Failure to implement previous AFCA determination on storm damage repairs, scope of works and temporary accommodation
Text of the determination
Amended Determination
|
Case number
|
12-24-164663
|
Financial firm
|
RACQ Insurance Limited
Case number: 12-24-164663 1 May 2026
1 Determination overview
1.1 Complaint
The complainant’s husband previously lodged a complaint with AFCA about whether storm-related damage to his and the complainant’s home was covered by their home insurance policy underwritten by the financial firm (insurer). That complaint resulted in a Determination issued on 2 February 2024 in favour of the complainant.
The complainant says the insurer has failed to implement the Determination and has not satisfactorily progressed or resolved the claim. She says that the Determination gave them the right to choose the relevant specialists to prepare the scope of works, and that the insurer must fund those repair costs. The insurer says the Determination requires both parties to work together to establish a scope of work and associated costings, and that the complainant has prevented this from occurring.
The complainant has also raised additional issues concerning financial loss. She said that she and her husband were required to decline a high value business contract because they needed to remain at the property to manage and make safe ongoing defects. She also seeks compensation for lost rental income.
The complainant also raises health concerns, stating that prolonged exposure to mould and the stress associated with the unresolved claim have required ongoing medical treatment and have caused significant personal hardship.
1.2 Issues and key findings
Has the insurer failed to implement the previous Determination?
Yes. I am satisfied that the insurer has failed to fully implement the previous Determination, which gave the complainant the right to choose the specialists to prepare the scope of works and quote(s). The insurer is required to fund the costs of the specialists chosen by the complainant (with the exception of the architectural specialist), and their quotes. However, the amount of the award for the building and temporary accommodation claim is limited to AFCA’s compensation cap of $631,500 (excluding interest).
Is the insurer required to pay other compensation?
Yes. The complainant is entitled to recover the indirect financial loss set out in section 2.2 of this Determination (up to AFCA’s cap, totalling $6,300). I am also satisfied that the insurer’s delays in implementing the previous Determination, and the impact this has caused, warrant an award of non-financial compensation of $6,300.
Why is the outcome fair?
The outcome is fair because the insurer is required to comply with its obligations under the previous Determination, and I am satisfied it did not. I have determined what is a fair resolution to the issues. It is also fair that the insurer is required to pay further non-financial loss compensation in the circumstances.
1.3 Determination
This determination is substantially in favour of the complainant. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to:
· pay the complainant $631,500 (the amount of the AFCA cap) for building damage and temporary accommodation, plus interest on $631,500 from 16 September 2024 until the date of payment
· pay the complainant $280,378.40 for contents damage, plus interest from 16 September 2024 until the date of payment
· pay the complainant $6,300 in non-financial loss compensation
· pay the complainant $6,300 in indirect financial loss compensation
· reimburse the complainant for GB’s invoiced costs (if any) associated with the preparation of the structural SOW and KR and RI’s invoiced costs (totalling $4,070 and $1,650 respectively) for the roof inspections and reporting undertaken
· pay the complainant any other reasonable professional expenses incurred in developing the SOWs (except for SO’s architectural invoice).
2 Reasons for determination
2.1 Has the insurer failed to implement the previous Determination?
Yes. I am satisfied that the insurer has failed to fully implement the previous Determination, which gave the complainant the right to choose the specialists to prepare the scope of works and quote(s). The insurer is required to fund the costs of the specialists chosen by the complainant (with the exception of the architectural specialist), and their quotes. However, the amount of the award for the building and temporary accommodation claim is limited to AFCA’s compensation cap of $631,500 (excluding interest).
Details of previous Determination
In December 2022, a severe storm caused roof damage and significant water ingress to the complainant’s house, leading to mould contamination and subsequent structural and contents damage. The insurer accepted the claim, but the complainant’s husband lodged a complaint with AFCA that the storm-related damage had not been properly repaired, and the insurer’s contractors’ work caused further deterioration, leaks, and mould contamination.
The AFCA Determination found that:
· the insurer was responsible for repairing all the original storm damage and the subsequent deterioration caused by its contractors’ inadequate and defective repairs
· the complainant had the right to choose his own qualified specialists to prepare the scope of works and quotations to repair the damage and mould remediation. Alternatively, he could approve specialists suggested by the insurer
· the insurer was required to pay the reasonable costs of the complainant’s chosen specialists
· the insurer was required to fund the complainant’s temporary accommodation, with no strict policy limit, until the home became fit to live in again, and
· the insurer was required to pay the complainant $4,500 in non-financial loss compensation, recognising the significant distress, inconvenience, and delays caused by the insurer’s handling of the claim.
In relation to the repair and remediation work, the previous Determination says as follows:
It is therefore appropriate to obtain a new detailed scope of works and quote for the recommended work….
