Claim declined for retaining wall collapse and damage; insurer said cause was drainage and other excluded factors, not storm or landslide
Text of the determination
Determination
|
Case number
|
12-24-131578
|
Financial firm
|
Allianz Australia General Insurance Limited
Case number: 12-24-131578 4 September 2025
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents insurance policy issued by the financial firm (insurer). The policy provides cover for loss or damage caused by storm, and loss or damage caused by or arising from landslide if it is caused directly by and within 72 hours of a storm.
The complainant lodged a claim with the insurer for damage to a boulder wall and other property following the collapse of the wall.
The insurer denied the claim on the basis the loss was caused by factors such as inadequate drainage, rather than a storm or resultant landslide. The insurer also states that loss or damage to retaining walls is expressly excluded from cover under the policy.
1.2 Issues and key findings
Is the loss covered under the policy?
The claimed loss and damage is covered under the policy, in part.
I am satisfied that the proximate cause of the claimed damage to the insured property was landslide caused directly by and within 72 hours of storm activity. This is covered by the policy. Moreover, the insurer can rely on the retaining wall policy exclusion to exclude its liability for damage to the wall itself, but not if repair of the wall is necessary to remediate the covered damage.
Should the insurer pay non-financial loss compensation?
Yes. The insurer should pay non-financial loss compensation to the complainant in the sum of $2,000.
Why is the outcome fair?
An insured event occurred that caused damage to the insured property. It is fair that the policy responds to this. The insurer is not entitled to rely on the policy exclusions to deny the claim, except for the repair or replacement of the retaining wall itself which is a policy exclusion. However, it is fair for the retaining wall to be repaired and/or replaced if this is shown to be fundamental to repairing the claim-related damage to the property.
An award of non-financial loss compensation is also justified in the circumstances.
1.3 Determination
This determination is partially in favour of the complainant.
If the complainant accepts this determination, the insurer is required to accept the claim for the storm-related damage (excluding repairing the damage to the retaining wall itself) and assess it in accordance with the policy’s terms and conditions and section 2.1 below.
2 Reasons for determination
2.1 Is the loss covered by the policy?
The claimed loss and damage is covered under the policy, in part.
I am satisfied that the proximate cause of the claimed damage to the insured property was landslide caused directly by and within 72 hours of storm activity. This is covered by the policy. Moreover, the insurer can rely on the retaining wall policy exclusion to exclude its liability for damage to the wall itself, but not if repair of the wall is necessary to remediate the covered damage.
Complainant seeks cover for damage caused by storm and landslide events
At the rear of the complainant’s property, there is a system of at least three boulder retaining walls, separated by terraces on each level. Two terraces sit below the upper terrace on which the main dwelling is located, and slope downwards towards a water body located to the south of the property. Together, these walls provide support for the terraces and ultimately the upper terrace on which the main dwelling is located.
On 12 May 2024 the lowest boulder wall collapsed following a landslide. This damaged the wall itself, as well as timber stairs, a timber boardwalk, a sewer pipe and a boundary fence at the insured property. The wall was again damaged following further landslide on 7 June 2024. There was prolonged and intermittent rainfall and storm activity occurring on and in the days preceding the landslides.
The complainant’s policy covers damage caused by one of the listed events. It does not provide cover for all damage. Amongst these events is cover for loss or damage caused by or arising from landslide if it is caused directly by and occurs within 72 hours of a storm. The PDS at page 17 states:
Storm, cyclone, rainwater or run-off. What’s covered? Building and/or contents…
Loss or damage caused by or arising from: landslide…if it is caused directly by and occurs within 72 hours of a storm.
The complainant says the cause of the loss or damage to the insured property is landslide caused by the storm activity. This is supported by the report of her geotechnical forensic investigator, TI, which states:
a rotational landslide has occurred…Surface waters were flowing along the site boundary during a prolonged and intermittent storm event…The cause of the above failure is deemed to be a prolonged rainfall event in May 2024. This event involved almost 200mm of rain falling over several days with the failure triggered when an additional 100mm rain fell in a 24 hour period shortly thereafter…It is deemed that the failure occurred because of this rainfall event.
