Home / Allianz Australia / Determination 12-24-152693
Determination 12-24-152693
Storm damage claim: scope and cash settlement of repairs, with supplementary revisions to the first determination
Summary
Supplementary determination revising the first determination on a storm damage home claim. The insurer must appoint an independent consultant to cost repairs, cash settle them with a 10% uplift, pay temporary accommodation and storage, and pay $3,000 for non-financial loss.
It is fair to revise the first determination to reflect matters agreed by the parties and updated scope of repairs, with an independent assessment of the cost.
Issues
- Claim amount dispute primary · upheld
“independent building consultant to prepare actionable quote; insurer to cash settle repairs plus 10% uplift”
- Claim denial secondary · not upheld
“Items 15.11 and 15.13 excluded because they relate to termite damage which is excluded under the policy”
- Repairs or contractors secondary · upheld
“assess whether items were damaged by the storm or by the insurer's builder (requiring rectification)”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial lossreassess claimrepair or rectify
Text of the determination
Determination - Supplementary
|
Case number
|
12-24-152693
|
Financial firm
|
Allianz Australia Insurance Limited
Case number: 12-24-152693 20 May 2025
Supplementary Determination overview
1.1 Supplementary Determination to AFCA Determination dated 22 April 2025
On 22 April 2025 the Australian Financial Complaints Authority (AFCA) has provided a Determination in relation to this complaint (152693) (the First Determination). Subsequent to the First Determination, the complainant and the insurer have raised further issues that are not specifically addressed in the First Determination. The outcome of those issues is recorded in this Supplementary Determination (Supplementary Determination).
It is fair for the outcome in the First Determination to be revised as set out in this Supplementary Determination to enable the complainant and the insurer to resolve this complaint. For the assistance of the parties, the revisions are set out in italics.
1.2 Issues and key findings
Should the First Determination be revised?
Yes. The First Determination should be revised as set out in this Supplementary Determination to address the additional issues raised after it was issued.
Is the outcome fair?
Yes. It is fair for the First Determination to be revised as set out in this Supplementary Determination and to assist the complainant and the insurer in the resolution of this complaint.
1.3 Supplementary Determination
This Supplementary Determination is substantially in favour of the complainant. Within 14 days of receiving notice of the complainant’s acceptance of the determination, the insurer shall:
appoint an independent building consultant/ engineer (at the insurer’s cost) to review the repair works referred to in section 3.2 and prepare an actionable quote of the cost of the repair works. The building consultant/ engineer is to be a specialist who is able to prepare both a SOW and an actionable quote. The independent building consultant/ engineer is not to be C (C is not named in this Supplementary Determination but is known to the complainant and the insurer). The assessment should involve the following process:
1. the independent building consultant/ engineer should review the items which the insurer had agreed to pay based on the insurer’s SOW dated 1 October 2024 (set out in Section 3.2(a) of this Determination (excluding Items 15.11 and 15.13) and provide an updated itemised quote to enable a cash settlement to be paid by the insurer
2. the independent building consultant/ engineer should review the additional items sought by the complainant on 25 November 2024 and make an assessment of whether (or not) they were damaged by the storm or were damage caused by the insurer’s builder (requiring rectification) and, if they were damaged by the storm or by the insurer’s builder (requiring rectification), to include such items in the actionable quote. The items sought by the complainant are set out in section 3.2(b) of this Determination. To the extent that there is any duplication in Sections 3.2(a) and 3.2(b), then the item should only be counted once in the actionable quote to be prepared.
2A. the independent building consultant/ engineer should review the items in the 0.2 N SOW (which is to be provided by the insurer to the independent building consultant) and provide an updated itemised quote to enable a cash settlement to be paid by the insurer. To the extent that there is any duplication in Sections 3.2(a) and 3.2(b) and the O.2 SOW, then the item should only be counted once in the actionable quote to be prepared.
