Home / Allianz Australia / Determination 12-24-170564

Determination 12-24-170564

Insurer declined additional variation claim of $8,580 for electrical work to relocate the Point of Access after paying $1,980 for the same works

FirmAllianz Australia
Decided2025-05-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$8,580
SourceAFCA PDF

Summary

The complainant claimed a second variation of $8,580 for relocating the Point of Access after the insurer had cash settled this work for $1,980. AFCA found the insurer entitled to deny the additional claim and found no delay.

The works were already cash settled and the complainant provided no evidence to justify the substantially increased cost, so he did not establish a basis for further payment.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-170564 | Financial firm | Allianz Australia Insurance Limited Case number: 12-24-170564 6 May 2025 Determination overview Complaint The complainant held a home and contents insurance policy with the financial firm (insurer) and lodged a claim for damage. The insurer accepted liability for the claim and paid a cash settlement. The issue in dispute is a variation claim of $8,580 for electrical work due to the current Point of Access (POA) being non-compliant. The insurer says it has already paid the variation claimed, and denies the claim is covered by the policy. The complainant says the expenses are related to the insured event because the non-compliance would have remained undetected but for the insured event. The complainant is represented. In this determination, the complainant and his representative are referred to as ‘the complainant’ unless context requires otherwise. Issues and key findings Is the insurer entitled to deny the claim? Yes. The complainant has not provided any information to justify the increased costs associated with moving the POA following the first variation claim of $1,980 on 3 August 2023. Has the insurer delayed the claim? No. The insurer received and determined the claim on 25 June 2024 and 30 July 2024 respectively. There is no information to show the insurer delayed the claim. Why is the outcome fair? The insurer has paid $1,980 to move the POA in addition to the initial payment of $396 for tiger tails in settlement of these works. The complainant has not established a basis as to why the insurer should now pay a substantial increase for these costs. The insurer’s decision to deny the additional variation claim is therefore fair. Determination This determination is in favour of the insurer. The insurer is entitled to deny the additional variation claim. It is not required to take any further action. Reasons for determination Is the insurer entitled to deny the claim? Yes. The complainant has not provided any information to justify the increased costs associated with moving the POA following the first variation claim of $1,980 on 3 August 2023. Complainant has shown a claimable loss under the policy The complainant is required to show, on the balance of probabilities (that it is more likely than not), that he suffered a claimable loss under the policy. This means he must show the loss was caused by a risk for which he is insured. Subject to the terms and conditions set out in the product disclosure statement (PDS), the complainant’s policy covers his home and contents for loss or damage caused by one or more of the insured events listed in the policy. The insurer accepts the complainant sustained damage caused by an insured event. On 5 July 2023 the insurer paid the complainant $51,817.97 based on a scope of works provided by CBS dated 5 June 2023. The settlement included a payment of $396 for the supply and installation of tiger tails, inclusive of a 20% margin and GST. The complainant says the insurer should accept the second variation On 3 August 2023, the complainant sought a variation of $4,118.40 for items including ’POA Relocation Charge‘ of $1,500. At the request of the insurer the complainant provided quotes from ACB (builder) dated 1 and 25 August 2023 that stated: POA Relocation Charge. Please Note – if the existing property power fuse is located at the house connection point there may be additional charges applicable. The fuse will need to be relocated into the street pole in accordance with workplace health and safety requirements 1/PS @ $1,500 The complainant also provided a report from the electricity provider which states an electrical contractor was required. The complainant did not provide a report from an electrician. The insurer accepted the claim for the POA relocation charge and cash settled that claim for $1,980, being the $1,500 claimed, plus GST, plus a 20% margin. Accordingly, after payment of the first variation, the insurer had paid $2,376 for electrical works including moving the POA. It is unclear whether the tiger tails quoted by CBS dated 5 June 2023 was an alternative to moving the POA. On 25 June 2024 the complainant made a claim for a second variation of $8,580 for the POA relocation. In support of the claim the complainant provided a 'variation report and quotation‘ from ACB dated 21 June 