Home / Suncorp Group / Determination 12-25-186335

Determination 12-25-186335

Insurer denied part of an escape of liquid claim (floor tiles and particleboard subfloor); also disputed temporary accommodation, storage, expert costs and non-financial loss

FirmSuncorp Group
Decided2025-07-31
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$155,359
Non-financial loss$10,000
Amount claimed—
SourceAFCA PDF

Summary

Homeowners claimed for escape of liquid damage; the insurer denied damage to floor tiles and some particleboard subfloor. AFCA found the damage was covered and ordered a cash settlement, ongoing temporary accommodation and storage costs, expert costs and $10,000 non-financial loss compensation.

The complainants established a claimable escape of liquid loss extending to the tiles and particleboard, and the insurer's incorrect denial and poor handling caused the TA limit to be exhausted and caused major stress.

Issues

Subjects and remedies

home or building damagemental healthpay claimpay compensationpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-186335 | Financial firm | AAI Limited Case number: 12-25-186335 29 July 2025 Determination overview Complaint The complainants hold home building and contents insurance with the financial firm (insurer). On 29 September 2024, they lodged a claim for damage caused by escape of liquid (EOL) from a burst hot water flexi-hose in the laundry. The insurer partially accepted the claim but denied liability for damage to floor tiles and to some particleboard subflooring. It says the tile damage was not caused by the EOL, and that there is no evidence the particleboard is damaged. The insurer has paid a daily $200 meal allowance in lieu of temporary accommodation (TA), and for contents storage. The complainants say the EOL damaged the entire floor and/or repair of the accepted damage will require a full floor replacement. They want the insurer to pay repair costs based on their quotes, meal/TA and storage costs above the policy limits, expert costs, and compensation. Issues and key findings Is the insurer entitled to deny the disputed damage? No. The damaged particleboard sheets extend under walls and tiled areas. Moisture trapped between the tiles, and the particleboard has caused further damage. The necessary repairs will require removal and replacement of all the tiles and particleboard. Is the insurer to pay ongoing TA and storage costs? Yes. The insurer’s incorrect claim decision has resulted in the TA limit being exhausted before the required repairs are completed. It may also result in exhaustion of the contents storage limit before repair completion. It is to cover those costs up to repair completion. Is the insurer to pay expert costs? Yes. The complainants’ expert reports assisted them to establish their claim for the disputed damage. The insurer is to reimburse the $2,941.50 the reports cost. Is non-financial loss compensation payable? Yes. The insurer has unreasonably caused the complainants major stress and inconvenience. It is to pay each of them $5,000 in non-financial loss compensation. Why is the outcome fair? The outcome is fair because the complainants have established a claimable loss for the disputed damage, and the insurer’s errors and delays justify requiring it to pay ongoing TA and contents storage costs and compensation. Determination This determination is in favour of the complainants. If they accept this determination, the insurer is to:  pay for the required repairs in accordance with section 2.1 below  pay TA costs and contents storage costs in accordance with section 2.2 below  within 14 days of receiving proof of payment from the complainants, reimburse them $2,941.50 for expert report costs  within 14 days of the complainants’ acceptance of this determination pay each of them $5,000 in non-financial loss compensation ($10,000 in total). Reasons for determination The complainants have raised concerns that when their contents are returned from storage, they will be mould affected. As neither of those events has occurred yet, I am unable to address the complainants’ concerns. Nothing in this determination affects their right to pursue a complaint in the future about their contents. Is the insurer entitled to deny the disputed damage? No. The damaged particleboard sheets extend under walls and tiled areas. Moisture trapped between the tiles, and the particleboard has caused further damage. The repairs will require removal and replacement of all the tiles and particleboard. Complainants must show a claimable loss under the policy terms ​​​The complainants are required to show, on the balance of probabilities (that it is more likely than not), that they suffered a loss claimable under the policy. This means they must show the loss was caused by a risk for which they are insured. ​​​Subject to the terms and conditions set out in the product disclosure statement (PDS), the policy covers the complainants for loss or damage to their home caused by a listed insured event. Those events include EOL. On 29 September 2024, the complainants notified the insurer that a hot water flexi-hose in the laundry had burst overnight, resulting in EOL for several hours. The EOL has caused damage in several rooms of the home. The insurer accepted damage to the carpet, wardrobe cabinetry, joinery, plaster, skirting boards, paint, and bedroom floors. To that extent, it has acknowledged that the complainants have shown a claimable EOL loss. However, the insurer says the EOL did not cause damage to floor tiles or to some particleboard subflooring. ​​​Once the complainants prove the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. ​Insurer denied the claim for the disputed damage On 29 September 2024, restorer BB inspected the home. BB reported to the insurer that:  the tiled floors and wall linings in the kitchen, lounge room, hallway, and laundry had elevated moisture levels  bedrooms 1 to 3 had wet and delaminated carpets, and elevated subfloor moisture levels  the