Insurer declined cover for storm/flood-related sinkhole, bridge and further home damage, claimed as total loss of home
Text of the determination
Determination
|
Case number
|
12-24-167425
|
Financial firm
|
RACQ Insurance Limited
Case number: 12-24-167425 29 April 2026
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents insurance policy underwritten by the financial firm (insurer). She says on or about 5 April 2024, storms and flooding caused damage to the home. The complainant lodged a claim.
The insurer partially accepted the claim. It offered to pay $60,775.61 for damage caused to the home. However, the insurer will not cover other damage to the building or the property (disputed damage) which it says was not caused by the storm/flooding events.
The complainant disagrees with the insurer. She seeks cover for the building sum insured ($600,000) and demolition costs ($120,000), plus costs and compensation in resolution of the complaint.
1.2 Issues and key findings
Is the insurer required to cover the disputed damage?
No. Based on the exchanged information, the complainant has not shown the dominant or effective cause of the disputed damage was the storm/flooding events. On balance, the proximate cause of the disputed damage were historic factors not related to the events or covered by the policy.
Is an award of compensation warranted?
No. The complainant was unsuccessful. It would not be fair to require the insurer to cover her costs. The insurer also did not cause undue delays or otherwise mishandle the claim.
Why is the outcome fair?
The complainant has not shown the disputed damage was claimable under the policy. It would not be fair to require the insurer to cover damage which was first noticed prior to policy inception or that it is not otherwise required to cover under the policy.
1.3 Determination
This determination is mostly in favour of the insurer.
The insurer is required to pay the complainant $60,775.61 if it has not already done so. It must also pay a contingency uplift for this settlement of 40%, being an additional $24,310.24.
As she was largely unsuccessful in her complaint, the insurer is not required to pay any of the complainant’s incurred fees. It is also not required to pay compensation for non-financial loss.
2 Reasons for determination
The complainant is represented by loss adjuster RL. For convenience, unless indicated otherwise, reference to ‘the complainant’ will include both.
2.1 Is the insurer required to cover the disputed damage?
No. Based on the exchanged information, the complainant has not shown the dominant or effective cause of the disputed damage was the storm/flooding events. On balance, the proximate cause of the disputed damage were historic factors not related to the events or covered by the policy. The insurer is entitled to rely on its earlier offer for settlement.
Complainant seeks cover for the total loss of her home
The complainant purchased the insured home in November 2023. It is a two-storey construction, built on a concrete slab in or about 1973. The home is situated adjacent to a creek, which runs behind the home.
The complainant took out cover with the insurer on 22 January 2024. Less than three months later, on 6 April 2024, she lodged a claim for storm and flooding damage.
The insurer agreed to cover some damage ($60,775.61) based on its initial inspection. Other damage was not covered, including for the development of sinkholes in the backyard, the loss of a footbridge and further home movement damage after the initial loss (disputed damage).
Whilst the complainant initially sought cover for the failure of a retaining wall, this has since been withdrawn.
The insurer says the loss is not covered because the proximate cause of this damage was:
long-term scouring and washing-away of the pipework backfill due to inadequate surface drainage.
Damage can have more than one cause. The proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss.
The insurer says the disputed damage was not caused by the claimed event. It offered to pay $60,775.61, based on quotes from its builder, less the policy excess to resolve the claim. There is no dispute the parties have come to an agreement in relation to the contents claim.
The complainant maintains the offer for building damage is inadequate. She says the home is dangerously unstable and unliveable.
The complainant was informed prior to this determination that AFCA’s jurisdictional limit for an award cannot exceed a principal sum of $631,500. She agreed to proceed with her complaint understanding that to be the case.
Onus on complainant to establish claimable loss
The complainant bears the onus of establishing, on balance, that she suffered a loss caused by an event covered under the policy. If the complainant establishes a claimable loss, the onus then shifts to the insurer to demonstrate, on balance, that it is entitled to:
· rely on a policy exclusion, or
· otherwise reduce its liability or decline the claim.
The reference to establishing issues ‘on balance’ means the relevant party must show it is more likely than not.
Policy covers listed events subject to terms, conditions and exclusions
The terms of the policy include the Certificate of Insurance and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainant.
The policy covers damage caused by one of the listed events during the period of insurance. It does not provide cover for all damage. Amongst these events is cover for loss or damage caused by a storm or a flood.
As there is no dispute the home was subject to storm and flood damage, the principal issue is whether the disputed damage was:
· caused by or related to the initial events which the insurer covered, or
· caused by a separate event which the policy also covers, or
· unrelated to the claimed events and not covered under the policy.
