Insurer deferred repairs until building defects rectified, ceased temporary accommodation, and offered cash settlement; complainant wanted prompt repairs and ongoing TA
Text of the determination
Determination
|
Case number
|
12-24-161272
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-24-161272 25 February 2026
1 Determination overview
1.1 Complaint
The complainant is an owners’ corporation and holds residential strata insurance with the financial firm (insurer). It lodged a claim for water damage to unit 1 of the insured premises.
Waterproofing defects in the bathroom were said to be the likely main cause of the damage. The insurer agreed to repair the resultant water damage after the bathroom defects were rectified. Further investigations showed external building defects could allow water ingress. The insurer said those defects also had to be rectified before it could undertake repairs.
The insurer paid the cost of temporary accommodation (TA) for unit 1’s owner from August 2024 to December 2024, but says it is not responsible for further TA until it can start repairs. It has also offered the complainant $109,706.83 as a cash settlement, based on builder AB’s quote, estimated TA requirements during repairs, plus a 20% uplift to each.
The complainant says the insurer’s defect rectification requirements are unrealistic and that it has unreasonably delayed undertaking the covered repairs. It wants the insurer to promptly attend to the repairs and pay TA costs until unit 1 is liveable again.
1.2 Issues and key findings
Is the insurer’s position reasonable?
Yes. It is reasonable for the insurer to defer undertaking repairs until such time as defects that could compromise those repairs are rectified. By late 2024, the need for TA ceased to be due to the claim event and instead was caused by the delays in rectification of the defects. The insurer’s position that it will only cover further TA costs once its repairs start is reasonable.
How is the claim to be resolved?
The ongoing delays in defect rectification are stopping the insurer from attending to repairs, so it is fair that the claim is cash settled. The insurer is to get an updated quote and repair time frame estimate from AB, then cash settle based on them plus a 20% uplift.
Why is the outcome fair?
The insurer cannot reasonably be expected to complete repairs until the building defects are rectified. The delay in their rectification means it is fair that the claim is cash settled based on an updated quote from AB reflecting current prices, and a reasonable repair period estimate.
1.3 Determination
This determination is substantially in favour of the insurer. If the complainant provides written notice that it accepts this determination, the insurer is to:
· within 14 days, request AB to provide an updated quote reflecting current pricing and an estimate of the likely timeframe for completion of the repairs
· within 14 days of receiving the updated quote and estimate, give the complainant a copy and pay it a cash settlement based on them plus a 20% uplift, less any unpaid excess.
2 Reasons for determination
The complainant is represented by strata manager R. For brevity’s sake, the complainant and R are referred to below as ‘the complainant’, unless context requires otherwise.
2.1 Is the insurer’s position reasonable?
Yes. It is reasonable for the insurer to defer undertaking repairs until such time as defects that could compromise those repairs are rectified. By late 2024, the need for TA ceased to be due to the claim event and instead was caused by the delays in rectification of the defects. The insurer’s position that it will only cover further TA costs once its repairs start is reasonable.
Background
Subject to the terms and conditions set out in the product disclosure statement (PDS), the policy covers the insured building against ‘Damage’ occurring during the period of insurance. The PDS defines Damage as ‘any partial or total accidental physical loss of, or destruction of property from any sudden and accidental cause not otherwise excluded by this Policy’.
The PDS does not define ‘accidental’. However, I am satisfied its natural and ordinary meaning is ‘unforeseen and unintended’.
On 20 March 2024, the complainant through its insurance broker B, lodged a claim with the insurer for water damage to the floorboards and walls of unit 1 (unit). Soon after, one of the insurer’s trades were told by the unit’s owner (owner) the claim had been ‘closed off’. On 21 April 2024, B confirmed to the insurer the claim was withdrawn.
On 24 July 2024, B asked the insurer to reopen the claim.
Experts identified internal and external building defects
Following the reopening of the claim, the insurer arranged for builder AC to inspect the unit. On 16 August 2024, AC reported that:
· there was extensive damage to the timber flooring throughout the unit
· there was a large volume of stagnant water under the floorboards, indicating an active leak
· as the flooring had expanded and lifted due to the water, internal doors had been damaged
· there was extensive mould development on surfaces throughout the unit
· the damage was consistent with having been caused by an escape of liquid, but its origin could not be identified
· it had arranged for its plumber to inspect the unit to identify the source of the leak as well as any maintenance issues/building defects
· ‘Any identified maintenance issues or building defects must be rectified prior to the commencement of the proposed insurable repairs’.
AC’s report was forwarded to B on 21 August 2024.
On 27 August 2024, the insurer’s loss assessor (LA) and restorer (AR) inspected the unit. All exterior facing walls showed elevated moisture levels, indicating that there could be an external source of water ingress. Works to mitigate the damage were recommended, including removal of flooring and ceilings. Causation investigations could then be progressed.
On 28 August 2024, the insurer accepted the claim. Also, LA informed B of the matters set out above, including the potential for an external source of water ingress.
On 3 September 2024, B provided the insurer with plumbing and building reports the complainant or owner had previously obtained. In summary, the reports concluded that issues with the bathroom’s waterproofing were allowing water to travel under the floorboards.