2024 that states: POA Relocation - After receiving electrical safety advice, the report revealed unsafe and unforeseen conditions with the POA. [Energy company] recommended engaging an electrician to relocate the fuse to the main pole to facilitate the work. Consequently, a variation has been raised to allow for the relocation of the POA. Supporting Documentation: Electrical Report In [ACB] professional opinion, we have determined that the following additional works are required in conjunction to our Scope of Works to bring the property to a pre-event condition and to complete the overall works within accordance to the current BCA / NCC. The complainant later provided a quote of $6,500 plus GST from CG (electricians). There is no information to show: the complainant has or will incur costs exceeding $1,980 for the POA removal and/or electrical work that any electrical work has been performed at the property whether the need to move the POA was in addition to, or an alternative to the tiger tails quoted by CBS why the complainant accepted the first cash settlement when ACB included a claim of $1,500 in their initial quote for POA relocation charge why the complainant did not submit a quote from an electrician when the second variation claim was made in August 2023 why the current claim was not made until June 2024 The insurer denies the claim There is no dispute the insurer paid $1,980 (inclusive of margins and GST) to cash settle the claim for moving the POA when it partially accepted the variation claim. The insurer now denies the claim saying the need to move the POA was not caused by an insured event. Insurer has shown it is entitled to deny the additional variation sought On 3 March 2025 the complainant submitted: the work was necessary to ensure the property was compliant and the works could be performed the insurer initially accepted a variation for the POA relocation the POA and switchboard were deemed non-compliant following the storm event the insurer is required to ensure compliance with the relevant standards the PDS does not explicitly exclude compliance costs. I accept the insurer is liable for the cost of moving the POA if this work is necessary to ensure remediation works can take place. However, the insurer cash settled the claim for these works. This included the complainant’s quote of $1,500 (exclusive of GST) to relocate the POA and the CBS quote of $300 (exclusive of GST) for tiger tails without the need to relocate the POA. It ultimately paid $1,980 to move the POA based on a quote from ACB dated 1 August 2023. The following year a subsequent claim was made for $8,580 inclusive of GST and margins, without any information from the builders to substantiate the large increase. The complainant also relied on a quote from an electrician. However, this did not state why the costs had increased. There is no dispute the parties settled the variation required to relocate the POA. No information has been provided to justify why ACB’s cost to relocate the POA increased from $1,500 plus GST to $6,500 plus GST, and/or whether the tiger tails quoted in the CBS quote would not be incurred if the POA was moved. In such circumstances when these works were cash settled, the complainant has not established a basis for the insurer to pay for additional costs for these works. Has the insurer delayed the claim? No. The insurer received and determined the claim on 25 June 2024 and 30 July 2024 respectively. There is no information to show the insurer delayed the claim. Insurer did not delay the claim The parties agree a claim was made for the variation on 25 June 2024. The insurer says the claim was supported by a report for solar panel damage to another property, consistent with a report on file dated 24 April 2024 from CG for another property. The complainant’s representative says on 25 June 2024 they were informed the variation had been sent to the loss adjuster for review. The insurer says on 15 July 2024 the loss adjusters responded to the insurer and further enquiries were made with the electricians who provided the initial quote. On 25 July 2024 the insurer requested information to determine the cause of the defect. That information was provided and on 30 July 2024 the claim was declined. Given the history relating to the POA, including the initial claim that was cash settled in July 2023, the subsequent payment on 16 November 2023, and third claim for the POA in June 2024, it was not unreasonable for the insurer to make the enquiries that it did. Once it received information in response to those enquiries it responded to the claim in a reasonable timeframe. Accordingly, I cannot identify any unreasonable delays caused by the insurer. Why is the outcome fair? The insurer has paid $1,980 to move the POA in addition to the initial payment of $396 for tiger tails in settlement of these works. The complainant has not established a basis as to why the insurer should now pay a substantial increase for these costs. The insurer’s decision to deny the additional variation claim is therefore fair. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.