Home / QBE / Determination 12-24-148038

Determination 12-24-148038

Insurer refused to accept the builder's margin on a roof variation claim after a hailstorm

FirmQBE
Decided2025-05-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,067
Non-financial loss—
Amount claimed$5,267
SourceAFCA PDF

Summary

The insurer accepted a roof hail claim and an electrician's invoice for a variation but rejected the builder's 20% margin. AFCA required payment of the full $2,067 variation with interest, but rejected the $3,200 non-financial loss claim.

A builder is entitled to a margin on work done by engaged trades under standard industry practice, but the delay was mainly caused by the representative's refusal to provide the invoice, so no non-financial loss is payable.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-148038 | Financial firm | QBE Insurance (Australia) Limited Case number: 12-24-148038 30 April 2025 Determination overview Complaint The complainant holds a home building and contents insurance policy with the financial firm (insurer). He lodged a claim with the insurer on 24 March 2023 for damage to the roof of the dwelling caused by a hailstorm that occurred on 20 October 2021. The insurer accepts the claim. It agreed to the complainant’s request for a cash settlement based on the insurer’s builder’s (AB) scope of works and quote (SOW). Following the cash settlement the complainant submitted a further variation SOW from its builder (AC). The insurer accepts the amount of the electrician’s invoice (CG). However, it does not accept the builder’s margin included in AC’s invoice. The complainant disputes the insurer’s rejection of the builder’s margin. He wants:  the insurer to accept AC’s invoice in full  $3,200 compensation for non-financial loss (NFL) for the delays in resolving the claim variation. A representative has assisted the complainant. Any reference within this determination to the complainant will include a reference to the representative unless otherwise stated. Issues and key findings Is the insurer required to pay the builder’s margin? Yes. This is because the exchanged information shows, on balance, AC is entitled to add a builder’s margin to the variation. Is the complainant entitled to NFL? No. This is because the exchanged information shows the delay in the insurer’s acceptance of the variation claim is because of the complainant’s representatives’ failure to provide the insurer with sufficient information to allow it to assess the claimed variation. Why is the outcome fair? The exchanged information shows AC is entitled to include a builder’s margin in the variation. It would be unfair for the insurer to exclude it from the accepted variation claim. It would be unfair to require the insurer to pay NFL. This is because complainant’s representative unreasonably delayed providing the insurer with sufficient information to assess its liability relating to the claimed variation. Determination This determination is partially in favour of the complainant. Within 14 days of receiving notice the complainant accepts this determination the insurer is required to pay the complainant $2,067 plus interest in accordance with s. 57 of the Insurance Contracts Act 1984 (the Act). Interest is to be paid from 6 February 2025 until the date of settlement. Reasons for determination Is the insurer required to pay the builder’s margin? Yes. This is because the exchanged information shows, on balance, AC is entitled to add a builder’s margin to the variation claim. Insurer accepts claim and variations The parties agree a valid claim has been established. The insurer accepts the claim. Following lodgement of the claim for hail damage to the roof on 24 March 2023, the insurer appointed a panel builder (AB). AB attended the property and provided a SOW and quote for repairs. The insurer sent this to the complainant with a request he obtain his own SOW and quote. The complainant did not obtain a SOW and accepted AB’s quote as a basis for settlement. On 29 May 2023, a cash settlement in the amount of $40,837 was paid to the complainant following the return of a signed cash settlement fact sheet and release. On 7 July 2023, the complainant sent a variation to the insurer in the amount of $5,417. Despite concerns the amount of the variation was excessive, the insurer accepted the variation and remitted payment to the complainant on 23 October 2023. The dispute is about a further variation request sent to the insurer on 7 July 2024; over 12 months after the initial settlement date. The variation is for the cost to meet the energy company’s safety requirements for replacement of the roof. CG performed the works in February 2024 and invoiced AC in the amount of $1,722 on 20 May 2024. However, the variation report and quotation for $2,067 submitted by AC includes a 20% builder’s margin. The insurer accepts CG’s invoice. However, it rejects AC’s entitlement to the builder’s margin. Parties disagree about inclusion of builder’s margin The insurer says the builder’s margin does not apply. This is because AC did not perform the work. As such, there were no extra costs for labour or materials incurred by AC. It also says the:  original SOW from AB includes such works by an electrician  initial cash settlement for $40,837 is based in AB’s SOW  variation is to adjust costs associated with extra works required by the energy company so there is no provision to apply a builder’s margin to the paid invoice. The complainant rejects the insurer’s submissions and says:  the variation should have been included in the approved scope of works for the roof replacement. The approved SOW includes a builder’s margin in accordance with standard industry practice  the builder’s margin is an allowance