Home / Allianz Australia / Determination 12-24-164140

Determination 12-24-164140

Partial denial of hail damage claim and adequacy of cash settlement

FirmAllianz Australia
Decided2026-01-22
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded$9,662
Non-financial loss—
Amount claimed$85,115
SourceAFCA PDF

Summary

A business's hail claim was accepted only for the newer Zincalume roof sheeting, with older galvanised sections denied as pre-existing damage. AFCA upheld the denial but increased the cash settlement to $9,662 by adding a builder's margin and risk uplift.

The complainant did not establish on the balance of probabilities that the denied damage was caused by the December 2023 hail during the policy period, but the cash settlement omitted a builder's margin and transfer-of-risk uplift.

Issues

Subjects and remedies

home or building damagenatural disastersmall businesspay claim

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-164140 | Financial firm | Allianz Australia Insurance Limited Case number: 12-24-164140 8 January 2026 1 Determination overview 1.1 Complaint The complainant (an incorporated entity) holds a business pack insurance policy covering accidental damage to a commercial property (policy). On 2 May 2024, a claim was lodged for damage to the property caused by a hail storm with a recorded date of loss of 17 December 2023. The insurer accepted the claim for hail damage to the newer Zincalume roof sheeting and offered a cash settled of $6,820 (exclusive of excess and GST). However, the claim for hail damage to the older galvanised roof sheeting was denied. This is because the observed hail damage is historic and occurred prior to policy inception. The complainant disputes the partial denial. It says the hailstorm caused damage across all roof sections, not just the newer sheeting. It says the partial acceptance is flawed. This is because it wrongly attributes widespread impact dents to maintenance or historic events despite photographic evidence indicating fresh, event‑related hail damage. It wants the insurer to accept the claim and pay a cash settlement for a full roof replacement based on its builder’s quote of $85,115. A representative is assisting the complainant. Any reference within this determination to the complainant includes the representative unless otherwise stated. 1.2 Issues and key findings Has the insurer correctly assessed the claim? Yes. This because the insurer has accepted the damage attributable to the claimed hail event. The exchanged information shows, on the balance of probabilities (that is more likely than not), the denied damage is maintenance related or pre-dated the policy. However, the insurer is required to increase the cash settlement offer to include a builder’s margin and an uplift for the transfer of risk. Why is the outcome fair? The outcome is fair because the complainant has not shown the denied roof damage was caused by hail or occurred during the policy period. It would be unfair to require the insurer to pay where no cover applies. The cash‑settlement offer is inadequate. It is fair to include a builder’s margin and uplift to reflect the transfer of repair risk. 1.3 Determination The determination is in favour of the insurer. Within 14 days of receiving notice the complainant accepts this determination, the insurer is required to pay the complainant in accordance with section 2.1 below. 2 Reasons for determination 2.1 Has the insurer correctly assessed the claim? Yes. This because the insurer has accepted the damage attributable to the claimed hail event. The exchanged information shows, on balance, the denied damage is maintenance related or pre-dated the policy. However, the insurer is required to increase the cash settlement offer to include a builder’s margin and an uplift for the transfer of risk. Complainant must show the damage claimed triggers cover under the policy It is accepted insurance law that the complainant carries the initial onus to establish, on the balance of probabilities (that is, more likely than not), a loss which is covered by the terms and conditions of the policy. Only if the complainant can do this will the onus shift to the insurer to show, on balance, it is entitled to decline cover in line with the policy wording or otherwise. Policy cover is subject to terms, conditions, and exclusions The policy incepted on 6 January 2023 and covers a period of 12 months to 6 January 2024. Coverage is defined in the product disclosure statement (PDS) and policy schedule (PS), which must be read together. There is no dispute the complainant received a copy of the policy documents. The insurer is entitled to rely on the policy terms in assessing the claim. Policy covers accidental damage The policy covers accidental damage to the insured premises under the