Any cover provided by the policy is subject to its terms, conditions and exclusions.
Insurer’s experts consider disputed damage is not covered under the policy
It is not in dispute the storm was significant. 194.8mm of rain fell within a 24-hour period to 9.00am on 6 April 2024 and flash flooding (or possible riverine flooding) occurred as a result. The insurer says it is prepared to cover the damage from these events.
Builder AG was the first to inspect the home on 7 April 2024. It noted there was extensive damage. AG undertook ‘make safe’ work and the complainant was moved out of the home into temporary accommodation.
On 11 April 2024, AG returned to the property and was alerted to a ‘giant sinkhole’ at the rear. The complainant says this emerged on or about 6 April 2024, though it was not noted in AG’s first report. AG recommended the appointment of an engineer.
The insurer appointed engineer IL. IL’s report after its attendance on 9 May 2024, found:
· retaining walls at the rear of the property (near the creek) each retained about 2.5m of soil
· the eastern retaining wall was built of solid concrete, and the western retaining wall was constructed of concrete block sleepers
· two additional timber sleeper retaining walls were built above the western wall
· these retaining walls were less than half a metre in height
· online photos show the collapsed concrete retaining wall was visible in November 2022
· there was a collapsed section of soil (sinkhole) approximately 1m long, 0.5m wide and 1.5m deep at the northern end of the property (backyard)
· online photos show this sinkhole present as early as 7 March 2023. It worsened by 15 June 2023, but was ‘seemingly repaired’ by 5 December 2023
· the concrete block wall had been backfilled with crushed rock which had eroded away, showing an agricultural drainage pipe at the base
· cracking was highlighted by the complainant to the north side of the alfresco, where previous cracking of up to 3mm had been repaired
· similarly sized diagonal cracking was evident from the post penetrations on the alfresco deck and cracking was also prominent where the balustrade was fixed to the brickwork
· the cause of the soil collapse was ‘long-term scouring and washing-away of the pipework backfill to the rear of the dwelling due to inadequate surface drainage’
· this caused ‘cavities below the surface soils’
· clayey soils and builder’s rubble in the backfill meant water ‘could not easily drain’ and the ‘limited compaction of the backfill material’ created ‘less cohesive soil’
· cracking and movement of the home was not due to the storm/flooding event or the erosion of the founding soils – it was caused by ‘long-term differential movement’
· a concrete pier at the northwest corner of home, which is at or below the base of the sinkhole confirms the footings have not been undermined by the claimed event or the erosion of soil
· the bridge across the watercourse at the rear of the home was gone at the time of inspection and its cause of failure cannot be ‘definitively’ determined
· looking at historical photos, the bridge was partially founded in the collapsed soil on the property, the failure of which was the likely cause of the bridge’s collapse.
Geotechnical expert WC inspected the home for IL and classified the soil at the site as ‘Class P’ or problem site. This was because it had ‘uncontrolled fill deeper than 0.8m’ and may be subject to landslip, collapse or erosion.
Complainant obtained expert reports and opinions
The complainant retained building consultant, MN. It provided three reports, dated 24 November 2024, 11 December 2024 and 2 July 2025. MN found:
· there were two previous sinkholes on the property filled in prior to the home being sold to the complainant and at least one of these sinkholes was visible in June 2023
· the volume of water from the flood event caused the ‘erosion of land’ on the property, leading to the ‘further displacement of retaining walls’, and the loss of the bridge
· further investigation should be done, including to the plumbing to see if there is damage to the pipes which created the sinkholes
· the retaining wall on the neighbour’s property ‘totally collapsed’ in the event as well
· visible movement is still ongoing on the complainant’s property
· further sinkholes are developing since the event as the rear yard is ‘slowly deteriorating due to the failure of the retaining walls’
· the home ‘in its current condition cannot now or ever be lived in again’.
MN considered the cost to stabilise the land and the home would be ‘considerably greater than the value of the building and the land combined’. It says the home should be demolished.
Surveyor MC provided a report dated 2 September 2025. MC confirmed there was a ‘downward tilt’ on the ground floor levels and the patio of the home. It says this is indicative of ‘subsidence of the land away from the canal towards the north east of the property and the neighbouring property’.
