Loss of rent benefits beyond four weeks and non-financial loss for handling of storm damage claim
Text of the determination
Determination
|
Case number
|
12-24-155278
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-24-155278 31 March 2026
1 Determination overview
1.1 Complaint
The complainant owns a tenanted single-storey unit, which is insured under a strata policy held by the body corporate and underwritten by the financial firm (insurer). In September 2024, the complainant lodged a claim under the policy for storm damage to his unit, including damage caused by a fallen tree and resultant roof and internal water damage.
The insurer partially accepted the claim and arranged inspections and repairs. The complainant said that the insurer was liable for more damage than what it accepted. This aspect of the complaint has now been settled.
The complainant’s claim for loss of rent benefits, however, is not resolved. The insurer paid loss of rent benefits, but only for a limited repair period. The complainant disagrees and says the property was unsuitable for occupation for a longer period. The complainant also says that the insurer should pay non-financial loss compensation for the distress, inconvenience and disruption caused to him by its handling of the claim.
1.2 Issues and key findings
Is the insurer required to pay further loss of rent benefits?
No. I am not satisfied that the complainant has shown that the property was unfit for occupation for a longer period than the insurer allowed for repairs. The complainant has also not shown that rent was reduced or not received during the longer make-safe period.
Should the insurer pay non-financial loss compensation?
Yes. I am satisfied that the insurer’s handling of the claim caused the complainant an unusual degree of distress or inconvenience warranting an award of non-financial loss compensation. I consider that $4,500 is fair in the circumstances.
Why is the outcome fair?
The complainant has not established that the property was unfit for occupation for a longer period than what has been accepted. It would not be fair for the insurer to pay for longer. However, it is fair that non-financial loss compensation is paid to the complainant.
1.3 Determination
This determination is in favour of the insurer. I am not satisfied that the insurer is required to pay any further loss of rent benefits beyond the four-week period already accepted.
However, if the complainant accepts this determination, within 14 days of being notified of the complainant’s acceptance, the insurer is required to pay the complainant:
· the accepted loss of rent benefits (if it has not already done so), for four-weeks loss of rent, together with interest calculated in accordance with section 57 of the Insurance Contracts Act 1984 (Cth), from 4 July 2025 until the date the payment is made, and
· $4,500 in non-financial loss compensation.
2 Reasons for determination
2.1 Is the insurer required to pay further loss of rent benefits?
No. I am not satisfied that the complainant has shown that the property was unfit for occupation for a longer period than the insurer allowed for repairs. The complainant has also not shown that rent was reduced or not received during the longer make-safe period.
The complainant has lodged a valid claim for damage
The complainant owns a single‑storey unit within a strata complex. The strata complex is insured under a residential strata building insurance policy held by the body corporate and underwritten by the insurer.
On 2 September 2024, a storm caused damage to the complainant’s unit, including damage from a fallen tree and resultant damage to the roof and internal areas of the unit. There is no dispute that this insured event occurred or that it caused damage to the unit requiring repair.
The complainant lodged a claim shortly after the storm. The insurer accepted the claim in part and arranged make safe works and repairs. However, during the course of the claim, disputes arose between the complainant and the insurer about whether the insurer was required to remove the fallen tree, whether the scope of works adequately addressed all the damage, and whether the initial make safe was adequate.
The complainant also raised concerns about delays in progressing the claim and the impact of those delays on the tenancy. The insurer accepted loss of rent benefits for a four-week period on the basis that this was the reasonable time to allow for repairs, and the property was not unfit for occupation beyond that time. The complainant says the property was unsuitable for occupation for a longer period due to the damage and the delays in repairs.
During the course of this complaint, the insurer agreed to remove the tree and cash settled the complainant for that work. The parties also agreed to cash settlements for the disputed internal and external repairs, and the insurer conducted a further make safe and assessment of the damage at the property.
As a result, most issues that were initially in dispute have now been resolved. However, a dispute remains about whether the insurer is required to pay loss of rent benefits beyond the four-week period already accepted, and whether the complainant is entitled to non‑financial loss compensation arising from the insurer’s handling of the claim.
Temporary accommodation cover does not apply
The terms and conditions of the policy are set out in the policy documents, including the Product Disclosure Statement (PDS) and the Policy Schedule.
The policy provides temporary accommodation cover, set out at page 19 of the PDS, and extracted in section 3.2 of this determination.
The complainant initially claimed temporary accommodation (and related costs) for his tenant. The insurer declined this, on the basis that the policy benefit applies only when the lot owner occupies the lot/unit, and does not extend to providing alternative accommodation for tenants.
I agree with the insurer’s assessment of this issue. The PDS is clear that the temporary accommodation benefit applies only to reimbursing a lot owner’s reasonable costs of temporary accommodation where their owner‑occupied lot (or unit) is unfit to be occupied by them due to an insured event. It does not extend to paying for alternative accommodation for a tenant of a leased lot/unit.
