Home / IAG / Determination 12-24-158258
Determination 12-24-158258
Scope of works and cash settlement amount for escape of liquid damage, plus claim delays
Summary
The insurer accepted an escape of liquid claim but disputed the scope of works; the complainant sought $46,728 based on his quote. AFCA rejected the quote, required further assessment by a hygienist and a builder after door jamb removal, and awarded $1,500 for delays.
The complainant did not substantiate that a full bathroom strip out was needed, but the insurer's assessment of liability was incomplete and claim delays warranted non-financial loss compensation.
Issues
- Claim amount dispute primary · not upheld“not satisfied that the complainant has established that the insurer should settle the claim based on his quote from KC”
- Inadequate claim investigation secondary · upheld“it has not been established whether repairs to the door jamb will require the waterproofing to be replaced... Further assessment of the mould is also required”
- Delay secondary · upheld“some delays caused by the insurer, particularly in the early aspects of the claim”
Subjects and remedies
home or building damagethird party authoritypay non financial lossreassess claim
Related
Text of the determination
Determination
|
Case number
|
12-24-158258
|
Financial firm
|
Insurance Manufacturers of Australia Pty Ltd
Case number: 12-24-158258 22 August 2025
1 Determination overview
1.1 Complaint
The complainant, together with his wife, hold a home and contents policy with the financial firm (the insurer). On 12 July 2024, the complainant lodged a claim for damage to his property following an escape of liquid event (EOL).
The insurer accepted the claim. However, a dispute has arisen as to the scope of works (SOW) to repair the damage from the insured event.
The complainant wants the insurer to cash settle him in the amount of $46,728 based on a quote that he has obtained for repairs. The complainant also seeks compensation for the insurer’s delays.
The complainant is represented by SJ, a friend. For convenience, unless indicated otherwise, any representation made is referenced as being from ‘the complainant’.
1.2 Issues and key findings
Has the insurer fairly assessed its liability?
No. Based on the exchanged information, it has not been established whether repairs to the door jamb will require the waterproofing to be replaced. It is reasonable that the insurer further assesses the damage by removing the door jamb and determine its liability. Further assessment of the mould is also required.
Is the complainant entitled to non-financial loss compensation?
Yes. The insurer is to pay the complainant $1,500 in non-financial loss compensation for claim delays.
Why is the outcome fair?
It is fair that the insurer further assesses its liability for repairs following the removal of the door jamb and based on a reasonable assessment of the claim-related damage. It is also fair that it pays compensation for claim delays.
1.3 Determination
This determination is substantially in favour of the insurer.
If the complainant accepts the determination, within 14 days of receiving written notice of the complainant’s acceptance, the insurer is to:
· settle the claim in accordance with section 2.1 below
· pay the complainant $1,500 in non-financial loss compensation.
2 Reasons for determination
2.1 Has the insurer fairly assessed its liability?
No. Based on the exchanged information, it has not been established whether repairs to the door jamb will require the waterproofing to be replaced. It is reasonable that the insurer further assesses the damage by removing the door jamb and determine its liability. Further assessment of the mould is also required.
Onus on complainant to establish a claimable loss
The complainant is required to show, on the balance of probabilities (that is more likely than not), that he suffered a claimable loss under the policy. This means that he must show the loss was caused by a risk for which he is insured.
Once the complainant, on balance, establishes a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving, on balance, the application of the exclusion or condition.
The terms of the policy include the Certificate of Insurance (COI) and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainant.
The policy covers damage caused by one of the listed events. It does not provide cover for all damage. Amongst these events is cover for ‘Water and oil leaks’. The complainant has also taken the additional cover of accidental damage.
On 12 July 2024, the complainant lodged a claim with the insurer. He said that he had found wet carpet in the hallway and bedroom. The complainant engaged a plumber who found a leak from the shower tap and water had escaped into the wall cavity.
The insurer accepts that the damage to the carpet and bathroom door architrave and architraves is consistent with the insured event. To that extent, it is not in dispute a claimable loss has been shown. However, the insurer says that the complainant has not established that mould remediation and a complete bathroom strip out, including new waterproofing is required to repair the damage from the EOL event.
