Delay in rectifying defective storm and bathroom repairs, and amount payable to settle the claims
Text of the determination
Determination
|
Case number
|
12-24-174469
|
Financial firm
|
Insurance Australia Limited
Case number: 12-24-174469 14 January 2026
1 Determination overview
1.1 Complaint
The complainant held a home insurance policy with the financial firm (the insurer). In 2020, she lodged claims for damage to her roofs (the storm claim) and her bathroom (the bathroom claim). The insurer accepted the claims and repaired the damage. The repairs were defective.
In 2021, the insurer offered to rectify the repairs, but the complainant did not allow this. The insurer offered to pay the cost of the work, but the complainant was not satisfied with the amounts offered. In 2025, the complainant sold the property without repairing it.
The complainant says the insurer caused long delays in arranging the rectification work. She says the insurer should pay for losses she suffered because of the delays, including increases in building costs from 2021 to 2025 and additional damage that occurred because the defects were left unrectified. She says the insurer should pay $534,025.62, being:
· $341,725.62 for the cost of rectifying the defective repairs
· $150,000 for the reduction in the sale price of the property
· $31,000 for lost income (due to the time spent managing the claims)
· $6,300 for non-financial loss (stress, inconvenience, and delay)
· $5,000 for the cost of pursuing this AFCA complaint.
The insurer has made settlement offers ranging from $180,000 to $266,759.89.
1.2 Issues and key findings
Did the insurer delay repairs?
No. The insurer offered to repair the property or pay the cost of repairs. The complainant did not allow the insurer to arrange repairs and did not arrange repairs herself.
What should the insurer pay for repairs?
A fair estimate of the cost of repairing all outstanding claim-related damage is $198,783.38. The insurer should pay this amount to settle both claims.
Is the insurer required to pay other compensation?
No. Besides the defective repairs, the insurer was not responsible for any errors that caused the complainant to suffer a loss.
Why is the outcome fair?
It is fair for the insurer to pay the cost of rectifying its defective repairs. However, it would not be fair for the insurer to pay for delays which were out of its control.
1.3 Determination
This determination is in favour of the insurer.
The insurer is entitled to settle the claims by paying $198,783.38.
2 Reasons for determination
2.1 Did the insurer delay repairs?
No. The insurer offered to repair the property or pay the cost of repairs. The complainant did not allow the insurer to arrange repairs and did not arrange repairs herself.
Insurer’s repairs were defective
On 13 November 2020, the complainant lodged two claims with the insurer. One claim was for damage to roofs caused by a storm on 31 October 2020 (the storm claim). The other claim was for damage caused by a leaking bath pipe on 9 November 2020 (the bathroom claim).
The insurer appointed a builder to repair the roofs and the bathroom.
On 21 July 2021, the insurer’s building consultant prepared a report saying the roof repairs and the bathroom repairs were defective. The insurer accepts the repairs were defective. This means the insurer was required to rectify the repairs or pay the complainant the cost of rectification.
Complainant wanted payment for cost of rectification
The insurer obtained rectification quotes from two other builders (CBS and SKO). CBS quoted $82,650.17 for roof rectification and $18,016.94 for bathroom rectification. SKO quoted $87,088.74 for roof rectification and $18,054.17 for bathroom rectification.
On 15 October 2021, the insurer emailed the rectification quotes to the complainant and asked if she wanted to ‘proceed with repairs’ (i.e. allow the insurer to appoint a builder to rectify the repairs) or ‘proceed with a cash settlement’ (i.e. have the insurer pay her the cost of rectification). The complainant did not say whether she wanted repairs or a cash settlement. She says this is because she asked the insurer detailed questions about the work included in the quotes and the insurer did not provide satisfactory answers.
In September 2021, the complainant says she did not trust the insurer’s builders, and she was considering ‘getting a cash settlement so we could engage builders that I could trust’. By November 2021, the complainant says the insurer knew she intended to seek a cash settlement.
In July 2022, the insurer offered to pay a cash settlement to settle the storm claim. The complainant said she was happy to accept the offer, and asked if the insurer would also pay a cash settlement for the bathroom repairs. By this time, it was clear she would not allow the insurer to rectify the repairs, but would accept a cash settlement for the cost of rectification.
Insurer not responsible for delay after July 2022
By July 2022, the complainant had decided she would not allow the insurer to repair the property. This means arranging repairs was the complainant’s responsibility, not the insurer’s.
The insurer did not prevent the complainant from repairing the property. Therefore, the insurer is not responsible for any delay in repairing the property from July 2022.
The complainant says she started seeking quotes in November 2022. She found it difficult to obtain quotes because there had been major flooding in the area in February 2022, and most builders were busy. She could not obtain any quotes until March 2023. She then continued to obtain quotes until March 2024.
