Home / Suncorp Group / Determination 12-24-130828

Determination 12-24-130828

Dispute over the cash settlement amount for storm/rockfall damage to the home

FirmSuncorp Group
Decided2025-09-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$261,986
Non-financial loss—
Amount claimed$300,581
SourceAFCA PDF

Summary

The complainants' home was severely damaged by a rockfall and they disputed the insurer's $548,419.71 cash settlement. AFCA found the insurer's quote was not actionable and ordered it to pay a further $261,986.04.

The insurer's preferred quote was a non-actionable liability quote, so BA's actionable quote was the fair basis for settlement, plus a 5% contingency for transfer of risk and delay.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-130828 | Financial firm | AAI Limited Case number: 12-24-130828 9 September 2025 1 Determination overview 1.1 Complaint The complainants held a home and contents insurance policy underwritten by the financial firm (insurer). In October 2020, the complainants’ home, which sits on a steep slope next to a park, was severely damaged by a rockfall. The complainants lodged a claim for the damage. The insurer accepted the claim but said it could not repair the home due to safety concerns at the site. The insurer paid a total of $548,419.71 to resolve the building claim. The complainants say the offer is not enough. They rely on an estimate from their quantity surveyor (BA), who is also a builder. BA says the more accurate repair cost is $771,815. The complainants also seek a 10% contingency uplift to increase the settlement to $848,996.50. 1.2 Issues and key findings Is the insurer required to pay an additional amount? Yes. The insurer’s cash settlement offer is not based on an actionable quote. The best estimate to repair the damage is BA’s quote. It is fair that the insurer increases its offer by $223,395.29 with an additional overall contingency uplift of 5%. This compensates the complainants for the loss of the insurer’s lifetime guarantee and the transfer of risk. Why is the outcome fair? The insurer elected not to undertake the work and therefore the only fair estimate to rely on is from BA. This estimate was inclusive of a contingency uplift (10%) and the insurer is only required to pay the quote amount ($771,815). However, given the delay with settlement, it is fair that the insurer adds an additional contingency of 5%. 1.3 Determination This determination is in favour of the complainants. If the complainants accept this determination, the insurer must, with 14 days, pay them $261,986.04 comprised of: · $223,395.29 to settle the building damage claim · an additional contingency uplift of 5% ($38,590.75) on the total settlement sum ($771,815) to compensate the complainants for the likely increase in costs since BA’s quote was prepared. 2 Reasons for determination The complainants are represented by solicitor MB. For convenience, unless indicated otherwise, reference to ‘the complainants’ will include both. 2.1 Is the insurer required to pay an additional amount? Yes. The insurer’s cash settlement offer is not based on an actionable quote. The best estimate to repair the damage is BA’s quote. It is fair that the insurer increases its offer by $223,395.29 with an additional overall contingency uplift of 5%. This compensates the complainants for the loss of the insurer’s lifetime guarantee and the transfer of risk. Complainants lodged claim for storm damage to home There is no dispute the insured home sustained significant damage on 25 October 2020. This was caused by a rockfall event due to a storm. A claim was lodged for building and contents damage. The contents claim was settled and is not part of this complaint. In March 2021, the insurer accepted the building damage claim. The insurer’s engineer (DW) inspected the home. DW prepared a detailed scope of works dated 26 April 2021 (DW SOW). Despite some initial disagreement between the parties, they now agree the home can be repaired. On 30 August 2021, the insurer informed the complainants it would not perform the repairs and offered to cash settle the building claim for $263,222.59. The insurer later paid an additional amount to the complainants on 14 October 2021. Based on the quote of builder RC, on 10 February 2022, the insurer agreed to add another $259,731.55 to its offer. This brought its settlement payment to $529,997.73. This amount was inclusive of a 10% contingency uplift to compensate the complainants for the transfer of risk and any additional minor repairs which might be required. Subsequently, the insurer also paid a further amount of $25,465.57 on 5 August 2022, bringing the total building settlement paid to $548,419.71. The complainants engaged BA to review the claim documentation. In its report of 9 May 2024, BA estimated the total repair cost would be $771,815, based upon the DW SOW. The complainants seek the difference between the amount paid and BA’s estimate, together with a contingency uplift as the complainants will have to oversee the work. Policy requires insurer to cover cost of repairing house ‘new for old’ The terms of the policy include the Certificate of Insurance and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainants. The policy provides ‘Complete Replacement Cover’ for the home. This means there is no cap on the home cover, with the insurer required to indemnify the complainants