​​Subject to the terms and conditions set out in the product disclosure statement (PDS), the policy covers the complainant for loss or damage to his home caused by a listed insured event. Those events include ‘Storm’. On 28 August 2024, the complainant notified the insurer that during a storm the day before, a large branch had fallen from a tree outside his property. He said the branch damaged his front gates, pillars, and security system and left a big dent in his sealed bitumen driveway. The PDS confirms on page 18 that the insured building includes sealed driveways, outdoor gates, and permanently fixed outdoor items and electrical appliances. The insurer accepted the claim and has paid a cash settlement for all aspects of the damage, except the driveway. While the insurer has also offered a cash settlement for the driveway damage, the complainant disputes its adequacy. Policy sets out extent of insurer’s claim settlement obligations The PDS says on page 75 that if the insurer’s builder is unable to complete repair of covered building damage, the insurer will cash settle the cost of repairs on a ‘new for old’ basis. ‘New for old’ is defined on page 77 of the PDS to mean repairing damaged parts with new items/materials that are reasonably available, regardless of age and with no depreciation allowance. However, ‘new for old’, does not mean repairing to a better standard, specification or quality then when new, or paying extra to replace or purchase an extended warranty. The PDS confirms on page 78 that the insurer will only repair damaged parts where the damage is covered by the policy. Except in limited circumstances (none of which are applicable here), the policy does not cover replacement of undamaged parts. Several examples are given, including that the insurer will only replace damaged roof tiles, not undamaged ones, even if the replaced tiles do not match the undamaged tiles. On page 79 of the PDS, there is an explanation of what happens when the insurer cannot find new materials to match undamaged parts. The insurer will offer to repair using similar new materials. If the insured is not satisfied with the proposed materials they can either: · pay the extra cost of replacing the undamaged part to achieve a uniform appearance, or · receive a cash settlement based on the cost of repairs using the proposed materials. As set out on page 84 of the PDS, where the insurer attends to repairs, the insurer guarantees the quality of the workmanship for the lifetime of the building. Insurer says it is only required to repair a section of the driveway On 17 September 2024, builder P attended the complainant’s home. P confirmed there was impact damage to the bitumen driveway, which had been constructed without any architectural or other breaks in it. The damage was just past the gate. The insurer recorded that the dent in the driveway was 40cm2. On 14 October 2024, P prepared a scope of works (SOW) and quote to repair the damage to the driveway. The work outlined primarily comprised of the following over a 10m2 area: · scrape back and remove loose debris · provide localised repair to substrate (sub-base) as required · supply and install new bitumen. In a desktop report dated 26 June 2025, the insurer’s building coordinator C said: · photos P had taken showed wear and tear erosion of the driveway’s top surface due to traffic travelling over it · such damage was to be expected as it was close to the main entrance to the property, and was unrelated to the tree branch impact · the impact damage had caused cracking to the top surface but appeared to stop where that surface met the exposed second layer · until invasive action is undertaken, it is not possible to determine whether the substrate below the impact area had been affected. However, P had allowed for this in its SOW · what P was proposing was not temporary patching · repairing the impact damage was reasonable, but a full resurfacing was not · the driveway was 432m2 while the impact damaged area was only about 3m2 · with minor localised damage such as the dent in the driveway, it is common practice to repair just the affected area. The insurer says it is entitled under the policy to limit its liability to the cost of repairing the damaged driveway section. It also says it has no obligation to replace the undamaged part of the driveway to achieve a uniform finish. The insurer rejects the complainant’s position that because of the damage, water will seep into the sub-base unless a full replacement is done. Complainant wants the insurer to pay for a full driveway surface replacement J built the driveway in mid-2023 and charged the complainant $39,600 to do so. Following the claim event, the complainant obtained a rectification quote from J totalling $17,990. In the quote, J said: · the storm damage meant a full asphalt restoration, rather than temporary patching, was required · ‘Driveway requires to be fully resheeted, so it doesn’t look like patch works and prevents water from seeping into sub-base'. The complainant submits that: · through no fault of his own, the driveway was damaged by a branch falling from