Insurer declined most of the claimed cracking damage as ground movement, wear and tear or shower leak, and offered a cash settlement for the cellar wall only

FirmYoui
Decided2025-12-03
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded—
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The landlord insurer accepted only the cellar wall damage and declined the remaining cracking as ground movement or wear and tear. AFCA found escape of water was the proximate cause, required reassessment, a scope of works, a cash settlement with 20% uplift, loss of rent with interest, and $2,000 non-financial loss.

The escape of water was the proximate cause of the significant cracking, so the insurer had not established the exclusions and had inadequately investigated the claim.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial lossreassess claim

Related

All Youi determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-130517 | Financial firm | Youi Pty Ltd Case number: 12-24-130517 28 November 2025 1 Determination overview 1.1 Complaint The complainant lodged claims under her landlord insurance policy (policy) with the financial firm (insurer) after discovering leaking water pipes in the property in June and September 2023. The complainant says the water escaped from a pipe near the bathroom causing cracking in the walls throughout the building. The insurer accepted the damage to the cellar wall, but declined the rest of the damage. It says it was caused by a leak from a shower recess or due to wear and tear, not the escape of water. The insurer says it is entitled to settle the claim with a cash payment for the cost of repair work to the cellar wall because its repairers cannot restore the wall to its pre-event state without performing upgrades to meet current building code requirements. The complainant says the amount offered by the insurer is insufficient. She also seeks loss of rent payments and compensation for non-financial loss. 1.2 Issues and key findings Is the insurer entitled to decline the disputed damage? No. The insurer has not shown it can decline all the disputed damage. The information shows the cracking that occurred after the leaking water pipes was caused by the escape of water. The insurer must undertake a further assessment of this damage. The insurer must also pay loss of rent. Is insurer’s settlement method fair in these circumstances? No. The insurer must undertake a further assessment and establish an agreed scope of work (SOW) with the complainant and obtain an actionable quote to determine a suitable cash settlement figure for the covered damage, together with a 20% uplift for contingencies and the transfer or risk. Is complainant entitled to non-financial loss (NFL) compensation? Yes. The insurer caused unnecessary delay due to improperly handling the claim. The insurer must pay the complainant $2,000 in compensation for non-financial loss. Why is the outcome fair? This is a fair outcome because the insurer has an obligation to assess a claim for damage thoroughly and effectively. Where an insurer has not done this, it is fair to overturn the claim decision, and to appropriately compensate the complaint for the avoidable impacts this has had upon her. 1.3 Determination This determination is substantially in favour of the complainant. Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer is required to: · accept the claim in respect of the disputed damage · pay the complainant $2,000 in compensation for non-financial loss · assess and pay the loss of rent claim under the policy together with interest under section 57 of the Insurance Contracts Act 1984 (Cth) · commence the process to appoint a building consultant to establish the SOW. The insurer must then engage a builder to provide an actionable quote for the repairs. The insurer must then pay this amount together with 20% uplift for the transfer of risk and contingencies within a reasonable time. 2 Reasons for determination 2.1 Is the insurer entitled to decline the disputed damage? No. The insurer has not shown it can decline all the disputed damage. The information shows the cracking that occurred after the leaking water pipes was caused by the escape of water. The insurer must undertake a further assessment of this damage. The insurer must also pay loss of rent. Onus on complainant to show insured event occurred The complainant has the initial onus to show on the balance of probabilities she suffered a loss caused by a risk insured under the policy. If the complainant establishes she has suffered a loss covered by the policy, the onus shifts to the insurer to show an exclusion applies. Subject to its conditions and exclusions, the policy provides cover for loss or damage caused by the insured events listed in the Product Disclosure Statement (PDS), including escape of water. Relevant extracts of the policy’s PDS are set out in section 3.2 of this determination. Parties dispute the cause of the disputed damage The insurer has partially accepted the claim and offered to settle a portion of the claimed damage (being the cellar wall). The complainant says the cracking to her home was caused by the impact of the escape of water on the foundations of her home. In January 2024, the insurer engaged [CZ], a structural engineer. CZ concluded that the cracking damage to the building is the result of long-term differential footing movement. CZ found: ‘The differential footing movement has been contributed to by a footing system of inadequate strength and stiffness and abnormal moisture conditions in reactive soils resulting from site drainage, nearby trees and the investigated water supply leaks.’ ‘The damage is of long-term consequence as evidenced by previous repair attempts.’ ‘The damage is considered to have been exacerbated by the leaks in the water supply system which caused soil swell and heave in the footing system.’ ‘The partial collapse of a cellar wall is the result of inadequate construction. The investigated leaks highlighted a pre-existing defect in the building’s construction. Had the wall been adequately constructed, the collapse would not have occurred.’ ‘Although no movement has yet occurred as a result of the partial collapse of the cellar wall, mitigation works are required to retain the soil and footings in this location to prevent damage from occurring.’ The complainant says the significant movement cracks that are now present were not present prior to the leaks. To support this, she has provided photos from a tenancy report before the leaks occurred. Some minor cracks and water damage appear in the photos in the tenancy report. However, the significant cracks she is claiming do not. The complainant also says any repairs to the minor cracks were before she purchased the property in 2003. Proximate cause of the cracking damage was the escape of water The proximate cause of damage is not the first, the last, or even the sole cause of a loss. It is the dominant and effective cause of the loss. It is the cause which sets the chain of events in motion leading to the damage, and without which, the damage would not have occurred. While it is clear there has been some repair work performed on the property in the past, and some leaks causing mould and water damage to the ceilings, the property in question is 150 plus years old. Despite its age, it was not until recently displaying the significant cracks now present. The tenancy report from shortly before the leaks occurred provides a thorough and complete picture of the state of the property. It does not show a property with substantial cracks one can fit an entire steel ruler into, as shown in later images. These images tell a story of a property that has experienced a recent and substantial event. The information shows the claimed damage is different from the aged repair work the insurer relies on to show there is a historical problem with the property. The insurer has not shown how the current, significant cracking damage originated from the more aged damage. Additionally, the insurer has not explained how the significant cracking can be both long-term, but also have appeared suddenly. CZ comments on the poor quality of the building footings. However, the report does not address how such a fundamentally poor footing system has stood the test of time, but then sudden, major cracks appeared shortly after the escape of water. One would expect significantly more damage and signs of ongoing repair if the cause of the significant cracking was long-term differential movement. CZ also concedes in its report that the water supply leaks are a cause of the differential footing movement and in fact exacerbated the cracking. On balance, the panel is satisfied the information shows the significant cracking the complainant is claiming for was caused by the escape of water. This is because the information shows this damage occurred after and was a result of the escape of a significant amount of water. The escape of water is the proximate cause of the disputed damage. The insurer also says the shower recess itself leaks when in use. This does not explain why this has only caused damage at the time the significant leaks from the mains pipes were detected, which were significant enough to fill the cellar to a foot deep. CR’s report has assessed the water usage and has noted increased water usage at the time of the claimed pipe failures, though has not thoroughly quantified the extent of them. This supports the view the pipe leaks are the more likely cause than a shower recess. The panel is satisfied foundation heave and then drying has the capacity to create the kinds of cracking damage shown in the images, and did so in these circumstances caused by the escape of water. The insurer may not rely on the exclusion for bringing a building up to code compliance. This is because it has not shown it did not comply at the time of construction. Further, this would be unfair because this would render it impossible to repair the property and unfairly burden the complainant with repair costs stemming from the insured event. Some damage may be declined as pre-existing or unrelated to the leak The two cracks noted in BB’s tenancy report have clearly occurred before the leak, meaning the insurer is not liable to repair them. Additionally, the same report notes the signs of leaks leading to water damage and mould in the ceiling and some walls. These can also be declined as pre-existing the leak. The insurer may also be able to decline (upon further assessment) some limited damage in respect of the shower recess. The insurer is also entitled to decline the leaking pipes themselves. The policy does not cover repairs of the item which leaked. Insurer relies on exclusions The insurer has cited several exclusions in the policy to support its decision to decline the majority of the claimed damage. The provisions are set out in full in section 3.2 of this determination. The exclusions the insurer relies on can be summarised as: ground movement wear and tear and other long-term causes water leaking from a shower recess completing work to bring a repair up to current building codes. The insurer has referenced various expert reports to support its position these factors are the proximate cause of the disputed damage and can therefore be declined. Summaries of these reports appear in section 3.3 of this determination. The insurer has also argued at stages through the claim process that other leaks are responsible for the damage, some of which fall within the exclusions cited above. The insurer has not, on the information available, established it may apply any of these exclusions. This is because, on balance, the information shows the proximate cause of the damage was the leaking pipes. Insurer to reattend, ensure property is dry, and assess the damage The insurer must organise a suitably qualified expert to confirm if the footing moisture has returned to normal levels, and if not, to confirm when this is likely. Once the founding soil is dry, if it has not already, the insurer will then need to arrange a thorough inspection of the cracking damage which occurred since the leaks appeared. The insurer must develop a scope of works that covers all the damage caused by the leaking pipes. Insurer to cover the complainant’s loss of rental income The panel is persuaded the property is unrentable in its current state due to the insured event. It will remain so until the repairs are completed. The complainant will need to supply her