for the cost to replace the home. This cover is provided on a ‘new for old’ basis. There is no dispute the complainants have established a claimable loss for damage under the policy. The parties agree the home is repairable in accordance with the DW SOW. They also agree the matter is suitable to cash settle. The parties disagree over the fair amount payable to implement the DW SOW. The insurer has already paid a significant settlement sum to the complainants. There is no reason to consider whether the insurer should attend to repairs. The parties accept a cash settlement is better. I am therefore satisfied the most practical way to resolve the matter will be by considering whether the amount paid is fair, or whether a further payment is warranted. Fair to rely on BA’s quote as a basis for settlement The insurer says BA’s quotation of $771,815 contains contingency allowances which are not justified and therefore excessive. It also notes that BA did not visit the site and simply based its quote on a ‘detailed review of the documentation provided’. The complainants say the $548,419.71 they have received so far is insufficient to repair the damage because: · the insurer’s quotation overlooks or underestimates the likely actual cost of rectification · BA writes that its ‘costings are based on detailed measures using industry rates for similar works, ensuring a precise estimation of the actual costs required for rectification’. I accept the BA quote serves to ensure it can and will undertake the repair work. I also accept it is more likely the BA quote is a fairer estimate of the cost to repair the damage than the insurer’s preferred quote from RC, as: · the insurer’s settlement offer was based on RC’s quote for $481,811.58 prepared on 12 February 2022, to which it added a 10% contingency uplift · this quote is now more than three and a half years old · the quote does not say if it is actionable · the insurer offered to cash settle the claim ‘due to safety concerns at the site’, implying it was not comfortable undertaking the repairs · the claim file notes and the quote itself say it is a ‘liability’ quote, implying RC does not intend to do the work and it is not actionable. The actionability of a quote is a key consideration for its acceptance. Any quote prepared for the repair of the complainants’ home must be actionable. The complainants need to be able to rely on the quote to get the work done for the quoted price by the contractor. I acknowledge a quote prepared without inspection of the site is not without problems. However, the BA quote appears to be the only actionable quote on which the complainants can rely to have the work completed. Based on the exchanged material, I am not satisfied the RC quote is actionable. I am not persuaded the complainants can rely on it to have their home repairs completed. I consider the RC quote served only to provide a figure for cash settlement purposes. I have no confidence a repairer will undertake the work for the complainants at that price. However, I am satisfied BA is prepared to undertake the work for its quoted price. Given this, I consider it is fair that this quote should be relied upon as a basis for settlement. Cash settlement offered by the insurer is not fair in all the circumstances I am not satisfied the insurer can show the amount it offered to resolve the claim will be sufficient to complete repairs. I am also not satisfied the RC quote serves to ensure the complainants can rely upon it to have the home repaired. Given this, I accept an additional settlement amount should be paid. Noting the only viable quote to address the repairs comes from BA, I am satisfied this quote for $771,815 should be preferred as a basis for settlement. As the difference between the amount paid and the BA quote is $223,395.29, I accept this is a reasonable starting point for settlement. As the BA quote includes a 10% contingency, I am not persuaded a further substantial allowance for contingencies is required. However, I acknowledge this amount is not in consideration of the transfer of risk for the insurer. It is a speculative amount added in consideration of possible additional repairs. I also note is has been more than 15 months since BA submitted its quote (9 May 2024). I accept it is possible that some costs have increased. Whilst I expect the contingency allowance in the BA quote ($63,786 plus GST) should cover much, if not all the additional costs, it does not account for the transfer of the building risk. To this end, I am satisfied adding another 5% to the overall value of the quote ($38,590.75) is fair. This additional contingency will compensate the complainants for the loss of the insurer’s lifetime guarantee and the transfer of risk. This brings the additional settlement to $261,986.04 and the overall settlement payment total to $810,405.75. I am satisfied this is a fair amount to resolve the claim. There is no need for the insurer to pay interest on this amount. 2.2 Why is the outcome fair? The insurer elected not to undertake the work and therefore the only fair estimate to rely on is from BA. This estimate was inclusive of a contingency uplift (10%) and the insurer is only required to pay the quote amount ($771,815). However, given the delay with settlement, it is fair that the insurer adds an additional contingency of 5%. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.