Insurer says the damage was caused by factors excluded from cover
The insurer says the proximate cause of damage is not landslide caused by and within 72 hours of storm. Rather, the insurer says the retaining wall’s failure and subsequent collapse causing damage to the wall and other insured property, was due to poor construction, inadequate draining, hydrostatic pressure, vegetation growth and gradual soil movement. These causes are not covered by the policy.
The insurer relies on the reports of its engineer, SE, and geotechnical specialist, WG, which state various and multiple factors caused the collapse of the wall, being soil erosion, inadequate drainage (resulting in hydrostatic pressure), vegetation growth, long-term weathering, and poor construction by today’s standards.
The insurer also states that TI’s report supports SE and WG’s findings of hydrostatic pressure and drainage issues being present.
Cause of claimed damage is storm and landslide events
There is no dispute that storm and landslide events occurred at the insured property on the relevant dates. The dispute is whether the cause of the damage to the insured property was these storm and landslide events.
Damage can have more than one cause. When deciding whether the policy responds, the proximate cause of the damage needs to be identified. This is a question of fact depending on the circumstances. The proximate cause is not necessarily the first or last or the sole cause of the loss. It is the effective, dominant or operative cause of the loss.
I have considered all the exchanged information. Whilst I acknowledge there may have been other contributing factors, I am satisfied the exchanged material shows that the collapse of the wall and resulting damage to the insured property only occurred because of the landslides, and that these landslides were caused directly by the storm activity. This is covered by the policy.
TI’s report is persuasive in its reasoning that the landslides caused by storm activity were the proximate cause of the failure of the retaining wall and resultant damage.
I am not persuaded that the insurer’s engineer or geotechnical specialist reports sufficiently refute this, nor demonstrate that these other factors would have caused the ‘inevitable’ failure of the wall, as submitted by the insurer. WG’s and SE’s reports confirm that, although the wall may have been impacted by factors such as soil erosion, hydrostatic pressure, vegetation growth and age, the landslides following the storm activity were the proximate, dominant and operative cause of the damage. WG states:
Despite the somewhat haphazard boulder placement of the components making up the retaining wall, and possible seepage induced settlement, it has stood for an estimated 25 to 50 years until the recent prolonged rainfall events. [Local] Weather Observations (BoM) for May 2024 show from the 2nd until 11th May, 296 mm fell (in 10 days). This high volume of rainfall reduced [the] soil[‘]s capacity to absorb further moisture. The cohesion between the soil particles was reduced behind the wall and the saturated soil was at close to its maximum load. Given the existing saturated soil conditions, the additional 96mm of rainfall that fell on Sunday the 12th is the event that ultimately resulted in the wall failure.
Whilst SE attributes the wall collapse to ‘a combination of ongoing issues’ rather than ‘a single isolated event’, it nonetheless acknowledges the storm event as the ‘catalyst’ and having ‘triggered’ the collapse. Ultimately, I am satisfied the loss is covered by the policy.
Policy exclusion for loss or damage to retaining walls applies
The policy specifically excludes ‘loss or damage to...retaining walls’ from storm and landslide cover.
Whilst the policy does not contain a definition of a ‘retaining wall’, the expert reports are all in agreement that the wall is a retaining wall.
The complainant says the wall is a ‘free draining wall’, rather than a ‘retaining wall’. The complainant says TI was only quoting from the insurer’s expert reports when calling it a ‘retaining wall’. I am not persuaded this is the case.
Whilst TI’s report refers to the wall as a ‘dry rock boulder wall designed as a gravity wall that relies on interlocking boulders’, this does not mean it is not a retaining wall. TI also states that such a wall ‘can be extremely effective as a retaining wall’. Moreover, TI refers to the wall as a ‘retaining wall’. For example, TI’s site observations refer to the relevant wall as one of ‘at least three (3) dry stack retaining walls’.