Complainant has obtained a quote for repairs
The complainant says:
· the water from the broken shower pipe tracked from the breach along the wall to the bathroom door entry
· both sides of the wall have been water affected and therefore need to be removed and replaced, as evidenced by the wet carpet in the hallway
· there is evidence of a damaged door jamb and yellow tongue flooring under the carpet at the bathroom door entry which means that the hallway plaster requires removal and replacement
· as the bathroom wall is required to be removed, it will require the bathroom removal and replacement
· the National Construction Code provides that if you remove and replace the water affected door jamb and architraves, the waterproofing membrane will be affected.
The complainant has obtained a quote from KC for repairs in the amount of $46,728. This includes a complete bathroom strip out, including new waterproofing, and repairs to the wall linings in the hallway and bedroom. The quote also includes costs for mould remediation.
The complainant has provided a photograph taken of the wall cavity. He says that this shows that there is water/mould affected plaster, framework and subfloor.
Insurer says further assessments required to establish extent of repairs
Following lodgement of the claim, the insurer appointed a restorer to attend the property to assess. On 17 July 2024, the restorer found that the moisture readings on the plaster walls and particle board subfloor were within normal parameters. No drying was therefore required. The restorer noted that the water had travelled along the wall towards the hallway, which connects the bedroom and lounge area.
The restorer found that the bedroom carpet was salvageable but recommended replacing the underlayer and smooth edges since there was organic growth marks found on the smooth edges. The restorer recommended the replacement of the hallway carpet as it found evidence of organic growth underneath the carpet, and the smooth edges were rotten.
The insurer appointed a builder FB who attended the property on 17 July 2024 to assess the damage. FB provided a quote for repairs but noted that if statutory upgrades were required for compliance, a variation may be requested. FB provided a quote in the amount of $3,335.33.
The insurer obtained information from FB whether the removal of the door jamb would necessitate a strip out of the bathroom and waterproofing. FB provided an email to the insurer dated 31 October 2024 where it notes:
[U]pon removal of the door jamb, should a waterproofing system by [sic] in place and be affected upon removal, then additional scope of works would apply. However, this cannot be foreseen until the door jamb is removed as we do not know whether one has been installed at the door jamb entrance.
Following receipt of the complainant’s quote which included costs for remediation of mould, the insurer sought to re-attend and inspect. The complainant refused the insurer’s request until access was granted in February 2025.
The insurer’s plumber AC attended on 7 March 2025 to conduct further leak detection testing. The insurer wanted to ascertain whether there was any other source of water causing the mould, noting that the restorer had found the area to be dry in July 2024.
AC concluded that there was no further escape of liquids that was contributing to the claimed event.
The insurer therefore did not believe that the complainant’s quote was fair and reasonable based on the available information from FB that ultimately works may not be required.
The insurer offered that it would further review its liability if the complainant were to proceed with the repairs and further work was required. It says that it would require the complainant to provide evidence from the builder, such as a formal report with photographs to support any extra costs incurred. It would then review this information and consider settling for any additional expenses that arise.
The insurer says that it offered the complainant a cash settlement of $3,335.33 based on the quote from FB and $1,306.62 for carpets. However, the complainants rejected this offer.
Insurer is not required to accept the complainant’s quote
I am not satisfied based on the complainant’s submissions that he has established that a bathroom strip out is required. I accept there are legitimate concerns as to whether the removal of the door jamb may affect the waterproofing. However, as acknowledged by FB, there is no evidence that the waterproofing in the bathroom extends to the doorway.
The complainant has not provided any expert report in support of his position. I place little weight on comments by the complainant saying that an engineer and a building consultant have advised that the entire bathroom is required to be removed, especially on the first floor, in the absence of any reports.
The National Construction Code (NCC) referred to by the complainant provides the relevant standards for waterproofing in areas adjacent to a shower. However, the complainant has not stated the relevant provision that he seeks to rely on. I note the NCC provides:
10.2.3 Area outside shower area
(1) For concrete, compressed fibre- cement and fibre-cement sheet flooring, the floor of the room must be water resistant.