bedroom carpets were not restorable, but their particleboard subfloors were  it had removed the carpets and had installed drying equipment. On 1 October 2024, builder RC inspected the home. RC told the insurer that:  the complainants had a continuous hot water system, so the hot water did not run out during the EOL event  there was damage to the particleboard subfloor in the bedrooms and living areas  the particleboard did not appear to have a protective coating on other side to protect it from environmental conditions  the subfloor had been affected by the EOL, but the extent of particleboard deterioration suggested the EOL did not cause all the damage observed  removal of the floor tiles and the kitchen were required to dry the subfloor  there was non-claim related water damage and mould to the bathroom ceiling  it estimated repairs would take six to eight weeks to complete  it recommended a causation report be obtained from an engineer. On 4 October 2024, RC’s plumber performed leak detection testing after the burst flexi-hose was replaced. The only leak detected was water dripping down the wall cavity behind the shower due to unsealed spindle penetrations. Engineer DW inspected the home on 22 October 2024. DW reported to the insurer that:  the condition of the particleboard flooring in bedrooms 1 and 2 was related to elevated moisture and humidity levels in the subfloor space due to the fall of the land and the absence of a suitable surface/subsurface drainage system along the home’s northern side  minor wall and ceiling cracking in the lounge room and kitchen were due to normal building movement, and likely pre-dated the EOL event  the minor floor tile cracking in the lounge room and kitchen was likely from several factors including long-term creep deflection of the suspended timber floor, lack of expansion joints, and other construction defects. The tile cracking likely pre-dated the EOL event  the EOL event resulted in water exposure over four hours. That would be unlikely to cause structural damage to the particleboard flooring or timber floor structure  there was long term water staining and damage to subfloor timber floor joists and bearers not associated with the EOL but related to elevated subfloor moisture and humidity levels  the bathroom’s waterproofing membrane had failed prior to the complainants buying the home, and had not been replaced  ‘The extent of damage/degradation to the particleboard flooring observed is not consistent with moisture exposure from the one-off event. The extent of damage/degradation observed is primarily due to long-term moisture exposure’. On 20 November 2024, BB identified elevated moisture readings and mould in the laundry cabinetry. The mould was cleaned away. BB said that the cabinets would need to be removed to check if there was mould growing behind them. In a report dated 28 November 2024, DW responded to the complainants’ comments on its first report. In essence, DW maintained its position. The insurer’s internal assessor (assessor) prepared a report following a reinspection of the home with RC, the insurer’s internal building co-ordinator, the male complainant and his builder on 18 December 2024. The assessor said:  it was determined that the damaged bedroom particleboard would have to be cut directly against the wall frames/base plates to enable replacement  while the complainant had raised concerns about possible mould behind the kitchen kick panels, restoration work had been completed including to those panels. There were no elevated moisture levels or evidence of mould on completion of the restoration work  the complainant would therefore need to remove the panels and provide images of mould behind them before BB would be re-engaged. Following receipt of the report dated 13 February 2025 by the complainant’s hygienist, RE, the insurer obtained further commentary from the assessor and from BB:  the assessor said the mould that had developed at the home six months after the EOL was more consistent with being caused by the long-term factors DW had identified, lack of adequate subfloor ventilation, and the high local external airborne microbial level  BB said: > RE had not provided thermal images or moisture meter readings to support its claim that moisture between the floor tiles and particleboard had not been adequately dried > based on the moisture results it had submitted to RC, the home had achieved ‘dry goal’ > there were no signs of tile cracking, loose grout, or glue un-bonding between its initial and final inspections, which would suggest moisture was not trapped beneath the tiles > the water staining on the joists, bearers and particleboard when observed from the subfloor area indicated long-term water leakage that had caused damage over time and could lead to mould growth. The insurer maintains that the EOL did not cause damage to floor tiles or to particleboard subflooring other than that in the bedrooms. Complainants say insurer should cover disputed damage Engineer PF inspected the home on 7 January 2025 and reported to the complainants that:  there were signs of moisture on the kitchen floor, and mould on its underside  the cement baseboard showed signs of moisture and deterioration, which may have been caused by water ingress where the kitchen floor tiles did not extend to cover the floor adjacent to the baseboard  water flow towards the home from the driveway (on its northern side) would be insignificant because the driveway slopes away from the home and water would drain towards the street  the exposed areas of particleboard flooring had significant water damage  structurally water damaged flooring sheets extend under internal walls into tiled areas  ‘the damage sustained to the kitchen and living areas was caused by water ingress into these areas. This may have been caused by the [EOL]’. The complainants have also provided a quote dated 2 February 2025 from builder PR for $129,466.04. The quote includes commentary from PR, including that:  as particleboard