The expert reports also variously refer to the wall as having functioned as a retaining wall to retain the soil on the slope in the area above it.
I am satisfied that the boulder wall that collapsed is a retaining wall.
The policy contains an exclusion from storm cover for ‘loss or damage to…retaining walls’ [emphasis added].
I am satisfied the insurer is entitled to rely on this exclusion to deny the claim for loss or damage to the retaining wall itself. However, this exclusion is limited to the wall only, and does not extend to loss or damage to other items of insured property.
This policy exclusion, however, does not operate by reference to the storm-related repairs that are required to the storm-damaged property. Therefore, this exclusion will not be able to be relied on by the insurer should it be established (pursuant to this Determination) that the repair or replacement of the retaining wall is a necessary requirement for safe and effective repairs to the storm-damaged property.
Insurer has not established that any other policy exclusions apply
The insurer says that, even if a storm or resultant landslide is the proximate cause of the loss or damage, the loss or damage to the other insured property is not covered due to policy exclusions.
The exclusions under the policy that the insurer relies on in this regard are set out in the PDS at pages 17 and 55 as follows:
Loss or damage caused by…hydrostatic pressure.
Loss, damage…as a result of, or caused by or arising from…Wear and tear…Including depreciation, gradual deterioration, wear and tear or lack of maintenance.
Loss, damage…as a result of, or caused by or arising from Inherent defects…Including faulty design or materials, structural defects or poor workmanship.
Loss, damage…as a result of, or caused by or arising from Soil movement…Including erosion, landslide, mudslide or subsidence unless it is directly caused by and occurs within 72 hours of an explosion, earthquake, tsunami, storm or flood (where your policy schedule shows you have optional cover for flood).
The insurer states in its response to AFCA’s Preliminary Assessment on this matter that:
As the damage to stairs and sewer pipe have been caused by the retaining wall[‘]s collapse, and the collapse of the retaining wall has in turn been caused by exclusions under the Complainant’s policy, the damage to the stairs and sewer pipe have also been caused by and arisen as a result of the exclusions under the policy.
However, as set out above, I am satisfied that the collapse of the retaining wall, and the resulting damage to the other property, was caused by the landslide following the storm activity rather than these other factors.
Whilst these other factors may have been present, they did not cause the loss or damage.
The loss or damage to the other property, being the timber stairs, a timber boardwalk, a sewer pipe and a boundary fence only occurred because of the failure of the retaining wall, which only occurred because of the storm activity. Landslide following storm activity is what ultimately caused loss or damage to the property, when viewed as a chain of events. The exclusions therefore do not apply.
Insurer to obtain scope of works
Within 21 days of receiving notice that the complainant accepts this determination, and subject to the complainant providing reasonable access to the property, the insurer must:
· pay to the complainant the sum of $2,000 in non-financial loss compensation; and
· engage an engineer, licensed building specialist and/or other suitably qualified experts (including, if necessary, a plumber), to draw up a comprehensive, up-to-date scope of works (SOW) regarding the necessary repairs and associated remedial works to the complainant’s property that I have determined is covered. For the sake of clarity, this is the damaged timber stairs, timber boardwalk, sewer pipe and boundary fence.
The SOW must also address whether repair or replacement of the retaining wall is fundamental to the remedial works of the covered insured property. If this is the case, then the SOW also needs to include the:
· repair and stabilisation of the retaining wall that failed; and/or
· supply and installation of a new robust, reinforced retaining wall to replace the wall that failed; and
· stabilisation or replacement of the other retaining walls located on the property to the extent that this is required for the repair or replacement of the property covered by the claim.
The abovementioned works must also, where required, be the subject of certification by the appropriately qualified specialists (such as geotechnical engineers) and must meet all applicable current Australian and New South Wales building, safety and construction standards.