commercial property section. Accidental damage must occur at the situation during the period of insurance. ‘Accidental damage’ is not defined in this section of the policy, so its ordinary meaning applies. The term accident in insurance policies is typically something that is unintended and unexpected. The parties agree the roof is damaged. The dispute is about the extent of hail, or accidental damage, which occurred during the period insurance. Insurer says damage has been correctly assessed On claim lodgement, the insurer appointed AN, who inspected the property on 7 May 2024. On 13 May 2024, AN reported no hail damage was found to the alsynite (polycarbonate) sheeting and nearby metal roofs showed no evidence of recent hail activity. A building consultant (MB) was instructed to assess and report on any resultant damage, and indicate, using regional historical hail data, when any identified hail damage most likely occurred. MB inspected the property on 27 May 2024. On 19 June 2024, MB reported: · the property contains mixed age roofing. Old, galvanised sheets (50+ years), newer Zincalume (installed around 2005), and polycarbonate roof sheets. · the old, galvanised areas: > display extensive deterioration: rust, corrosion, detached sheets, footfall damage, creasing > contain hail indentations, all are described as old/pre-existing > historical events with hail 4–6.7 cm are consistent with these older dents. · newer Zincalume areas: > no storm damage to laps > about 50% of sheets have one small indentation on rib; cappings also show minor denting > these are consistent with the 17 December 2023 event which had 1.5–2 cm hail and are very minor > this minor hail did not shorten the lifespan of the newer roofing because, under the manufacturer’s technical bulletin, risks like ponding and corrosion apply mainly to low‑pitched roofs. The subject roof has a 19‑degree pitch, making these risks negligible. · air conditioning coils showed no hail impact, suggesting no significant recent hail · polycarbonate sheets are aged/brittle with maintenance related damage only · hail splatter marks on the neighbouring roof show 1.5–2 cm impacts consistent with the 17 December 2023 event and match the size of the dents on the newer Zincalume sheets and cappings. MB concludes: · significant wear-and-tear dominates · no functional damage or reduced lifespan from the recent hail · the old roof has reached end of its serviceable life · minor recent hail did not shorten lifespan of newer roofing. At the insurer’s request, MB submitted a supplementary report (11 July 2024). It confirms: · only the newer Zincalume sheets and cappings on the upper hip roof show hail damage consistent with the recent event · all other dents across the older roofing are historic and outside policy coverage. MB provided fully itemised scope of works to repair the accepted portion only. The insurer obtained two repair quotes, $9,312 from CB and $7,320 (ex GST) from RB. On 18 July 2024, it partially declined the claim, offering a cash settlement of $6,820 (net of the $500 excess) based on RB’s quote. Complainant claims full roof replacement The complainant disputes the insurer’s partial acceptance. It says the event‑related hail damage is far more extensive than the insurer acknowledges. It says it acted properly and in good faith by notifying a claimable loss that occurred during the policy period. The damage affected the roof, falling within policy cover. Even if the manufacturer considers the roof’s integrity unaffected due to pitch, hail impact still constitutes a covered loss. Relevantly, the complainant says: · applying a common-sense assessment, the hail event on 17 December 2023 could have caused damage to the entire roof, not just the newer upper hip roof. > the storm involved hailstones ranging from pea‑size to golf‑ball size, therefore capable of causing widespread impact damage > it is not reasonable for MB to conclude hail selectively damaged only the new Zincalume sheets while ignoring older roof sections which were equally exposed. · the claim should be assessed solely on the date of loss. > even if there were historical hail events affecting the roof, this claim concerns the December 2023 event only, and the question is whether the event caused the observed damage. · MB’s conclusions are inconsistent and require clarification. > MB uses its observations as ‘supporting evidence.’ However, MB may be applying standards inconsistently > it also questions if similar claims in the area were also partially declined on the basis of multiple hail events and requests transparency for fairness. · evidence from local residents contradict MB’s characterization of ‘small hail.’