Home / Auto & General / Determination 12-24-141129

Determination 12-24-141129

Delays and mishandling of storm damage claim repairs by insurer's builders

FirmAuto & General
Decided2025-05-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

Complainants' storm damage home claim was accepted but repairs were significantly delayed, partly by the insurer's builders. AFCA ordered $500 non-financial loss each and required the insurer to offer a choice between continuing with the builders or a cash settlement.

The insurer is responsible for its agents' delays, so further non-financial loss is warranted and the complainants should choose between the current builders or a reinstated cash settlement.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-141129 | Financial firm | Auto & General Services Pty Ltd Case number: 12-24-141129 30 April 2025 Determination overview Complaint The complainants lodged a claim with the financial firm (insurer) under their home insurance policy. The insurer accepted the claim and organised a scope of works (SOW). The complainants are dissatisfied with the way the insurer handled the claim. Issues and key findings Did the insurer mishandle the claim? Yes. The insurer and its agents were partially responsible for delays. However, there were also unforeseen delays due to the need to obtain multiple council permits. Are the complainants entitled to additional compensation? Yes. As the insurer has already paid compensation of non-financial loss for delays in June 2024, a further $500 non-financial loss for each complainant is appropriate. How should the claim be resolved? Given the delays have to a large extent been caused by the current builders it is appropriate for the insurer to offer the complainants the following options: continue with the current builders, or reinstate the offer of a cash settlement of the claim. Why is the outcome fair? The exchanged information shows the insurer delayed the claim, causing the complainants and their family stress and inconvenience. Given the significant delays caused by the builders, it is appropriate for the insurer to allow the complainants to choose to either retain the builders or accept a cash settlement. Determination This determination is in favour of the complainants. Within 14 days of receiving notification of the complainant’s acceptance of this determination, the insurer is required to pay the complainants $500 each and provide them with the option to either continue with the current builders or accept a cash settlement. Reasons for determination Did the insurer mishandle the claim? Yes. The insurer and its agents were partially responsible for delays. However, there were also unforeseen delays due to the need to obtain council permits. Claim has been delayed On 13 February 2024, the complainants lodged a claim saying the insured property had been damaged by a fallen tree during a storm. The claim was accepted. However, there were delays due to the following disputes: the scope of works (SOW) including whether the slab, retaining walls and fence were covered under the policy, whether the fence was 50% or 100% owned by the complainants, and specifications for the fence, including whether it was timber, colorbond or a combination of both, the fence height and whether it was compliant. In addition, there have been the following delays: the builders commencing the remediation works the need to obtain permits to erect the fence the need to obtain permits to work on council ground while erecting the fence the failure by the builders to identify the structural damage to the property until the time the buildings works were due to commence additional investigations to address the structural damage the need to obtain a building permit for the structural damage the complainants not signing the SOW due to disputes about the scope of the works, and additional damage caused due to delays in remediating the initial damage. Complainants sought new builder The complainants expressed dissatisfaction with the builder multiple times since the claim was lodged and requested new builders be appointed. The insurer initially advised the complainants this could be considered. The insurer’s claim notes reveal the complainants were offered a cash settlement on 6 August 2024 due to delays. However, the complainants rejected that offer to retain their warranty. The insurer rejected the complainant’s subsequent request for new builders to be appointed as a new builder may not warrant the works completed by the current builders and may cause further delays. The complainants also say there is remaining debris from the storm. They have provided photographs of roof tiles on the ground. The insurer’s claim notes reveal the tree that damaged the property was removed. There is no information on file to determine whether the tiles are or will be removed, or whether they will be used during the remediation. I could not identify any complaint made by the complainants about the tiles within the claim notes, although as noted above it is unclear whether the tiles will be used and/or removed during the remediation. Until the damage caused to the roof is remediated, I am unable to address this issue. Some delays outside insurer’s control The insurer could not control the following delays the need to obtain multiple permits from the council, assessing some of the variations to the SOW including the retaining wall and garden shed slab enquiries about the fence including whether it was compliant given it was originally built to code at a height of 1.8m but subsequently changed to 2.4m, and the materials used for the fence including whether it should be reconstructed using timber, colorbond, or a combination of both, and changes to the footings given the 2.4m height. However, the insurer, who is responsible for the actions of its agents, including the builders, was responsible for the following delays: the repeated need for the complainants to confirm the fence was 100% their property rather than only 50% delays by the builders in commencing the works the failure by the builders to identify the damage to the roof was structural and the delays in submitting an application to council for the building works, and the need for reassessment due to additional damage caused by the delayed repairs. Insurer mishandled claim As the insurer and its agent, the builder, contributed to significant delays, I am satisfied the insurer mishandled the claim. The insurer should pay compensation for stress and inconvenience the complainants suffered as a result. Are the complainants entitled to additional compensation? Yes. As the insurer has already paid compensation of non-financial loss in June 2024 for delays, a further $500 non-financial loss for each complainant is appropriate. AFCA can award compensation for non-financial loss AFCA will award compensation for non-financial loss (capped at $6,300) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because complainants have suffered some inconvenience and delays. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. The complainants are dissatisfied with the insurer’s handling of the claim Amongst other things, the complainants say: there was a lack of communication from the insurer’s builders regarding the progress of the repairs the repairs have been delayed they have incurred unnecessary energy costs due to the loss of heat because of the damage and the need to install air-conditioning they have lost some use and privacy of their property due to the lack of fencing, and they have been unable to use part of the house due to the unrepaired damage. The insurer does not dispute that there were delays in commencing the repairs. The insurer agreed to waive the $1,000 excess and pay non-financial loss compensation of $2,000 following an earlier AFCA complaint. The complainants accepted that offer on 15 June 2024 and subsequently made the current complaint to AFCA in September 2024 for further delays. The complainants are not seeking monetary compensation but instead have brought the complaint to AFCA to expedite the remediation. Given the insurer has already paid compensation of non-financial loss for delays, a further $500 non-financial loss for each complainant is appropriate. How should the claim be resolved? Given the delays have to a large extent been caused by the current builders it is appropriate for the insurer to offer the complainants the following options: continue with the current builders, or reinstate the offer of a cash settlement of the claim. The insurer offered a cash settlement The complainants were offered a cash settlement which they rejected due to concerns about warranties. Since 23 May 2024 the complainants have expressed dissatisfaction with the current builders and have made multiple requests for a new builder to be appointed. On 7 August 2024, the complainants were told they could have new builders appointed. They were subsequently advised that new builders could not be appointed due to the new builder’s inability to warrant the work performed to date by the current builders. The insurer is responsible for the work of its agents, including the current builders. If there were warranty issues with the work performed by the current builders, the insurer would be liable for rectification of that work, whether that rectification be performed by the current or newly appointed builders. Accordingly, warranty concerns do not prevent the insurer from appointing new builders. The insurer should reinstate the offer of a cash settlement The complainants lodged their complaint with AFCA seeking expedition of their repairs rather than monetary compensation. As noted above the insurer has previously offered non-financial loss and a cash settlement. Given the complainants are concerned about the delays which are in part due to the actions of the current builders, the insurer should reinstate the offer of a cash settlement. A change of builders at this stage of the claim is likely to further delay remediation. Why is the outcome fair? The exchanged information shows the insurer delayed the claim, causing the complainants and their family stress and inconvenience. Given the significant delays caused by the builders it is appropriate for the insurer to allow the complainants to choose to either retain the builders or accept a cash settlement. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Chronology The following chronology is based on the information on file and includes some significant dates. In addition to the dates below there were other dates where the complainants sought updates, however as the insurer does not say the complainants have failed to mitigate the delays, the additional contact does not alter the outcome of the complaint. | Date | Action | 13-02-2024 | Insured event and claim lodged | 17-02-2024 | Builders site inspection | 27-02-2024 | Roof Inspection report | 01-03-2024 | Insurer provided report advising complainants to address maintenance items. | 05-03-2024 | Permit application (working within road reserve) submitted to council | 28-03-2024 | SOW issued but did not include full amount for fence | 12-04-2024 | Updated SOW | 26-04-2024 | complainants sought further update from insurer | 06-05-2024 | Updated SOW received but did not include fence | 15-05-2024 | Insurer advised complainants own 100% (not 50%) of fence | 20-05-2024 | Complainants say they requested new builders | 23-05-2024 | Contracts issued for building works. Complainants express dissatisfaction with builders. | 14-06-2024 | Issues with SOW raised. Compensation offered for non-financial loss | 15-06-2024 | Complainants accept offer of non-financial loss ($1,000 excess waived and additional $2,000) | 18-06-2024 | Insurer reviews variation request | 24-06-2024 | Complainants offered cash settlement. Complainants advised they would obtain their own quotes. | 30-06-2024 | Contracts signed for building works | 17-07-2024 | Variation quote from builders for fence | 22-07-2024 | Complainants say builders attend site but advise a permit is required for the fence | 29-07-2024 | Variation required due to structural work. Building permit required, complainants and insurer advised it would take 6-8 weeks to obtain. | 01-08-2024 | complainants seek update | 06-08-2024 | Complainants request new builder | 07-08-2024 | Complaint made to insurer. Offered cash settlement based on current SOW or retain current builders. Asbestos report confirmed no asbestos. | 23-08-2024 | Complainants advised documents submitted to council due to structural work in roof | 05-09-2024 | Complainants advised documents sent to council | 09-09-2024 | Complainants report further damage to due delays in remediation | 11-09-2024 | Council approved fence. | 18-09-2024 | Permit received from council for fence | 22-11-2024 | Building works permit for home and fence

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.