is laid under the walls and through doorways, and damaged sheets continue under tiles, the tiles and flooring throughout the house must be pulled up  it agreed with RC that removal of floor tiles and the kitchen was required to dry the subfloor  failure to do that had led to long term moisture damage to the subfloor in the tiled areas, with recent tile movement and grout damage having become evident  the damaged flooring sheets the insurer accepted as covered continue under internal walls and damaged sheets extend under tiled areas, necessitating complete removal  untreated high residual moisture levels (measured) in the tiled areas had led to structural damage to the subfloor sheets, necessitating removal of the tiles and the damaged subfloor throughout the home  after that, the remaining structure and the subfloor space would need mould treatment and drying to return moisture levels to normal before repairs could be completed  it had demolished and reconstructed the bathroom. It could confirm that the waterproofing in the old shower area had been correctly repaired and retained its integrity as the insurer’s plumber had demonstrated  the shower spindle penetrations were not sealed correctly but only slightly leaked when a solid water stream was directed at the fitting. They remained dry during normal use  the historical subfloor damage in that area was stable and dry and had been replaced as part of the bathroom renewal. As noted above, the complainants also rely on a report dated 13 February 2025 by hygienist RE, following an inspection of the home on 13 January 2025. RE said:  there was water damage to the particleboard flooring to the bedrooms, kitchen, lounge room and hallway. The particleboard had swollen and lost structural integrity  there was moisture staining, water damage and active mould to the flooring and subfloor  moisture was trapped beneath the tiles on the particleboard and had not adequately dried  moisture remained in the subfloor and required more adequate ventilation after the EOL  moisture levels of the internal areas tested exceeded dry standard  internal airborne microbial concentrations were high but reflected the local environment  a swab taken from damaged flooring in the entry foyer returned a high level of surface mould contamination  it recommended mould remediation be undertaken, including but not limited to removal of all water damaged particleboard flooring. The complainants note the EOL involved 500 Celsius hot water. They estimate that the time from the beginning of the EOL to removal of carpet and completion of mopping up would have been more than 12 to 14 hours. They have provided images and a video of the EOL which show water covering tiled areas of flooring and completely saturated carpeting. They have also provided a photo taken on 20 November 2024 of BB’s moisture meter on the flooring outside the framing of one of the bedrooms, adjoining the tiled hallway and living room area. The meter shows a high moisture reading. This was after extensive drying efforts. In April 2025, the complainants arranged for PR to commence removal of the particleboard sheets in the bedrooms, being areas of damage accepted by the insurer. They have provided photos they say show:  particleboard sheets running under wall frames were structurally unsound, had expanded and/or was falling apart  collapsed particleboard sheets hidden under tiles at the transition from room to room  where the particleboard had broken during tile removal, there were visible wet spots as well as mould spots on top of and within the board’s fibres. The complainants submit that: This Particleboard flooring is no longer structurally sound as a base to support the house structure being walls and roof, or as flooring to support the tile overlay, as evidenced by tile movement and grout cracking since the event…the tiles need to be removed to dry the Particleboard flooring underneath. The tiles are purely collateral damage…the damaged sheets that extend under the walls of the house need to be removed and replaced as they have lost structural integrity to support the house structure, necessitating removal of the adjoining tiles to facilitate access for these structural repairs. Insurer is not entitled to deny the disputed damage I am satisfied that the complainants have established a claimable loss for the disputed damage. The damaged particleboard sheets extend under walls and tiled areas. Moisture trapped between the tiles and the particleboard has caused further damage. The repairs will require removal and replacement of all the tiles and particleboard. This is because:  the insurer has accepted damage to the particleboard in the bedroom  PR and PF confirm that particleboard continues under walls into other rooms and goes under tiled areas  RC, PR and RE confirm that the tiles needed to be removed to enable drying of the particleboard  I am satisfied moisture was trapped between the tiles and the particleboard, leading to further damage. None of the BB reports submitted to AFCA show the moisture levels returned to dry standard, BB’s moisture meter on 20 November 2024 showed a high level, and RE confirmed as at 13 January 2025 internal area levels exceeded dry standard  the images taken after PR commenced work confirm the particleboard is structurally unsound, had collapsed under the tiles, was still wet and was mould affected  considering the matters set out above, I do not find DW’s views persuasive. The only quote submitted to AFCA that addresses all the damage to be covered is PR’s quote dated 2 February 2025 for $129,466.04. As the parties’ relationship has broken down and noting PR has commenced some of the repair work, it is reasonable that the insurer pays a cash settlement based on PR’s quote. A 20% uplift is to be applied to allow for contingencies and loss of the insurer’s lifetime repair guarantee. The amount payable, $155,359.25, is to be paid within 14 days of the complainants accepting this determination. I note that the