Accordingly, the complainant is not entitled to temporary accommodation benefits.
Policy provides cover for loss of rent
The complainant has also claimed loss of rent benefits, which is covered under the policy where the property is unfit to be occupied due to the damage (see section 3.2 of this determination for the PDS extract).
The insurer accepted the complainant’s loss of rent claim for a four-week period. It says this was based on the reasonable repair period (noting that it cash settled the repair works). The complainant disputes that assessment. He says the damage (and delays in making the property safe and progressing repairs) meant the property was not fit for occupation for a longer period.
I note that the complainant says he is entitled to loss of rent for a three‑month period, which he understands to be the maximum payable under the policy. However, this maximum three-month period applies to a different clause of the policy, where a tenant remains in occupation but the lot/unit is partially unfit and the lot owner necessarily incurs a cost to abate (reduce) the tenant’s rent during the disruption. This is different from the loss of rent clause outlined above, which is payable by reference to the period of repairs/reinstatement and reletting, rather than a rent abatement period. This is what I have considered in making my determination.
Insurer says property was unfit to be occupied for a limited period only
The insurer says the unit was unfit for occupation for the period of time it would have taken to complete the accepted internal repairs. It says the accepted damage was non‑structural (limited to plastering, painting and reinstating fixtures) and did not affect essential services. On that basis, it allowed loss of rent for four weeks only.
In support of this position, the insurer relies on its claim file material and information from the external experts it engaged, including:
· the initial roof inspection report from ND which identifies limited impact damage (broken tiles, gutter/fascia/antenna) and does not identify broader structural issues
· the make-safe report(s) (including the initial make safe attendance on 7 September 2024, shortly after the storm) and the insurer’s position that temporary tarping to the roof addressed immediate weatherproofing needs until the repairs could be completed
· its building assessment and report and resultant quotes, which assesses the accepted repairs as plaster/paint/reinstatement items
Complainant says property was unfit to be occupied for a longer period
The complainant says the unit was unfit for occupation for a substantially longer period than the four weeks allowed by the insurer. He says that, following the storm event on 2 September 2024, the tenant’s occupancy was disrupted by ongoing roof and water‑ingress issues, and that the unit could not reasonably be treated as safe and suitable to live in while the claim and repairs (including make-safe works) were being progressed.
He says the initial make-safe on 7 September 2024 (which involved placing a tarpaulin over broken roof tiles) was inadequate and did not properly prevent ongoing water ingress, including around the damaged roof area and the antenna/fascia. He says that further rain occurred during September and October 2024 and the temporary tarping that did not fully seal the affected areas left the unit exposed to continuing water entry and a risk of worsening internal damage. He made complaints to the insurer about this at the time.
The insurer’s make-safe provider re‑attended the property on 22 October 2024 and carried out further make safe works including covering additional broken tiles and sealing the edges of the tarp. Additional make safe works were later undertaken on 9 April 2025 (including removal of debris from the roof and lopping of overhanging branches).
The complainant issued his tenants with a notice to vacate on 22 November 2024 (nominating a termination date of 31 January 2025) on the basis that the repairs to the unit could not be done while the tenant was living there. The tenant ultimately vacated and returned the keys on 19 February 2025.
Accept that the property was unfit for occupation until 22 October 2024, and then again for the four-week reasonable repair period
I am satisfied that the exchanged material shows that the storm and fallen tree on 2 September 2024 caused roof damage (broken tiles and associated damage to guttering, fascia and antenna) and that, in the weeks that followed, the unit was exposed to an ongoing risk of water ingress. Although make safe works were undertaken on 7 September 2024, I am satisfied that the complainant has shown that these works were insufficient, and the material risk of ongoing water ingress was not addressed until the second make safe works occurred on 22 October 2024.
Whilst I also note that further make-safe works occurred on 9 April 2025, the exchanged material does not show that the property was unfit for occupation between 22 October 2024 and 9 April 2025. In particular, there are no contemporaneous reports of further water ingress, emergency repairs, reports of mould, or safety concerns (such as electrical hazards) during that period that would establish the property was unsafe or unsuitable to be lived in.
Whilst I have accepted that the property was unfit for occupation from 2 September 2024 until 22 October 2024, the complainant has not submitted any information showing that the tenants paid no rent or reduced rent during this period. The tenants did not vacate the property until 31 January 2025. As such, I am not satisfied that the complainant has established a valid claim for loss of rent during this period.
I am satisfied however that there is a valid claim for loss of rent for the duration of the reasonable repair period. As I have outlined above, the insurer has assessed the reasonable repair period as four weeks. This is based on the accepted scope of internal works and the repair quotation.
