Home / Blue Zebra / Determination 12-24-176243

Determination 12-24-176243

Cash settlement amount for hail-damaged pergola, including cost of replacing flashings

FirmBlue Zebra
Decided2025-10-27
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded$8,982
Non-financial loss—
Amount claimed$8,877
SourceAFCA PDF

Summary

The complainant's pergola was damaged by hail and the insurer offered a cash settlement excluding flashings. AFCA found the flashings had to be replaced to complete repairs and directed a cash settlement of $8,981.50.

Flashings, though not hail damaged, must be replaced to carry out the insured repairs, so their cost falls within the insurer's liability and the policy's upgrade exclusion and uniform finish limit do not apply; a 15% contingency is fair for a cash settlement.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Blue Zebra determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-176243 | Financial firm | Blue Zebra Insurance Pty Ltd Case number: 12-24-176243 23 October 2025 1 Determination overview 1.1 Complaint The complainant held a landlord accidental damage policy with the financial firm (insurer) and lodged a claim for a pergola damaged by a hailstorm on 19 December 2023. The complainant obtained quotes of $8,877 and $7,810 to repair the damage. The insurer says the complainant’s quote includes the cost to repair items which were not damaged by the storm. It says damage is limited to the roof sheeting and has offered a cash settlement based on a quote for replacement of $3,603.60 plus an allowance of $540.54 for contingencies. The complainant says the insurer’s offer is not reasonable, does not allow for replacement of flashings which will be damaged during the course of repairs, and settlement should be based on her quotes. 1.2 Issues and key findings Is the insurer’s settlement offer fair and reasonable? No. The pergola was damaged by hail, and while the insurer accepted the claim, its settlement offer excluded the cost to replace flashings. The exchanged information confirms the flashing must be replaced to complete covered repairs, regardless of their condition. A fair settlement is $8,981.50 based on the complainant’s quote to replace roof sheets and flashing, with a 15% allowance for contingencies. Why is the outcome fair? The outcome is fair because the complainant’s quote reflects the actual cost of necessary repairs due to the insured event. Although the flashings were in poor condition before the storm, there is no indication they did not fulfill their purpose. Given the flashings required replacement to complete the insured repairs, rather than to upgrade or maintain the building, this cost should be included in settlement. Given the potential for cost increases and risk transferred to the complainant via a cash settlement, it is fair that 15% is allowed for these potential contingencies 1.3 Determination This determination is in favour of the complainant. If the complainant accepts this determination, within 14 days of acceptance the insurer should cash settle the complainant $8,981.50. 2 Reasons for determination 2.1 Is the insurer’s settlement offer fair and reasonable? No. The pergola was damaged by hail, and while the insurer accepted the claim, its settlement offer excluded the cost to replace the flashings. The exchanged information confirms the flashing must be replaced to complete insured repairs, regardless of their condition. A fair settlement is $8,981.50 based on the complainants quote to replace roof sheets and flashing, with a 15% allowance for contingencies. No dispute pergola damaged by a storm The complainant lodged a claim for damage to a pergola caused by hail. The complainant’s policy covers buildings and contents if they are accidentally destroyed, lost or damaged during the period of insurance. There is no dispute that the pergola was damaged by hail, with roof sheeting requiring replacement, or that the complainant has established a claimable loss under the policy. The dispute is over whether the insurer’s settlement offer is fair. Complainant’s quotes include cost to replace flashing The complainant provided two quotes. The first, from AL at $8,877, proposes to complete work without the use of scaffolding. It allows to: · remove and replace roof sheets and flashing · replace gutters and downpipes. The complainant’s second quote, from BE at $7,810, allowed for: · removing and replacing roof sheets and flashing · portable scaffolding. The insurer provided one quote, from NE at $3,603.60. This allowed for: · removing and replacing damaged roof sheets · mobile scaffolding. NE’s quote includes site cleaning, waste removal and builders’ margin as separate line items. These items are not described in the complainant’s quotes which are presented as a lump sum and lack itemised costings. However I consider these costs are likely included in the lump sum cost by AL and BE. The main difference between the insurer’s quote and the complainant’s is that NE’s is limited to replacing roof sheets, while the complainant’s quotes include additional works such as flashing, and for AL, replacing gutters and downpipes. Flashing was not damaged by hail The insurer says the condition of flashing was poor prior to the hail event. It has supplied a roof report, prepared by NE, which says flashing to the roof sheets have insufficient lapping and are unsealed. NE also describes split flashing, however based on photographs this issue is with main building rather than the pergola. While both BE and AL quote to replace flashing, each has confirmed this was not on the basis it was hail damaged. Rather, AL quoted to replace as it needed replacement in future, and BE as the existing flashing was not up to standard. The complainant says that hail damage to flashings is visible in images. Having reviewed these photographs, I am unable to discern any markings to the flashings which are clearly related to hail. The flashing is soft and flexible in nature and conforms to the pattern roof sheet. It is not a flat, sheer surface on which indentations are clearly visible. Having reviewed photographs, and considering the consensus of expert opinion, I consider the flashing was in poor condition prior to the event. Further, I am not persuaded the flashing, or gutters and downpipes, were damaged by hail. Flashings