LA responded to B on the same day. It agreed the waterproofing issues were a contributing factor to the damage and said the complainant should promptly address those issues. LA again referred to the potential for other contributing factors given the external walls’ elevated moisture levels. LA confirmed investigations would continue after flooring removal and drying.
By late September 2024, the flooring had been removed and drying works completed.
The insurer arranged for engineer SC to inspect the unit on 25 September 2024. In its report dated 17 October 2024, SC said:
· in addition to the defectively installed and failed bathroom waterproofing membrane, the bathroom’s floor finishes and fall were defective
· there were several likely causes of water seepage into the façade and wall, being:
> the minor leak from the bathroom
> cracked wall render
> failed façade weatherproofing
> water seepage through wall penetrations, awning flashings, and a box gutter
> defective balcony edge rebate and wall flashings
· each of those matters involved defective design or workmanship, and/or gradual deterioration, wear and tear
· ‘given the pre-existing defects present on site, the instructing builder may be unable to provide an adequate warranty relating to the internal remediation work within the property’.
On 17 October 2024, SC also provided a detailed scope of works (SOW), which separated water damage repairs from defect/maintenance rectification works.
On the same day, LA provided B with SC’s report and SOW. LA said the complainant would need to attend to the listed rectification works before the insurer could undertake repairs.
On 28 October 2024, the complainant advised that it had commenced rectification work in the bathroom given the previous advice the water was coming from that room. The complainant said SC had failed to identify which of the other possible defects had in fact contributed to the damage, such that it would be obtaining its own engineering report.
On 16 December 2024, engineer NE inspected the unit. On 18 December 2024, the complainant received NE’s report which said:
· the internal concrete slab and the cracked external render both had high moisture content
· the lack of movement joints was a likely contributing factor to the cracking
· moisture was able to penetrate through the cracks
· the box gutter on the awning did not have a sump or overflow provisions installed
· there was no sealant around the drainage pipes on the façade to prevent moisture entry
· the façade weepholes were defective and could allow moisture to track in
· water testing of the façade led to high moisture readings, indicating active water ingress
· the non-compliant balcony waterproofing would not prevent wind driven rain ingress
· water testing of the balcony also resulted in water leaking into the unit.
On 6 March 2025, NE undertook further investigations. It found that while brickwork cavity flashing was present, it was in a poor and deteriorated condition. The flashing would allow moisture to pass through, potentially into the unit.
On 3 April 2025, AR reinspected the unit. Moisture readings throughout the unit were within dry parameters, but surface mould growth had occurred despite previous remediation. AR said that indicated ‘possible water ingress from the exterior envelope of the building’.
Insurer’s position on repairs is reasonable
The complainant says the insurer has unreasonably delayed undertaking the covered repairs and should be required to progress them now because:
· the insurer initially told it to rectify issues in the bathroom, which it did, only for the insurer to later raise several other defects for it to rectify
· the insurer’s rectification requirements are unrealistic in terms of timeframe and scope
· it is unclear whether any of the defects identified have contributed to the damage and, if so, which ones
· it does not believe the defects pose a barrier to the insurer completing the repairs it accepted as covered given the lack of clarity about their contribution to the damage, if any
· the insurer’s claim handling has involved extensive delay.
However, based on the exchanged information, I am satisfied the insurer’s position that it will not complete repairs until the identified defects are rectified is reasonable. This is because:
· the insurer promptly progressed its investigations once the claim was reopened
· through B, the insurer promptly put the complainant on notice that maintenance issues/building defects would likely need to be addressed before covered repairs start
· through B, the insurer promptly put the complainant on notice before the complainant rectified the bathroom that there could be an external source of water ingress
· SC identified several external building defects that would likely cause water ingress
· the insurer immediately provided SC’s report and SOW to the complainant through B, and confirmed the complainant would need to attend to the listed rectification works before it could start repairs
· NE later confirmed that the external defects were allowing water ingress
· I accept the water ingress would compromise the insurer’s repairs such that it is reasonable for the insurer to require the defects to be rectified before it starts repairs
· based on consideration of the dates set out above, I do not agree that the insurer’s claim handling has caused any undue delay
· as outlined further in section 2.2 below, on 8 November 2024, the insurer put forward a reasonable cash settlement proposal to allow the complainant ‘to manage the defect repairs and subsequent resultant repairs at their own pace’.
Insurer’s position on TA is reasonable
The PDS confirms on page 17 that the insurer will pay reasonable TA costs necessarily incurred due to a unit being unfit to be occupied due to covered damage. Payment ceases once the unit can be reoccupied following repairs.
Page 21 of the PDS includes a term which says if an insured causes unreasonable delay in commencing/carrying out repairs, the insurer will not pay extra costs resulting from the delay.
The owner moved out of the unit in late August 2024 due to mould issues and trip hazards. The insurer agreed to pay for her TA costs, being $885/week.