Then, within a further 14-day period of receipt of the SOW, the insurer is to obtain at least one actionable quotation based upon the SOW, either by way of a tender process or otherwise. Each builder engaged to provide quotes must visit the site in preparing their quote.
Within seven days of receipt of the SOW and associated quotation(s), the insurer must elect to either:
· commence the necessary repairs and associated works at the earliest available date, or
· offer a cash settlement to the complainant comprising a sum equal to the total of the preferred actionable quotation, plus a 20% contingency on top of this to factor in the risk of the works passing to the complainant and the likely possibility that further works may be required.
Given any cash settlement will be based on an up-to-date estimates with a contingency uplift, I am satisfied there is no need to award interest.
The insurer’s liability is limited to the building sum insured. The insured is also able to rely on the settlement conditions in the PDS for dividing fences if the damaged boundary fence is a dividing fence.
2.2 Should the insurer pay non-financial loss compensation?
Yes. The insurer should pay non-financial loss compensation to the complainant in the sum of $2,000.
AFCA can award compensation for non-financial loss
Under the AFCA rules, non-financial loss compensation (capped at $6,300) may be awarded in circumstances where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Moreover, non-financial loss compensation is not intended to be a punishment for any wrongdoing on the part of the insurer.
Complainant is seeking compensation
The complainant has stated that the stress of dealing with the insurer and its experts has been ‘substantial’ and that she has been required to deal with an unreasonable number of communications from her insurer about her claim.
She has also stated that she experienced an unreasonable delay in obtaining assurances that her property was safe to continue living in, delays in having the sewer pipe temporarily repaired leading to an unreasonable period of raw sewage leaking onto the property, and delays in having the sewer pipe permanently repaired which has caused discomfort and stress, particularly due to having the sewer pipe diverted onto her neighbour’s land as a temporary fix.
Compensation is warranted
I accept the complainant in this matter has suffered an unusual degree of physical inconvenience and interference with her expectation of enjoyment and peace of mind, and also unreasonable delay in resolving her claim. In particular:
· The insurer’s decline of the claim relating to the damaged sewer pipe means it has been diverted onto the complainant’s neighbour’s property for over one year. I acknowledge the stress and strain this has placed on the complainant and her relationship with her neighbours.
· I have also considered the complainant’s distress about feeling ‘overwhelmed’ at being contacted by ‘around 20 people from various companies’ and also ‘three different loss adjusters who I had to explain everything to again from scratch’. Whilst it is not unusual to deal with various parties in the assessment of a claim, this is an excessive number given the circumstances and I accept that this caused the complainant an unusual additional amount of stress and inconvenience.
· I also acknowledge the poor experience of the complainant in the initial stages following the claim denial where the insurer failed to give her time to make further submissions in the internal dispute resolution process. This caused the complainant further anxiety and inconvenience.
Given these considerations, the insurer is required to pay to the complainant the sum of $2,000 in non-financial loss compensation.
Reimbursement of professional costs
Under AFCA Rule D.5, AFCA can determine an insurer contribute up to $5,000 in professional costs reasonably incurred by a complainant in the course of a complaint. The complainant incurred report fees in obtaining a report from TI. The report assisted the complainant in establishing her case and was relied upon in reaching this determination.
I therefore consider it is fair for the insurer to reimburse the complainant for her costs in obtaining the report, together with interest calculated pursuant to section 57 of the Insurance Contracts Act 1984 from the date of the complainant’s payment for the report.
2.3 Why is the outcome fair?
An insured event occurred that caused damage to the insured property. It is fair that the policy responds to this. The insurer is not entitled to rely on the policy exclusions to deny the claim, except for the repair or replacement of the retaining wall itself which is a policy exclusion. However, it is fair for the retaining wall to be repaired and/or replaced if this is shown to be fundamental to repairing the claim-related damage to the property.
An award of non-financial loss compensation is also justified in the circumstances.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.