The exchanged material does not include any contrary independent view (such as a builder’s program, work, health and safety direction, or alternative quote) establishing that the property needs to be vacant for a longer period for these works to be carried out safely and effectively. Rather, the complainant’s view that the work would take longer than four weeks is based on his own assessment of the scope and complexity of the works and the practical difficulties of coordinating works while a tenant remained in occupation. This is not persuasive in establishing that the repair period accepted by the insurer is not reasonable.
In these circumstances, I am not satisfied that the complainant has established an entitlement to loss of rent benefits beyond the four-week period already accepted by the insurer. As such, within 14 days of being notified of the complainant’s acceptance of this determination, if it has not already done so, the insurer is required to pay the complainant the accepted loss of rent benefits, for four weeks loss of rent, together with interest calculated in accordance with section 57 of the Insurance Contracts Act 1984 (Cth), from 4 July 2025 (the date the insurer initially accepted the loss of rent claim) until the date the payment is made.
2.2 Should the insurer pay non-financial loss compensation?
Yes. I am satisfied, on the material before me, that the insurer’s handling of the claim caused the complainant an unusual degree of distress or inconvenience warranting an award of non-financial loss compensation. I consider that $4,500 is fair in the circumstances.
AFCA can award compensation for non-financial loss
Under its rules, AFCA may award non-financial loss compensation (capped at $6,300) in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind.
Compensation for non-financial loss is not awarded by AFCA when a person suffers the normal degree of inconvenience when a problem occurs. Moreover, non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer.
Compensation is warranted in the circumstances
The complainant says the insurer’s actions throughout the course of the claim have caused him an unusual degree of distress and inconvenience. In particular, he says the insurer’s handling of the make-safe phase of the claim was inadequate and slow, which left the unit exposed to an ongoing risk of further water ingress for an extended period. As outlined above, I have accepted that the initial make safe works on 7 September 2024 were insufficient and that the material risk of ongoing water ingress was not addressed until the second make-safe works on 22 October 2024.
I accept that the complainant experienced an unusual degree of distress and inconvenience due to this, in particular. The combination of an unresolved weatherproofing risk over a number of weeks and the need for repeated follow-up goes beyond the normal degree of inconvenience that would ordinarily be expected in an insurance claim.
I also accept that the complainant experienced additional distress and inconvenience arising from the insurer’s handling of the storm‑damaged tree and overhanging branches. The exchanged material shows that this was a protracted issue, involving ongoing disagreement about the insurer’s responsibility for removal, delays in decision‑making, and repeated communications from the complainant raising safety concerns. During this period, the complainant reasonably remained concerned about the risk of further branches falling onto the dwelling, causing additional damage or exacerbating the existing roof issues.
The complainant was required to spend a significant amount of time pursuing the insurer for clarity and action, including providing photographs, responding to insurer positions, and escalating concerns about safety and further damage. While this issue was ultimately resolved by agreement, including a cash settlement for the disputed repairs and tree removal, the length of time taken to reach that outcome, the delays in resolving this and the prolonged claim handling caused an unusual degree of distress and inconvenience to the complainant.
I consider that an award of $4,500 in non-financial loss compensation is fair and reasonable in the circumstances.
2.3 Why is the outcome fair?
The complainant has not established that the property was unfit for occupation for a longer period than what has been accepted. It would not be fair for the insurer to pay for longer. However, it is fair that non-financial loss compensation is paid to the complainant.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Policy terms and conditions
PDS, page 19
a. Temporary Accommodation
When You occupy Your Lot/Unit We will pay the reasonable cost of Temporary Accommodation You necessarily incur if Your Lot/Unit is made unfit to be occupied for its intended purpose due to:
i. Damage to Your Insured Property that is admitted as a claim under Policy 1; or
ii. reasonable access to or occupancy of Your Lot/Unit being prevented by Damage from an Event claimable under Policy 1 happening to other property in the immediate vicinity.
b. Rent
When You have leased out or can substantiate by means of a signed agreement that You would have leased out Your Lot/Unit or Common Area We will pay the actual Rent You lose or would have lost if Your Lot/Unit or Common Area is made unfit to be occupied for its intended purpose due to:
Damage to Your Insured Property that is admitted as a claim,
We will pay…from the time of the Event until the time Your Lot/Unit or Common Area is relet following completion of rebuilding, repairs or Replacement provided You demonstrate You have taken all reasonable actions to obtain a new Tenant
PDS, pages 12-14
You means the Body Corporate, Corporation, Owners Corporation, Plan or Company named in the Schedule including…Lot Owners
Lot Owner means a person, persons or other entity registered as a proprietor or owner of an estate in fee simple in a Lot/Unit in Your Building in terms of the Strata Legislation applying where Your Insured Property is situated
Tenant means any person authorised under the terms of a lease, rental or similar type agreement who occupies a Lot/Unit including any other co-inhabitant or family normally resident with that person