(2) For timber floors including particleboard, plywood and other timber based flooring materials, the floor of the room must be waterproof.
(3) Wall/floor junctions must be-
(a) waterproof; and
(b) where a flashing is used, the horizontal leg must be not less than 40mm.
However, the complainant has not provided any evidence in support of what the construction standards were when the bathroom was constructed. Further, while the complainant says that the replacement of the door jamb necessitates the replacement of waterproofing, the NCC provides:
10.2.31 Door jambs on tiled floors
Where the bottom of a door jamb does not finish above the floor tiling, the portion of the door frame below the floor tiling must be waterproofed to provide a continuous seal between the perimeter flashing and the waterstop.
The complainant has not provided evidence to support where the door frame finishes.
I note that FB did not expect that removing the door jamb would impact on the waterproofing membrane.
I am satisfied that the insurer’s approach is reasonable. That is, it must be firstly determined whether there is waterproofing present when the door jamb is removed. The insurer is then to assess its liability at that time. It would not be fair to require the insurer to accept the complainant’s quote when it has not been substantiated that all repairs are necessary and claim related.
The complainant has provided photographs which he says shows mould. The insurer has not responded to this. I note that the assessor observed mould present underneath the hallway carpet. However, now more than a year after the EOL event, the carpet remains in place.
It is therefore reasonable that the insurer appoints a hygienist to re-assess the property, noting that it now more than a year from the EOL event and there are ongoing concerns about the presence of mould.
How the claim should be settled
The policy provides that the insurer will choose how to settle the claim, by either arranging for repairs or paying the reasonable costs to repair the home. The policy does note that it seeks consent from the insured prior to arranging for its preferred repairers to repair the home.
I am not satisfied based on the exchanged information, that the complainant has established that the insurer should settle the claim based on his quote from KC.
I am not satisfied that the cash settlement offer from the insurer based on the quote from FB in the amount of $3,335.33 is a fair assessment of its liability. I also accept that as the insurer did not take steps to remove the affected carpets, I cannot be satisfied that the restorer’s assessment of the bedroom carpets as being salvageable is correct and/or whether further remediation is required.
The insurer is to re-assess whether remediation is required, including whether the carpet in the bedroom can be remediated.
Should the complainant accept the determination, within 14 days of being notified of the complainant’s acceptance, the insurer is to:
· appoint a hygienist to prepare a SOW for remediation of the insured damage- including carpets
· within 14 days after receipt of the SOW from the hygienist, the insurer is to appoint a builder (other than FB) to remove the door jamb and then prepare a SOW and quote for repairs to the insured damage (which includes the carpet)
· if the complainant elects a cash settlement, the insurer is to cash settle based on the quote obtained following the removal of the door jamb with a 10% uplift for contingencies and the loss of a lifetime guarantee on the repairs.
2.2 Is the complainant entitled to non-financial loss compensation?
Yes. The insurer is to pay the complainant $1,500 in non-financial loss compensation for claim delays.
AFCA can award compensation for non-financial loss
Under our Rules, AFCA can award up to $6,300 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience.
We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim.
Delays not solely caused by the insurer
The insurer says that it attempted to communicate with the complainant between August and September 2024 for the purpose of planning for site attendance and to complete repairs. It says that there was no contact with the complainant during this time.
The insurer says that it sought to further investigate the issue of mould following receipt of the complainant’s quote from KC. However, the complainant refused access to the insurer until late February 2025.
The insurer had made an offer in relation to non-financial loss compensation. However, this conditional offer was withdrawn.
I acknowledge that there were some delays caused by the insurer, particularly in the early aspects of the claim. However, I also accept that the complainant contributed to these delays, including his refusal to allow access to the insurer to re-assess.
The complainant seeks compensation for delays, site attendances and time spent on the phone. However, I am satisfied that the site attendances and phone calls were part of the claims process.
In all the circumstances, I am satisfied that the insurer should pay the complainant $1,500 in non-financial loss compensation.
2.3 Why is the outcome fair?
It is fair that the insurer further assesses its liability for repairs following the removal of the door jamb and based on a reasonable assessment of the claim-related damage and it pays compensation for claim delays.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.