3. the independent building consultant/ engineer should provide a written estimate of the period of time (in weeks) it is estimated the repair works will take to complete
on the appointment of an independent building consultant/ engineer, they shall have access to the complainant’s home to conduct the necessary inspections and prepare an actionable quote
within 14 days of the assessment being made, the insurer is to cash settle the repairs to the complainant’s home based on the independent building consultant/ engineer’s assessment plus a 10% uplift
pay the complainant as a cash settlement for temporary accommodation during the period in which the repair works are estimated by the building consultant/ engineer to take to be completed
pay for the costs of furniture storage as a cash settlement during the period in which the repair works are estimated by the building consultant/ engineer to take to be completed
pay the sum of $3,000 to the complainant for non-financial loss compensation
Reasons for determination
2.1 Should the Determination be revised?
Yes. The Determination should be revised as set out in this Supplementary Determination.
AFCA Determination dated 22 April 2025
On 22 April 2025 AFCA provided the First Determination. This Supplementary Determination should be read in light of the First Determination.
Further issues raised post-Determination
Subsequent to the First Determination, the complainant and the insurer have raised further issues:
whether the appointment of an independent building consultant/ engineer should not be C. The insurer and the complainant have agreed that the independent building consultant/ engineer is not to be C (C is not named in this Supplementary Determination but is known to the complainant and the insurer). It is fair and appropriate that the First Determination be revised accordingly in this Supplementary Determination.
whether the Items 15.11 and 15.13 should be excluded from the Section 3.2(a). The insurer and the complainant have agreed that the Items 15.11 and 15.13 are to be excluded because they relate to termite damage which is excluded under the policy. It is fair and appropriate that the First Determination be revised accordingly in this Supplementary Determination.
whether the independent building consultant/ engineer should review the additional items sought by the complainant on 25 November 2024 to make an assessment for damage caused by the insurer’s builder (requiring rectification). The insurer and the complainant have agreed the independent building consultant/ engineer should review the additional items sought by the complainant on 25 November 2024 to make an assessment for damage caused by the insurer’s builder (requiring rectification). It is fair and appropriate that the First Determination be revised accordingly in this Supplementary Determination.
whether the independent building consultant/ engineer should review the items in the document prepared by N on 5 December 2024 and known as the 0.2 N SOW (which is to be provided by the insurer to the independent building consultant) and provide an updated itemised quote to enable a cash settlement to be paid by the insurer. The insurer and the complainant have agreed that the independent building consultant/ engineer should review the items in the 0.2 N SOW and provide an updated itemised quote to enable a cash settlement to be paid by the insurer. It is fair and appropriate that the First Determination be revised accordingly in this Supplementary Determination.
whether the independent building consultant/ engineer should review (or the insurer should cash settle) the insurer’s original builder’s 26 April 2024 SOW. This issue was raised by the complainant and declined by the insurer. It would not be fair for the building consultant/ engineer to have to review (or for the insurer to cash settle) the insurer’s original builder’s 26 April 2024 SOW. This is because the repairs to be assessed by the independent building consultant/ engineer are now not the same scope and the 26 April 2024 SOW is outdated by the events which have occurred.
2.2 Why is the outcome fair?
Yes. It is fair for the First Determination to be revised as set out in this Supplementary Determination and to assist the complainant and the insurer in the resolution of this complaint.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
3.2 Repairs to be costed by the independent building consultant/ engineer
Insurer’s agreed items to be cash settled (excluding Items 15.11 and 15.13)
Items sought by the complainant to be cash settled provided the independent building consultant/ engineer is of the opinion that they were damaged by the storm or by the insurer’s builder and do not duplicate items in Section 3.2(a) of this Determination
replacement of bottom kitchen cabinets
replacement of kitchen benchtop
replacement of kitchen splashback
kitchen overhead cupboards to be removed carefully while gyprocking occurs on kitchen walls and then reinstalled
Gyprock of all kitchen walls that were removed
Gyprock of 60mm in two rooms
new stair rail that was damaged where flooding occurred
installation of new cabinet in laundry where flooding occurred and damaged previous cabinet and removal and disposal of old one
building waste removal
reassembly of the wall unit in the outdoor room
damage to curtains in the dining room
full clean and floor cleaning
electrician to reconnect of circuits and certification of appliances are still safe to operate, e.g. oven, air conditioner, power points