The panel accepts the complainant had difficulties obtaining quotes for reasons outside her control. However, the insurer offered to repair the property in 2022. The complainant chose to decline this offer and accept the burden of arranging repairs herself. Furthermore, the complainant did not start repairs when she started to receive quotes in March 2023. She left the property unrepaired until she sold it in April 2025.
For the above reasons, the insurer is not responsible for any delay in repairing the property from July 2022. Therefore, the insurer is not required to pay for:
· any increase in building costs from July 2022
· any additional damage that occurred because the complainant left the property unrepaired.
2.2 What should the insurer pay for repairs?
A fair estimate of the cost of repairing all outstanding claim-related damage is $198,783.38. The insurer should pay this amount to settle both claims.
Insurer offered $138,359.08 to settle storm claim
On 18 May 2022, the insurer offered to settle the storm claim by paying $82,650.17 for roof repairs (CBS quote dated 16 February 2022) and $2,985.40 for cladding replacement (CBS quote dated 24 December 2021).
On 27 June 2022, the complainant obtained a quote from a builder (NB) for $42,114.05 for cladding replacement. On 6 July 2022, the insurer offered to pay $42,114.05 for cladding replacement, in addition to the above amounts.
On 18 July 2022, the complainant said she was happy to accept the insurer’s offers. However, on 7 October 2022, she said she believed the quotes were outdated and she wanted them increased.
On 29 August 2023, the insurer reviewed CBS’ quote for roof repairs. The quote said the area of the garage roof sheets to be replaced was 132m2, but calculated the cost of this work based on an area of 71m2. The insurer said the value of the work mistakenly omitted from the quote was $9,609.46. The insurer offered to pay this in addition to the above amounts.
Insurer offered $32,261.21 for additional damage relating to storm claim
On 27 September 2022, water entered the building during a storm. This damaged the kitchen ceiling, rear patio ceiling, and upstairs bathroom window. The insurer’s loss adjuster said this occurred because of the defective roof repairs.
On 31 October 2022, the insurer obtained a quote from another builder (ADV) for $32,261.21 to repair the damage. The insurer offered to pay this amount for the additional damage that occurred because of the defective roof repairs.
The insurer says it is not responsible for any damage that occurred because of the complainant’s failure to rectify defects. However, it has maintained its offer to pay for the damage caused by the storm on 27 September 2022. It has not provided information showing a reasonable person in the complainant’s position would have rectified the defective roof repairs before 27 September 2022, preventing the damage.
The panel considers it fair for the insurer to pay for the damage caused by the storm on 27 September 2022.
Insurer offered $18,262.46 to settle bathroom claim
On 29 September 2021, CBS quoted $18,016.94 for bathroom rectification.
On 19 September 2022, CBS prepared an updated quote of $18,262.46 for bathroom rectification. On 30 September 2022, the insurer offered to pay this amount to settle the bathroom claim.
Complainant has not shown 2022 quotes were insufficient
The complainant appointed a builder (GB), who inspected the property and prepared a report dated 15 September 2024.
GB’s report said the cost of repairs had increased significantly since 2022. As stated above, the insurer is not responsible for these cost increases.
GB prepared a supplementary report dated 3 March 2025 saying the property had deteriorated due to the lack of repairs since 2022. As stated above, the insurer is not responsible for this damage.
GB’s report said the quotes obtained in 2022 were insufficient at the time they were prepared. However, it did not provide any persuasive evidence to show this.
GB’s report said the 2022 quotes did not include specialised coastal-grade materials such as Colorbond Ultra, or a roof insulation blanket such as Anticon. CBS’ quotes for roof repairs included new Colorbond Ultra roof sheets and a new Anticon blanket.
GB’s report said the 2022 quotes did not include painting or waterproofing. CBS’ quote for bathroom repairs included painting and waterproofing.
The complainant has not provided other information showing the insurer’s quotes were insufficient at the time they were prepared.
The complainant obtained quotes that were higher than the insurer’s quotes. However, this does not prove the insurer’s quotes were insufficient at the time they were prepared. The insurer’s quotes were actionable; the complainant had the option of having the insurer’s repairers perform the quoted work. It is fair to settle the claims based on the insurer’s quotes.
No contingency for transfer of risk
When an insurer settles a claim by repairing damage, it guarantees the quality of the repairs. If the repairs are unsuccessful, or cause additional damage, the insurer is responsible for the cost of rectification. When the insurer settles a claim by paying the cost of repairs, it transfers this risk to the customer. Furthermore, the customer may find it more difficult and expensive to arrange repairs, because they do not have the insurer’s industry knowledge and bargaining power.
AFCA considers that if an insurer chooses to cash settle a claim, it should consider paying an allowance for the transfer of risk. Generally, AFCA considers that a reasonable allowance is likely to be between 5% and 25% of the quoted cost of repairs.