When it provided B with SC’s report and SOW on 17 October 2024, LA said the insurer would continue to cover TA costs while the covered repairs were planned and carried out. However, it noted that if defect rectification unreasonably delayed the ability to move forward with the repairs, TA coverage would cease following provision of at least two weeks’ notice.
On 27 October 2024, LA reconfirmed those matters to B and advised TA coverage would resume once repairs could safely proceed.
In its IDR response letter dated 8 November 2024, the insurer told the complainant TA may be cancelled if there was evidence defect rectification was being unreasonably prolonged. The insurer said there was no current indication that was the case, so TA continued to be extended for the time being.
In a letter dated 16 December 2024, the insurer told the complainant:
· it had covered TA costs during the make safe and investigations stages
· it was now apparent that defect rectification had been delayed, unreasonably preventing it from progressing claim related repairs
· the need for ongoing TA was no longer due to the covered damage but was caused by the uncovered, delayed rectification works
· it would therefore cease paying for TA
· once defect rectification was done it would resume covering TA during the repair period.
The insurer subsequently agreed to cover TA from 16 to 30 December 2024, aligning with the two weeks’ notice period LA had referred to in his email to B dated 17 October 2024.
The complainant submits that the insurer’s decision to end TA on the grounds of unreasonable delay is unjustified. It says the time taken to obtain and consider advice from NE was reasonable. Further, that the insurer’s claim handling caused unnecessary delay.
On 17 October 2024, the insurer advised the complainant of the required external defect rectification works, that it would be required to attend to them before covered repairs could be done, and that unreasonable delay in rectification would result in TA ceasing. NE’s report, which the complainant had from 18 December 2024, confirmed the presence of the defects and that they were causing water ingress.
I also note that at no stage in the period between 16 December 2024 and 30 December 2024 did the complainant inform the insurer it was committed to progressing defect rectification.
As noted above, I do not agree that the insurer’s claim handling has caused any undue delay
In the circumstances, I am satisfied that it was reasonable and in accordance with the policy terms for the insurer to cease paying TA costs on the basis it will recommence payments once it is able to attend to repairs.
2.2 How is the claim to be resolved?
The ongoing delays in defect rectification are stopping the insurer from attending to repairs, so it is fair that the claim is cash settled. The insurer is to get an updated quote and repair time frame estimate from AB, then cash settle based on them plus a 20% uplift.
Cash settlement of claim is reasonable
The PDS confirms that the insurer may either attend to covered repairs or pay an insured the cost of those repairs by way of a cash settlement. In determining which option to follow, an insurer must act reasonably.
The claim event occurred two years ago. The complainant was on 17 October 2024 informed of the defect rectification work that had to be completed before the insurer attended to repairs. The rectification is still yet to take place. Further, it is apparent that the relationship between the complainant and the insurer has deteriorated.
I am therefore satisfied that it is reasonable that the claim be cash settled.
How the claim is to be resolved
A cash settlement must be based on a reasonable quote for claim related repairs, actionable by a retail customer. An uplift is typically applied to the quoted amount to allow for contingencies. It should also serve to compensate for the transfer of risk and the loss of the lifetime guarantee.
In its IDR response letter dated 8 November 2024, the insurer offered the complainant a cash settlement of the cost of covered repairs plus a 20% contingency uplift plus TA costs for 12 weeks based on the estimated repair timeframe. The insurer observed the cash settlement option would enable the complainant to manage defect rectification in a way that met its timing issues.
The insurer obtained quotes based on SC’s SOW for claim related repairs from AB and from builder EP.
The insurer then had the quotes assessed by quantity surveyor IC. On 8 April 2025, IC reported that AB’s revised quote dated 8 April 2025 would be fair and reasonable after an allowance for floor levelling (defect related) and GST on warranty insurance were removed.
On 6 May 2025, AB provided a further revised quote in accordance with IC’s report. The quote totalled $82,572.36. On the same day, IC confirmed that quote was actionable.
On 15 May 2025, the insurer offered the complainant a cash settlement as follows:
|
AB quote for repairs
|
$82,572.36
|
20% contingency uplift
|
$16,514.47
|
TA at $885/week for estimated 10 week repair period
|
$8,850.00
|
20% contingency uplift (2 weeks)
|
$1,770.00
|
Total
|
$109,706.83
I am satisfied that SC’s SOW encompasses the reasonable extent of claim related repairs. I also consider 20% to be a fair contingency uplift. IC has confirmed AB’s quote dated 6 May 2025 was actionable. However, that quote was prepared over nine months ago, so may not reflect current prices. Further, the quote did not include an estimate of the repair period.
Therefore, if the complainant accepts this determination, the insurer is to request AB to provide an updated quote reflecting current pricing and an estimate of the likely timeframe for completion of the repairs. On receiving the updated quote and estimate, the insurer is to give the complainant a copy and pay it a cash settlement based on the quoted amount plus TA based on the repair period estimate plus a 20% uplift to both, less any unpaid excess.
2.3 Why is the outcome fair?
The insurer cannot reasonably be expected to complete repairs until the building defects are rectified. The delay in their rectification means it is fair that the claim is cash settled based on an updated quote from AB reflecting current prices, and a reasonable repair period estimate.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.