complainants have confirmed that while PR has commenced the work, they are yet to make any payments to PR. Is the insurer to pay ongoing TA and storage costs? Yes. The insurer’s incorrect claim decision has resulted in the TA limit being exhausted before the required repairs are completed. It may also result in exhaustion of the contents storage limit before repair completion. It is to cover those costs up to repair completion. Policy covers TA and storage costs As set out on page 39 of the PDS, the policy covers reasonable TA costs where the insured home has been damaged by a covered incident to the extent it cannot be lived in. TA costs are covered until the home is repaired to the point where it can be lived in again. The maximum amount payable is 10% of the home building sum insured (in this case, $54,580). Page 44 of the PDS confirms that when covered loss or damage to contents means undamaged contents cannot be kept at the insured address, the. insurer will pay the reasonable cost to transport and store the undamaged contents. The maximum amount payable is 10% of the contents sum insured (in this case, $11,630). Insurer is to pay ongoing TA and storage costs The insurer was paying a daily $200 meal allowance in lieu of TA. It says this was at the complainants’ request. The complainants say that was because the insurer did not offer appropriate accommodation for them and their dogs. Instead, they have been living in their garage. In any event, it appears the insurer ceased paying the allowance in or about late May 2025 as the policy limit had been reached. The insurer has also been paying for storage of the complainants’ contents. As at 18 February 2025, $1,557 of the $11,630 policy limit had been paid. The insurer’s continued denial of the disputed damage despite increasing evidence from the complainants it should be covered has delayed completion of the required repairs. As a result, the TA limit has been exhausted already, and it may be that the contents storage limit is also exhausted before the home is returned to a liveable state. It is therefore fair and reasonable for the insurer to continue to pay for TA costs and for contents storage until the date on which the home will be repaired. As the repair costs are to be cash settled, the TA costs component should be too. The complainants are to obtain a written estimate from PR of when the repairs will be completed. The insurer is to pay a TA cash settlement for the period from when it ceased paying TA, and for future TA based on that estimate at $200/day plus 20%. The insurer is to pay the applicable amount within 14 days of receiving PR’s time estimate from the complainants. The insurer is to continue to pay contents storage costs until the repairs are completed. Is the insurer to pay expert costs? Yes. The complainants’ expert reports assisted them to establish their claim for the disputed damage. The insurer is to reimburse the $2,941.50 the reports cost. AFCA may require insurer to contribute to a complainant’s professional costs The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs incurred by the complainant. These costs are, however, usually capped at a total of $5,000, unless special circumstances apply. When considering whether to require an insurer to make a costs contribution, AFCA considers matters such as the complexity of the complaint and whether the complainant needed to incur costs to understand or establish their claim. Insurer is to reimburse expert costs The complainants’ expert reports have assisted them to establish an entitlement to cover for the disputed damage. It is reasonable to require the insurer to reimburse those costs. The complainants seek reimbursement of $2,941.50 ($1,100 for PO’s report, $1,391.50 for RE’s report, and $450 for PR’s report/quote). On being provided proof of payment by the complainants, the insurer is to reimburse them. Is non-financial loss compensation payable? Yes. The insurer has unreasonably caused the complainants major stress and inconvenience. It is to pay each of them $5,000 in non-financial loss compensation. AFCA can award compensation for non-financial loss ​Under paragraph D.3.3 of its Rules, AFCA may award up to $6,300 in compensation for non-financial loss where the insurer’s actions have caused an unusual amount of physical inconvenience, time taken to resolve the situation, interference with the complainant’s expectation of enjoyment or peace of mind. Where there is more than one complainant, and each complainant suffered non-financial loss, each can be awarded compensation. ​​​​AFCA takes a conservative approach to awarding compensation for non-financial loss. We expect complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. Insurer is to pay non-financial loss compensation The complainants say that the insurer’s poor claim handling, delays and inadequate communications have caused them major stress and inconvenience. They say the insurer’s adversarial approach to the claim made them feel pressured, coerced and deceived. They also say that while the insurer enquired as to their wellbeing, it did not change its conduct. During the claim, the insurer offered the complainants access to counselling. It has also offered them $1,000 in non-financial loss compensation for their claim experience. Having reviewed the exchanged information, I am satisfied the insurer’s claim handling has been poor. That has had a profound impact on the complainants, significantly and detrimentally affecting the personal wellbeing of both of them. In the circumstances but considering the relatively brief time frame since the EOL occurred, it is fair and reasonable to require the insurer to pay each of the complainants $5,000. Why is the outcome fair? The outcome is fair because the complainants have established a claimable loss for the disputed damage, and the insurer’s errors and delays justify requiring it to pay ongoing TA and contents storage costs and compensation. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.