| > it cites social‑media evidence showing larger hailstones than the pea‑size hail MB references > this visual evidence supports the possibility of more extensive recent hail damage. · damage from foot traffic should be covered under ‘accidental damage.’ > the insurer confirmed the policy covers ‘property insured that is accidentally damaged’ during the policy period > foot‑traffic damage falls within ‘accidental damage’ and is not excluded, therefore should be covered. The complainant reject’s the partial acceptance and the offered $6,820 settlement. It says localised repairs to the Zincalume roof are unsuitable. This is because the damage is widespread and irregular, increasing the risk of leaks, aesthetic inconsistencies, and voided warranties on coated metal sheeting. This may accelerate deterioration. Consistent with industry practice, full roof replacement is the reasonable method to restore the property to its pre‑event condition. On balance, disputed damage is pre-existing I have carefully considered all the exchanged information. On balance, I am not satisfied the disputed damage is attributable to the hail event of 17 December 2023, or that any accidental damage occurred during the policy period. I do not find the complainant’s submissions compelling. This is because they are founded on the possibility of damage and not supported by any independent expert evidence establishing a causal link between the claimed hail event and the damage. Specifically: · the complainant’s submission relies on general assumptions about storm intensity and uniform exposure rather than on property specific evidence · exposure to hail does not establish all observed damage was caused by the December 2023 event · MB found impact damage consistent with hail primarily to the upper hip roof, with other areas displaying characteristics inconsistent with the event. Common sense cannot displace the need for evidence of causation · the nature and distribution of the damage does not support the assertion all damage was caused by the the December 2023 event, particularly where expert evidence supports alternative causes · the complainant has not shown the creasing caused by foot traffic was caused by a discrete accident event during the policy period. MB identified damage consistent with maintenance related foot traffic over time. Cover is not presumed by the absence of a specific exclusion · MB cites BoM historical data showing multiple severe hail events in the area before the 6 January 2023 policy inception. With hail up to 6.7 cm, MB found the size and pattern of dents on the original roof matched these earlier storms rather than the pea‑to‑marble‑sized hail of 17 December 2023 · the assertion that localised replacement of the damaged Zincalume sheeting would void manufacturer warranties, lead to future leaks, or cause accelerated degradation is unsupported by any manufacturer guidance, technical bulletin, or independent expert evidence. References to standard industry practice are unsubstantiated · how other claims in the area were managed is not relevant to whether the complainant has established the December 2023 hail event caused damage to the property. The insurer is obliged to assess the claim based on the evidence relating to this roof, not to demonstrate uniform outcomes across different claims. I am not satisfied, on balance, the complainant has established the damage to the galvanised roof was caused by hail, or accidentally during the period of insurance. Equally, I am not satisfied the complainant has established the Zincalume section of the roof requires full replacement. The claim has been correctly assessed. The insurer is not required to replace the entire roof. Cash settlement offer is inadequate The insurer chose to cash‑settle the claim using the lowest quote from RB ($7,320 ex GST, minus a $500 excess). However, RB’s quote omits a builder’s margin, and the cash settlement excludes a transfer of risk contingency. As a result, I am not satisfied the cash settlement is adequate. I am satisfied it is fair to increase the offer based on RB’s quote, plus a 20% builder’s margin and 10% contingency uplift for the transfer of risk. As the complainant is registered for GST, the settlement is GST exclusive. · RB Quote (ex. GST): $ 7,320 · 20% builder’s margin: $ 1,464 · Plus 10% uplift: $ 878 · Settlement: $ 9,662 Within 14 days of receiving notice the complainant accepts this determination, the insurer is required to pay the complainant $9,662. 2.2 Why is the outcome fair? The outcome is fair because the complainant has not shown the denied roof damage was caused by hail or accidentally during the policy period. It would be unfair to require the insurer to pay where no cover applies. The cash‑settlement offer is inadequate. It is fair to include a builder’s margin and uplift to reflect the transfer of repair risk. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.