In this case, the insurer is not required to pay an allowance for the transfer of risk, because:
· the insurer offered to repair the damage
· the complainant sold the property without repairing it, so she did not incur any risk associated with arranging repairs.
Insurer should settle claims by paying $198,783.38
For the above reasons, the panel considers it fair for the insurer to settle the claims for a total of $198,783.38, being:
· $93,550.80 (CBS quote for roof repairs, 19 December 2022; updated version of original quote for $82,650.17 dated 16 February 2022)
· $9,609.46 (garage roofing mistakenly omitted from CBS quote)
· $2,985.40 (CBS quote for cladding replacement, 24 December 2021)
· $42,114.05 (NB quote for cladding replacement, 27 June 2022)
· $32,261.21 (ADV quote for water damage, 31 October 2022)
· $18,262.46 (CBS quote for bathroom repairs, 19 September 2022; updated version of original quote for $18,016.94 dated 29 September 2021).
2.3 Is the insurer required to pay other compensation?
No. Besides the defective repairs, the insurer was not responsible for any errors that caused the complainant to suffer a loss.
Insurer not responsible for reduction in property sale price
The complainant sold the property without rectifying the defects in April 2025.
Immediately before the sale, the complainant said the unrepaired defects would reduce the sale price by about $800,000. She also said the unrepaired defects had delayed the sale, which increased her tax liability by about $140,000 per year. She asked the insurer to compensate her for these losses by paying $150,000 (in addition to paying the cost of the outstanding repairs).
The insurer has agreed to pay the cost of repairing the defects. It would not be fair for the insurer to pay for the reduction in property value in addition to paying the cost of repairing the defects.
As stated above, the insurer is not responsible for any delay in repairs from July 2022. Therefore, the insurer is not required to pay compensation for any reduction in the sale price of the property, or any increase in the complainant’s tax liability, caused by the delay.
Insurer not required to pay for professional costs
Under the AFCA Rules, we can require an insurer to contribute to professional costs a complainant incurred in making a complaint. We cannot award more than $5,000 for professional costs unless there are special circumstances. In considering whether an insurer should contribute to a complainant’s costs, we consider whether they were reasonably incurred, and whether they helped resolve the complaint.
The complainant appointed a builder (GB) to inspect the property and prepare reports on the cost of repairs. GB issued invoices totalling $3,588.55 for this work.
Much of GB’s reports were about increases in the cost of repairs after 2022. This was only relevant because the complainant did not repair the property, and did not allow the insurer to repair the property, in 2022. GB’s first report said the quotes obtained in 2022 were insufficient at the time they were prepared, but the reasons it gave for this conclusion were incorrect.
GB’s reports did not help resolve the complaint. The insurer is not required to contribute to the cost of appointing GB.
Insurer not required to pay for complainant’s representative
The complainant was represented by a family member or friend.
The complainant says her representative spent approximately 775 hours over two years managing the claims on her behalf. She says the time spent managing the claims, and the stress this has caused, reduced her representative’s earning potential. She seeks compensation of $31,000 for lost income and $6,300 for non-financial loss.
AFCA can award compensation to a complainant for indirect financial loss (including loss of income) and non-financial loss (stress, inconvenience, and delay) caused by an insurer mishandling a claim. The complainant did not live at the insured property and had little personal involvement with the claims. The available information does not show the complainant suffered any indirect financial loss or non-financial loss relating to the claims. The complainant’s representative is not a complainant, so AFCA cannot award any compensation to her.
The complainant says her representative has spent at least 200 hours managing this AFCA complaint. She seeks $5,000 for the costs of pursing this AFCA complaint.
As stated above, AFCA can require an insurer to contribute to professional costs incurred by a complainant in the course of a complaint. However, the available information does not show the complainant paid her representative to manage this AFCA complaint. The insurer is not required to pay for the time spent by the complainant’s representative managing this AFCA complaint.
Insurer not required to pay interest
Section 57 of the Insurance Contracts Act 1984 (Cth) says an insurer must pay interest on a claim settlement payment from the time it was unreasonable to have withheld payment.
The insurer offered to rectify the defective repairs or pay the cost of rectification. The insurer did not pay the complainant because she did not accept the insurer’s settlement offers and did not provide bank details enabling the insurer to pay her.
The insurer has not unreasonably withheld payment. Therefore, it is not required to pay interest.
2.4 Why is the outcome fair?
It is fair for the insurer to pay the cost of rectifying its defective repairs. However, it would not be fair for the insurer to pay for delays which were out of its control.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:
· an ombudsman
· a member with extensive experience in consumer and small business advocacy
· a member with extensive experience in insurance.
Complainant represented by family member or friend
The complainant was represented by a family member or friend. In this determination, statements by the complainant’s representative are treated as if they were made by the complainant.