must be replaced in order to carry out insured repairs BE says flashings cannot be removed and reinstated once detached. The exchanged information does not include any submissions showing that flashings are typically reused, or could be reused in these circumstances (even if in good condition). While the flashings were not damaged by an insured event, I am satisfied their replacement is a necessary and consequential part of carrying out the covered repairs. Insurer liable for cost of replacing flashings required to enact insured repairs The policy excludes costs associated with upgrading undamaged parts of the building to comply with current building regulations or law. However, this exclusion does not apply here. The replacement of the flashings is not an upgrade or compliance requirement. It is a cost directly incurred to enact the insured repairs, irrespective of regulations or laws. The works cannot be completed without removing and replacing them. The policy also limits the insurer’s liability for repairing or replacing undamaged items to achieve a uniform finished with insured repairs. This limit is on the voluntary replacement of undamaged areas to achieve aesthetic consistency. It does not apply to undamaged parts of the building which must be replaced to achieve insured repairs. I accept the flashings had insufficient lapping, were unsealed, and their replacement was considered a sensible option by all builders. However, I also note there is no evidence they did not serve their purpose prior to the storm given there is no evidence of wood rot or other damage shown to be related to their condition. In that sense they remained a functional part of the structure. While AL says replacement would be required in future, there is no timeframe attached. There is no indication the complainant was intending to replace them at any stage soon, and while I accept replacement was required in the future, I am not satisfied they would not have served their purpose for an extended period despite their overall condition. While the flashings may have needed replacement at some future point, the information provided does not show it was necessary now other than to complete the covered repairs. I am therefore satisfied the insurer’s liability extends to the cost of removing and replacing the flashings as part of reinstating the damaged roof sheets, even if the flashings were in poor condition. This is because their replacement is necessary to enact the insured repairs, rather than to improve or maintain the property, or bring it into compliance. Insurer is not liable for gutters or downpipes Neither the complainant or any expert says the gutters and downpipes were damaged by the storm, or require replacement to complete the covered repairs. While this issue is not in dispute, for completeness, I note the insurer is not liable for their replacement. Insurer should cash settle repairs based on complainant’s quote AL has confirmed that NE’s quote is reasonable for replacing roof sheets and all associated works. BE says NE’s quote is reasonable for replacing roof sheets only, suggesting an additional $800 allowance for mobile scaffolding labour given difficulties posed by the block. I am satisfied NE’s quote is fair, however NE is unwilling to carry our repairs and its quote does not include the cost of replacing flashings. The quote from AL includes the cost of replacing gutters and downpipes which were not damaged by the storm, and do not require replacement. The BE quote allows for replacing the roof sheets and flashing, and includes the cost of scaffolding (as does NE). I am satisfied BE’s quote should form the basis of settlement given it is willing to carry out the work, and has only quoted for the required repairs. BE quotes $7,810 to complete the works. The quote is dated 6 September 2024. Noting the potential for construction costs to have increased since September 2024, and the transfer of risk to the complainant in declining to carry out repairs, for the purpose of settlement it is fair that the insurer pay the complainant an additional 15% for contingencies. In my view the insurer’s settlement offer was not fair or reasonable. This is because it did not allow for the replacement of flashings required in order to complete insured repairs. A fair settlement is $8,981.50, being the cost of replacing roof sheets and flashings quoted by BE, plus a further 15% to allow for contingencies. 2.2 Why is the outcome fair? The outcome is fair because the complainant’s quote reflects the actual cost of necessary repairs. Although the flashings were in poor condition before the storm, there is no indication they did not fulfill their purpose. Given the flashings required replacement to complete the insured repairs, rather than to upgrade or maintain the building, their cost should be included in settlement. Given the potential for cost increases and risk transferred to the complainant via a cash settlement, it is fair that 15% is allowed for these potential contingencies 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy terms How we settle your claim - buildings When your buildings are destroyed or damaged during the period of insurance we will ordinarily pay for the cost of repair or replacement with new material. We may not always be able to repair or replace your buildings, for example: · if the materials needed for the repair or rebuild are not readily available; · if the repair or rebuilding cannot commence for a significant amount of time; for example, due to availability of service providers; · if the pre-incident condition of the buildings prevents us from repairing or rebuilding them; · if the event insured under this policy makes the land unsafe to build on; for example, after an earthquake; or · if any buildings or any part thereof (including subsequent alterations or renovations) did not comply with local government or other statutory requirements at the time of construction (that you could have reasonably been expected to be aware of), for example, the building was never approved by council or correctly certified, or renovations were not built in line with the relevant building code at the time. In such situations, we will pay the cash settlement value in respect of your claim or part of it.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.