The complainant will need to allow reasonable access to the property for the purposes of the necessary inspection. However, given the difficulties of the complainant’s dealings with the insurer to date (and his justified concerns about the quality and reliability of some of the insurer’s trades/experts), I consider it fair and appropriate that the complainant has the right to either choose the relevant (appropriately qualified) specialists to prepare the scope of work and quote(s), or to approve any specialists suggested by the insurer. Alternatively, the complainant might agree that each party submit scopes/quotes from their chosen experts to provide a reasonable basis for comparison and assist in reaching a fair settlement. (If the complainant chooses his own specialist, then the insurer remains responsible for the related costs.)
The insurer is liable for the work/costs identified in the new scope and quote obtained.
If cash settling for the mould damage, the insurer is required to do so based on the new agreed scope of works and by reference to at least one quote for that scope which is actionable by the complainant as a retail customer. The cash settlement is to include an uplift of 10% on the quoted amount, to allow for contingencies and the transfer of risk to the complainant.
The complainant says the insurer has not complied with the previous Determination
The exchanged material shows that after acceptance of the previous Determination, the following has occurred:
· the complainant proceeded to engage an architect, builder, roof specialists and a restoration company to prepare scopes of works (SOWs)
· based on these SOWs, the complainant obtained a quote for the building remediation work, and another quote for the contents loss
· the insurer has not approved the work outlined in the SOWs or the resulting quotes, nor paid the costs incurred by the complainant associated with developing the SOWs. The insurer has also not paid for the limited moisture drying works already undertaken.
· the insurer says that it has not been provided with access to the property to prepare its own SOW, and that unless and until this occurs, it is not liable to fund or accept the complainant’s independently obtained SOWs or quotes
· the insurer paid $80,300 for temporary accommodation, but the complainant says this did not reflect meaningful assistance in securing suitable accommodation and did not resolve her and her husband’s living situation while the home has remained uninhabitable, and
· the insurer paid the complainant’s husband the $4,500 in non-financial loss compensation awarded in the Determination.
The insurer has failed to implement the previous Determination
Apart from the payment of the $4,500 in non-financial loss compensation, I am satisfied that the insurer has failed to implement the previous Determination.
The core issue in the previous Determination was the complainant’s right to choose suitably qualified specialists to prepare the new SOW(s) and quote(s), with the insurer required to fund the reasonable costs of those specialists and their quotes. I am satisfied that the exchanged material shows that the insurer has failed to do this. I note that:
· the complainant engaged a builder (GB) to assess the structural issues, co-ordinate trades to assist in finalising the SOW, and prepare a consolidated quote for the remediation of the building damage. The insurer did not approve or fund this work
· the complainant engaged two roof specialists (RI and KR) to assess defective roof work and determine the rectification requirements. These reports formed part of the SOW process, but the insurer did not reimburse their costs (totalling $5,720) or consider their findings.
· the complainant engaged a restoration company (RE) as the mould remediation specialist, who performed site inspections, mould cleaning, HEPA air filtration, contents assessment and remediation planning for the SOW. It is noted however that their invoices (totalling $20,376) were ultimately paid by the insurer which it said was ‘as a gesture of goodwill’ rather than as implementation of the Determination
· the complainant engaged an architect (SO) to prepare building plans, fittings schedules, drawings and co-ordination required for the development of the SOW, but the invoices (totalling $51,594.30) have not been paid by the insurer
· the complainant coordinated multiple other trades and specialists over a six‑month period to produce the complete SOWs, including removalists, engineers, and restoration assessors, yet the insurer has not paid any of the related invoices or participated in the process
· the insurer did not act to repair or make safe the ongoing building defects, including continued water ingress, despite the Determination requiring the insurer to rectify unresolved defects and attend to ongoing leaks.
· the insurer did not progress its own SOW, stating that it could not fund or accept the complainants’ independently obtained scope because it had not been granted access to the property to prepare its own SOW.
I acknowledge the insurer’s view that the previous Determination says that ‘the complainant will need to allow reasonable access to the property for the purposes of the necessary inspection’. However, this does not state the access is for the insurer or its appointed specialists. Rather, the next paragraph of the Determination says that it is fair and appropriate for the complainant to either choose the relevant (appropriately qualified) specialists to prepare the SOW and quotes, or approve any specialists suggested by the insurer. The complainant has chosen to engage her own specialists. This is contemplated and in line with the previous Determination. The insurer is therefore required to fund these costs.
Based on the exchanged information, I am satisfied that the costs submitted by the complainant for the development of the SOWs are reasonable, with the exception of SO’s costs. For the reasons I have outlined below, I am not persuaded that the complainant has shown that, on balance, SO’s charges were necessary or reasonably incurred for the purpose of preparing the SOW.