a tree for which the local council is responsible · when the claim event occurred, the driveway was only 12 months old, in excellent condition, and not affected by wear and tear · patching is not a suitable remedy as it is not equivalent to restoring the driveway to its pre-damage condition · ‘The damage is in a prominent location, and any patch would be highly visible – reducing the visual and material quality of the driveway’ · J confirmed that full resheeting is required to prevent water ingress, ensure structural integrity, and maintain surface uniformity · ‘Patching would amount to a substandard, short-term fix’ · as an invasive inspection has not been carried out, whether the sub-base has been damaged cannot be verified · ‘It is not reasonable to expect me to accept an inferior patch repair on a new $39,000 driveway. I simply seek restoration to the condition it was in prior to the damage’. Insurer is not liable for a full driveway replacement Based on the exchanged information, I am not satisfied that the insurer is liable for a full driveway replacement. This is because: · the damaged area of the driveway is 3 to 4m2, although P has allowed for repair of 10m2 · the policy makes clear that the insurer: > will only repair damaged parts where the damage is covered by the policy > is not required to replace undamaged parts to achieve a uniform appearance · therefore, any concerns about the appearance of a patch repair are not a relevant consideration in terms of policy response · in any event, the driveway is bitumen/asphalt and can be repaired with that same material. This means that it is likely that there will be a reasonably consistent appearance · I am not satisfied that P’s proposed works would be a temporary or short-term fix. I find C’s more detailed commentary on that aspect more persuasive than J’s brief reference · J has not explained why the damage means water will seep into the sub-base unless a full replacement is done · images of the driveway indicate it slopes down from the home to the front gates. The damaged area is close to the front gates. It seems unlikely water seepage at that point would travel upwards and affect the sub-base to the undamaged section of the driveway · P has allowed for localised repair to the sub-base if it becomes clear that is required. 2.2 Is the insurer required to pay a higher cash settlement? Yes. The insurer’s offer is based on a quote builder P prepared over 17 months ago. Also, the insurer did not include in its offer an uplift for contingencies and loss of its lifetime guarantee over repairs. The insurer is to obtain an updated quote from P reflecting current retail prices and pay the complainant that amount plus a 20% contingency uplift. ​It is reasonable that the driveway damage is cash settled All other aspects of the claim have been cash settled and it appears both parties prefer to cash settle the driveway damage. In the circumstances and given that the complainant wants the undamaged part of the driveway replaced as well, I am satisfied that it is reasonable that the driveway damage is cash settled. A cash settlement must be based on a reasonable quote for claim related repairs, actionable by a retail customer. An uplift is typically applied to the quoted amount to allow for contingencies and loss of the lifetime guarantee that applies to insurer approved repairs. For the sake of completeness, I acknowledge that the policy says the insurer may cash settle based on an assessed quote for less than what it would cost a retail customer because it is able to secure discounts from its supplier network. However, that does not align with AFCA’s general approach to cash settlement, and I am not satisfied that it is fair in the circumstances. Insurer is required to pay a higher cash settlement than it offered Following receipt of P’s SOW dated 14 October 2024, the insurer offered the complainant the amount P had quoted, $1,402.15, as a cash settlement for the driveway repairs. I am satisfied that P’s SOW reasonably addresses the work required to repair the driveway damage, noting it allows for an area of 10m2 to be repaired, despite the dent being only 3 to 4m2. The SOW also includes items typically paid by a consumer rather than an insurer, such as builder’s mark up and supervision costs. However, the SOW was prepared 17 months ago so will not reflect current retail prices. Also, the insurer’s cash settlement offer to the complainant did not include an uplift for contingencies and loss of lifetime guarantee. Therefore, if the complainant accepts this determination, the insurer is to ask P to update the amounts in its SOW dated 14 October 2024 to reflect current retail prices. It is then to pay the complainant the updated amount plus a 20% uplift which includes an allowance for the possibility localised repair to the sub-base is required. 2.3 Why is the outcome fair? The outcome is fair as it reflects the insurer’s policy obligations but ensures the cash settlement for the damaged driveway section is based on current prices and allows for contingencies. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.