The complainant obtained an engineering report from engineer AT. After attending the property, AT found in its report of 12 June 2025 that:
· the high volume and velocity of water flow from the storm/flooding event caused significant damage to the home
· this contributed to and/or exacerbated the ‘scouring and washaway of the embankment’, leading to further movement of the home and was the ‘primary cause’ of damage
· it did not agree with the findings of IL (about the cause of damage) or WC (about the foundations being inadequate for the home).
Clear there was damage to the property before the complainant bought it
When purchasing the home in late 2023, the complainant obtained a pre-purchase inspection report from builder HR. However, she did not obtain or review it until after she moved in.
HR’s report of 22 November 2023 highlighted some pre-existing issues with the home and surrounds. HR noted under ‘Items Requiring Attention or Rectification’:
Subsidence/failure to concrete retaining wall to the rear water course may in part be associated with land slippage &/or poor workmanship. Replacement/upgrade to include adequate footings/drainage detail in conjunction with an engineer’s advice/specification is recommended. Note: Without retaining the watercourse further shear failure to the clay embankment would be anticipated.
No work was done by the complainant prior to the claimed loss.
Overall, HR considered the home was ‘structurally sound’ and in ‘fair condition’. It also noted the proximity of the local creek and recommended a search of council records for details of any previous flooding or water damage incidents.
The complainant says the selling agent assured her there was ‘nothing to worry about’ within the HR report. She believes this agent:
· was an acquaintance of the former owner, and
· likely assisted the previous owner to fill in the sinkholes which were present, with this work ‘not engineer designed or council approved’.
She believes the agent and/or the previous owner acted deceptively with the sale of the home, as she had no knowledge of the previous issues with the retaining walls.
The complainant also obtained a letter from the previous owner to the council, seeking assistance with the land. Dated 2 November 2022, this letter was sent by a relative of the elderly owner, submitting the home was ‘structurally unsafe’. I accept this shows there were known issues at the property prior to the complainant’s purchase of it. The letter does not show how this should be part of any accepted claim.
Insurer is not liable for damage which pre-dated the policy
It is not in dispute there were significant sinkholes at the property before the complainant’s purchase. These had been filled in before the property was advertised for sale.
AFCA does not have jurisdiction over the sale or what took place leading up to it. More to the point, the insurer was not on risk in 2023 when these sinkholes were present (or repaired).
No specific evidence was provided about the extent of pre-sale work to prepare the home before it was advertised. Clearly, there was some work done.
Whilst I acknowledge the sinkholes reopened after the storm and flooding events, I do not consider the events were the proximate cause of the damage. This was the lack of adequate foundations, inadequate compacting of the soil, inadequate drainage and possible issues with the underground pipes. These issues all pre-dated the policy coming into effect.
This means the insurer is not liable for them.
That the flooding events (in particular) meant the sinkholes became apparent again does not mean it was the proximate cause of the damage. There were historical and unresolved issues with the retaining walls, water flow over the property, prior sinkholes, poorly compacted soil in the repaired areas, and other issues.
In my view, this extends to the footbridge as well. Evidence about this damage is not strong from either party, though it was apparently secured in the collapsed retaining wall soil from the complainant’s home. Given the retaining walls were not fit for purpose (as evidenced by the sinkholes present in 2023), this is not a loss the insurer should be liable for.
Insurer not liable for additional damage to home either
The damage to the home is more difficult to assess and quantify.
I accept the home has deteriorated since it was assessed by AG at the outset of the claim. This does not mean the insurer is liable for it.
On balance, I accept the historical issues with the retaining walls, soil and sinkholes on the property meant the home was not secure on the foundation soils.
IL considered movement at the home was due to ‘long-term differential movement’. It identified significant and varied floor differentials throughout the ground floor of the home (164 mm), the upper floor (117mm) and the alfresco (190mm). I agree such differential movement amongst the respective floor levels was likely indicative of foundation soil movement.
I consider this movement was likely exacerbated by the sinkholes. However, I do not consider the further damage to the property is covered. In my view, it was predominately caused by the historical issues at the property. These issues pre-date policy inception and are therefore not within the coverage provided.
There is also no persuasive evidence of a secondary and claimable event to cause this damage. I acknowledge ongoing rainfall likely worsened the issues, but this was due to the pre-purchase condition of the property, not any specific event. The same goes for the complainant’s suggestion that the pipes under the soil might be compromised. This was not proven, but to the extent it existed, I am satisfied it likely pre-dated the policy.
The PDS confirms for flood claims, the insurer does not cover:
Loss or damage caused by erosion, landslide, subsidence, vibration, earth shrinkage or expansion or any other earth movement no matter how it is caused.