The insurer says that architectural work substantially exceeds what is needed for the remediation task and is not proportionate to the requirements of the Determination. I agree with this. Although the prior Determination required the complainant to obtain a new detailed SOW and quotation, it did not require the preparation of architectural plans, design documentation or extensive fittings and finishes schedules of the type produced by SO. These documents were not necessary to identify the rectification works arising from the insured event and therefore I am satisfied that the associated costs of these are not reasonably recoverable.
I have also considered the quotes submitted by the complainant for the building remediation work (including structural damage, mould damage and roof damage) and the loss of the contents. The complainant has provided quotes as follows:
· quote from GB, dated 21 August 2024, for the building remediation work, totalling $1,045,766.70
· quote from RE, dated 25 June 2024, for the contents loss, totalling $280,378.40.
The insurer has not shown that these remediation costs or the proposed SOWs submitted by the complainant are unreasonable, nor has it produced any alternative quotes or expert reports showing that the SOWs and quotes proposed by the complainant fall outside what the previous Determination said. In the absence of such contrary information, and given that the work performed aligns with the process set out under the previous Determination, I am satisfied that both the costs incurred (with the exception of SO’s costs) and the resulting SOWs and quotes are reasonable.
I have also considered the exchanged material about the temporary accommodation costs and I am also not satisfied that the insurer has appropriately and fully implemented this aspect of the Determination.
I acknowledge the insurer’s concerns about possible irregularities with some of the temporary accommodation invoices submitted for reimbursement. But those concerns do not relieve the insurer of its obligation under the previous Determination to fund temporary accommodation until the home is made safe and fit to live in. As the remediation works have not been undertaken, I am satisfied that the home remains uninhabitable. The insurer is entitled to investigate any suspected irregularities separately, however, this does not suspend or negate its obligation to comply with the Determination unless and until it has a legal basis for withholding these costs.
Insurer to resolve the complaint
To resolve this aspect of the complaint, the insurer is required to fully implement the terms of the previous Determination. This requires the insurer to take the following steps:
· in accordance with the previous Determination, pay the complainant a cash settlement based on the quote from RE for the contents loss, totalling $280,378.40. Given the time that has elapsed since RE’s quote, the insurer is required to pay interest on this amount, calculated in accordance with section 57 of the Insurance Contracts Act 1984, from 16 September 2024 (being 14 days after the insurer was provided with RE’s quote, after which time it was unreasonable for the insurer to withhold payment), until the date of settlement
· in accordance with the previous Determination, the complainant was entitled to select suitably qualified specialists to prepare the new SOW(s). The insurer must therefore, upon being provided with proof of payment by the complainant:
> pay GB’s invoiced costs (if any) associated with the preparation of the structural SOW
> pay KR and RI’s invoiced costs (totalling $4,070 and $1,650 respectively) for the roof inspections and reporting undertaken
> pay any other reasonable professional expenses incurred in developing the SOWs, except for SO’s architectural invoice, which is not reasonably recoverable for the reasons I have outlined above.
· Also in accordance with the previous Determination, the insurer is liable for the work/costs identified in the quotes obtained by the complainant. As such, the insurer is required to:
> fund the rectification and remediation works identified in the SOWs obtained by the complainant (excluding the SOW developed by SO)
> in funding these works, the insurer is to rely on the quotes from GB and RE provided by the complainant, and pay a cash settlement to the complainant, subject to AFCA’s compensation cap outlined below
> comply with the terms of the previous Determination regarding its limits of liability. As outlined in the previous Determination, AFCA determined that it was not fair in the circumstances for the insurer to limit its liability to the sum insured at the time of the damage (which was $350,000 for the building and $40,000 for the contents). AFCA’s position on this issue has not changed.
The insurer’s total liability for the building claim (which also includes the further temporary accommodation costs) is subject to AFCA’s applicable compensation cap, being $631,500. For this reason, for the purposes of this Determination, I have also determined that it is not necessary for the building quotes already obtained by the complainant to be updated to reflect today’s prices nor have I considered an uplift amount, because the compensation cap has been reached.
However, the payment of interest is not also subject to AFCA’s compensation cap. Given the time that has elapsed since the complainant’s quotes were provided, it is only fair that the insurer is required to pay interest calculated in accordance with section 57 of the Insurance Contracts Act 1984, from 16 September 2024 until the date of payment. This date is 14 days after the insurer was provided with GB’s quote, after which time it was unreasonable for the insurer to withhold payment. Interest is payable on the maximum AFCA can award the complainant, being $631,500.
Lastly, the insurer is also required to fund all temporary accommodation obligations until the property is safe and fit to live in, noting the complainant is also required to co-operate with the insurer in accordance with the policy terms and conditions. As I have outlined above, this, however, is also subject to AFCA’s applicable compensation cap of $631,500 that applies to the building damage (and temporary accommodation) component of this complaint.