that covers additional indirect expenses incurred in performing extra work. These include: > compliance and safety regulations for modification of the structure > co-ordination with trades to ensure completion of the work > insurance and liability provisions covering the additional scope. Insurer required to accept variation in full I have carefully considered all the exchanged information. I am satisfied, on balance, the insurer is required to accept AC’s variation inclusive of the builder’s margin. I am satisfied AC entitled to a builder’s margin even if it did not perform the work. This is because:  AC engaged CG; a suitably qualified trade to do the electrical work required by the energy company. CG invoiced AC for the works in May 2024  AC is responsible for the oversite of work performed by CG  it is standard industry practice to add a margin to work completed by third parties to cover indirect costs, overheads, and a margin for profit  a builder’s margin is a legitimate part of a builder’s pricing structure reflecting their role as project manager and principal contractor. The amount is dispute is $313 (plus GST). The insurer accepts the variation to the SOW and agrees to pay for the cost of the work performed by CG. The original scope and quote that formed the basis for the initial cash settlement includes a builder’s margin. Given the above, it is fair in all the circumstances the insurer accepts the builder’s margin included in AC’s variation report. Within 14 days of receiving notice the complainant accepts this determination the insurer is required to pay the complainant $2,067 plus interest in accordance with s. 57 the Act. Interest is to be paid from 6 February 2025 until the date of settlement. Is the complainant entitled to NFL? No. This is because the exchanged information shows the delay in the insurer’s acceptance of the variation claim is because of the complainant’s representatives’ failure to provide the insurer with sufficient information to allow it to assess the claim. Complainant’s representative primarily caused delay The complainant says the insurer should pay $3,200 NFL because of the delay in resolving the claim variation. The situation has been ongoing since July 2024, prolonging the uncertainty and adding to the complainant’s frustration. I am satisfied it would be unfair to require the insurer to pay NFL in this instance. This is because the exchanged information shows the delays were primarily caused by the complainant’s representative. The exchanged material shows:  following submission of the variation on 4 July 2024 the insurer sent it to an assessor on 8 July 2024. The variation included the energy companies’ safety advice however omitted any quote or invoice from the electrician (CG)  on 15 July 2024 the insurer expressed concerns about the delay in the completion of repairs. It suggested its panel builder could expedite the process  on 23 July 2024 the insurer requested trade quotes to validate the costs of the variation. This is because NearMap images show the roof repairs had already been completed  the complainant’s representative lodged a complaint with the insurer about its claim manager and the request for trade quotes  on 25 July 2024 the insurer responded; it appointed a new claims manager and reiterated its request for supplier quotes or invoices for the completed works  in response, the complainant’s representative said the insurer should arrange for its own comparative quote to validate the variation rather than relying on it to do so  the complainant’s representative maintained this position until January 2025 when it provided unredacted documentation to AFCA at AFCA’s request. On receipt of this information the insurer agreed to accept the costs included in CG’s tax invoice in the amount of $1,722.60 on 6 February 2025. The insurer says:  the invoice is dated 20 May 2024; had the complainant provided this invoice unredacted at the time the variation claim was lodged, it could have assessed it sooner  the invoice was only submitted by the complainants’ representative as part of the AFCA process  as it did not have the opportunity to review the invoice or costing it has not contributed to the delay. I am not persuaded by the argument the onus is on the insurer to obtain its own comparative quote to validate the variation. This is because:  the onus rest with the complainant to prove the additional work claimed is reasonable, necessary, and directly related to the insured event  supporting evidence is required to establish the variation claim. The insurer has the right to review the variation request. The insurer made a reasonable request for supporting documentation to enable it to perform its assessment. CG performed the work in February 2024 and invoiced AC in May 2024. CG’s invoice was available at the time the variation claim was lodged with insurer in July 2024. The complainant’s representative unreasonably refused the insurer’s multiple requests for this information. Its refusal delayed the assessment process. Had the complainant’s representative submitted CG’s invoice to the insurer when the variation claim was lodged in July 2024, I am satisfied the insurer would have assessed the claim sooner. Given the above, the insurer is not required to pay the complainant NFL. Why is the outcome fair? The exchanged information shows AC is entitled to include a builder’s margin in the variation. It would be unfair for the insurer to exclude it from the accepted variation to the SOW. It would be unfair to require the insurer to pay NFL. This is because complainant’s representative unreasonably delayed providing the insurer with sufficient information to assess the claim. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.