But we do cover damage caused by landslide or subsidence that:
· occurs within 72 hours of the first loss or damage to your home or your contents caused by the flood or water runoff, and
· is solely caused by the flood or water runoff (that is, not caused by or contributed to by erosion over time, structural or design fault, or any other factor).
Whilst some damage might have occurred within 72 hours of the flood, I am not satisfied it was solely or even predominately caused by the flood or water run-off. It was due to issues which pre-dated the inception of the policy.
Section 46 of the Insurance Contracts Act does not apply
The complainant raised the issue of section 46 of the Insurance Contracts Act 1984 (ICA), suggesting the insurer should be liable for the damage to the home.
Section 46 of the ICA provides:
Pre-existing defect or imperfection
(1) This section applies where a claim under a contract of insurance (other than a contract of insurance that is included in a class of contracts declared by the regulations to be a class of contracts in relation to which this section does not apply) is made in respect of a loss that occurred as a result, in whole or in part, of a defect or imperfection in a thing.
(2) Where, at the time when the contract was entered into, the insured was not aware of, and a reasonable person in the circumstances could not be expected to have been aware of, the defect or imperfection, the insurer may not rely on a provision included in the contract that has the effect of limiting or excluding the insurer's liability under the contract by reference to the condition, at a time before the contract was entered into, of the thing.
This section is not applicable. The insurer did not rely on a limitation or exclusion based on a reference to the condition of a thing before the policy came into effect. Section 46 offers no protection to the complainant.
Insurer to increase settlement payment to the complainant
I acknowledge the complainant’s concerns about AG’s quoted repair amount, however:
· the quotes were compiled soon after AG’s inspection of the home
· it is no longer feasible to requote the damage as the home has been declared unliveable
· given the passage of time, I accept it is likely other damage has developed which is not related to the loss
· the quoted repairs will likely not be done if the home is to be condemned.
No contingency uplift was offered with the settlement, and I consider this should have been done. I am also concerned about the viability of the quote, noting AG said it would not guarantee repairs. This point is arguably moot as the work will likely not be done. However, I consider it is fair that an additional amount be included with the settlement.
Whilst AFCA generally awards a contingency uplift of between 10-25%, depending on the nature of the work, I consider a more generous award is warranted here. The insurer must pay the quoted amount, plus a contingency uplift of 40%. This is because:
· there are reasonable doubts about the viability of the AG quote, noting it was never going to do the repairs and ultimately ceased trading
· no second attempt was made to ascertain a fair repair cost
· considerable time has elapsed since the initial quote and relevant costs will have increased
· I have not made an allowance for interest, and
· there is an inherent uncertainty about how much additional damage to the home might be related to the original covered damage.
To this end, the insurer must pay the agreed amount of $60,775.61 less the policy excess (if it has not already done so). It must add to this amount an additional $24,310.24 (40%). This makes for a total settlement of $85,085.85.
2.2 Is an award of compensation warranted?
No. The complainant was unsuccessful. It would not be fair to require the insurer to cover her costs. The insurer also did not cause undue delays or otherwise mishandle the claim.
Complainant seeking reimbursement of fees incurred
Under our Rules, AFCA can require the insurer to reimburse the costs incurred by a complainant, including professional fees or expert costs. Unless unusual circumstances apply, we will not require that an insurer pays more than $5,000 for these costs.
We consider whether the costs were reasonable and whether they helped the complainant obtain a better outcome than that offered by the insurer.
I do not consider the complainant’s experts helped to resolve the complaint. The claim for the disputed damage was not successful. Therefore, it would not be fair to require the insurer to reimburse the costs the complainant incurred.
AFCA can award compensation for non-financial loss
Under our Rules, AFCA can award up to $6,300 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience.
We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim.
No need to pay compensation for non-financial loss
I acknowledge the difficult position the complainant finds herself in. I further acknowledge the loss of her home and difficult personal circumstances have made her claim experience frustrating. However, I am not persuaded the insurer acted improperly.
Substantively, I consider the issue here was the home had pre-existing problems the complainant was not aware of at the time she purchased it. This is not the insurer’s fault or its responsibility to cover.
Overall, I consider the insurer handled the matter reasonably, except for not paying a contingency uplift with the settlement. This has been corrected.
I am not persuaded that the insurer is required to pay compensation for non-financial loss.
2.3 Why is the outcome fair?
The complainant has not shown the disputed damage was claimable under the policy. It would not be fair to require the insurer to cover damage which was first noticed prior to policy inception or that it is not otherwise required to cover under the policy.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.