2.2 Is the insurer required to pay other compensation?
Yes. The complainant is entitled to recover the indirect financial loss set out in section 2.2 of this Determination (up to AFCA’s cap, totalling $6,300). I am also satisfied that the insurer’s delays in implementing the previous Determination, and the impact this has caused, warrant an award of non-financial compensation of $6,300.
Complainant is seeking compensation for indirect financial loss
The complainant says that she and her husband suffered significant financial harm as a result of the insurer’s delays and failures, including:
· loss of income because they were forced to decline a high value business contract (worth $500,000 per year) that would have generated substantial earnings, and
· medical expenses incurred for both of them (of around $13,440 in total) due to prolonged exposure to mould and the stress associated with the unresolved claim, which the complainant says required ongoing treatment and contributed to significant personal hardship.
The complainant also seeks loss of rental income in relation to another property, which she says became uninhabitable due to mould and unresolved defects, resulting in the property being unable to be legally rented. This property is not the subject of this determination, so I have not considered this.
Compensation for indirect financial loss is warranted
I acknowledge that the complainant’s policy excludes cover for any consequential (indirect) loss. Page 84 of the PDS states that the insurer does not cover:
Any indirect loss. Any loss or extra expense which indirectly results from an event we cover under your policy.
Despite this, under paragraph D.3.2 of the AFCA Rules, we can award up to $6,300 in indirect financial loss compensation for additional loss suffered when an insurer mishandles a claim.
I am satisfied that the complainant should be compensated for the medical expenses that she has incurred for her and her husband’s treatments, which are a result of the insurer’s mishandling of the claim.
The exchanged information shows that whilst the complainant and her husband were (at times) living in temporary accommodation since the previous Determination, they continued to be exposed to the mould conditions at the property due to their ongoing attendance to manage inspections, SOWs and the mould remediation work. As a result, the complainant and her husband have suffered ongoing and worsening health impacts, including respiratory symptoms, skin and eye irritation, fatigue, and stress related illness, which their treating practitioners expressly link to prolonged exposure to mould in the home and the insurer’s significant delay in properly rectifying the property.
The medical evidence confirms the need for formal treatment programs under a specialist mould illness practitioner, with documented treatment costs of $620 per month per person for at least six months, plus up to $500 per month per person for medications and IV therapies. These expenses were reasonably incurred because the insurer failed to implement the previous Determination in a timely manner and failed to make the property safe, resulting in extended exposure to harmful environmental conditions.
Consistent with the AFCA Rule based cap, the insurer is required to pay the complainant $6,300 for indirect financial loss relating to medical expenses.
As I have awarded the complainant indirect financial loss compensation for their medical expenses up to the AFCA cap, I am not required to also consider the claim for loss of income in this matter, as any further award would exceed the AFCA cap.
AFCA can award compensation for non-financial loss
Under the AFCA rules, non-financial loss compensation (capped at $6,300) may be awarded in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind.
Compensation for non-financial loss is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Moreover, non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer.
Compensation for non-financial loss awarded in previous Determination
In the previous Determination, AFCA awarded the complainant $4,500 in non‑financial loss compensation. This award recognised the significant distress, inconvenience, and delays the complainant experienced due to the insurer’s handling of the claim, including inadequate and defective repairs, poor responsiveness, and the resulting deterioration of the property.
Further compensation for non-financial loss is warranted in the circumstances
While the complainant has already been awarded non‑financial loss compensation in the previous Determination, I am satisfied that further compensation is warranted in the circumstances.
The insurer has continued to cause the complainant an unusual degree of distress, inconvenience and disruption by failing to implement the earlier Determination in any meaningful way. This includes not funding the reasonable costs of the complainant’s chosen specialists, not progressing the required SOW, and not acting to repair or make safe the ongoing defects, despite these steps being central obligations under the prior decision.
The result has been a prolonged period of well over a year during which the complainant has remained exposed to ongoing water ingress, mould contamination and unsafe living conditions. Medical evidence provided confirms that the complainant has suffered continuing physical symptoms and stress related health impacts arising from these unresolved conditions. The significant personal hardship, loss of enjoyment of the home, and the disruption to daily life caused by the insurer’s noncompliance goes beyond the normal inconvenience associated with a disputed claim.
In these circumstances, and given the seriousness and duration of the detriment suffered, I consider that an additional award of $6,300 in non‑financial loss is fair and appropriate.
2.3 Why is the outcome fair?
The outcome is fair because the insurer is required to comply with its obligations under the previous Determination, and I am satisfied it did not. I have determined what is a fair resolution to the issues. It is also fair that the insurer is required to pay further non-financial loss compensation in the circumstances.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.