rental ledger showing the date at which the current tenancy ended to the insurer. The insurer must cover the loss of rent under the policy terms. Additionally, the insurer must pay the complainant interest on the value of any loss of rent payment it has not made until the date of payment under with section 57 of the Insurance Contracts Act 1984 (the Act). The interest payment calculation begins from the date of the insurer’s final decision letter until the date the payment is made. 2.2 Is insurer’s settlement method fair in these circumstances? No. The insurer must undertake a further investigation of the covered damage to ascertain a scope of works. The insurer may not rely on the compliance exclusion. Cash settlement is a fair outcome, once appropriate contingencies are added The panel has considered the insurer’s proposal to settle the claim for the cellar wall as a cash settlement in lieu of repairs given the challenges in repairing a building of this nature. The insurer must instruct a suitably qualified building consultant to create s scope of works, as described above in section 2.1, in addition to the cellar wall. The insurer must then engage a builder to provide an actionable quote. The insurer may not rely on the compliance exclusion in these circumstances. The insurer must pay the complainant based on the actionable quote and increase the cash settlement by 20% for continency and the transfer of risk noting the works are likely to be complex given the age of the property and the extensive damage. 2.3 Is complainant entitled to non-financial loss (NFL) compensation? AFCA’s approach to NFL compensation Under the AFCA Rules, we can award up to $6,300 compensation for non-financial loss. We will only award this type of compensation if a complainant suffers an unusual degree of physical inconvenience, unnecessary delay, or unreasonable interference with their enjoyment of peace of mind because the insurer mishandled the claim. We recognise making a claim can be stressful and time-consuming, even if the insurer handles the claim correctly. We will not award compensation for the ordinary degree of inconvenience that comes with making a claim. An award of NFL is warranted in these circumstances The panel is satisfied an award of NFL is warranted in these circumstances. The panel notes the insurer has not applied sufficient scrutiny to the expert reports and has not organised a geotechnical assessment of the foundation soils when one is needed. This has placed the complainant into a situation of uncertainty and prolonged financial distress for an extended period of time, now reaching more than two years since the first claim was made. The panel has carefully reviewed the call notes, which provide detail about the stress and inconvenience the complainant has experienced. Accordingly, the panel is persuaded $2,000 NFL compensation is fair in the circumstances. 2.4 Why is the outcome fair? This is a fair outcome because the insurer has an obligation to assess a claim for damage thoroughly and effectively. Where an insurer has not done this, it is fair to overturn the claim decision, and to appropriately compensate for the impact of this. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: the legal principles applicable industry codes or guidance good industry practice previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes: an ombudsman a member with significant experience in consumer and small business advocacy a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: available documents the recollections of the parties all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy provisions Escaping Water What is covered? Loss or damage to the insured property caused by escaping water that occurred: suddenly and without warning; or slowly over a period of time and you could not reasonably have been aware of it. … What is not covered? Loss or damage which was: caused by water escaping slowly over a period of time and you could reasonably have been aware of it; caused by water escaping: from a leak in a shower base, recess or cubicle; …General exclusions These general exclusions apply to all sections of your policy. We will not pay for: … additional costs resulting from your buildings or any part thereof not being compliant with building codes, regulations or laws, including any required approval by the relevant building authority, that were already in place when the buildings were originally built, subsequently altered or renovated; … We will not pay for loss, damage or legal liability: … caused directly or indirectly by hydrostatic pressure, rising water table, expansion or contraction of the earth, ground or soil; … We will not pay for death or bodily injury to any person, or loss or damage to property, caused directly or indirectly by: … wear and tear, rust, corrosion, or deterioration; … 3.3 Expert report summary | Record | Key points | Complainant’s real estate agent (BB) Tenancy inspection report 13 February 2023 | · Water stain appearing on the entry hall ceiling outside the master bedroom. · Water stain on the left-hand side of the fireplace in bedroom 1. · Water stain on the left-hand side wall of bedroom 2. · No water staining or mould noted in bathroom 1 (subject of this claim). · Ceiling and pantry has drill holes from recent roof leak and a make safe board in place in the kitchen area. · Movement crack on both sides of the living room heater fire at the plaster join. · Ensuite has a movement crack at the left-hand side of the window. · No damage or cracks noted in the sitting room. · No cracks noted in the property except the living room and ensuite as noted above. | Insurer’s plumber (BL) Leak detection report 27 September 2023 | · Attended property on 27 September 2023 · Confirmed with owner there was a previous leak and now having another leak. · Plumber who last attended said hot pipe behind the shower was leaking. BL confirmed still leaking. · Flood tested the shower base which failed. Water was leaking under the shower base and soaking the chipboard below. · Tap spindles were not silicone sealed and could also be causing leakage. · Capped the hot water line to stop the leaking. · Includes images of the shower spindles, chipboard and bearer beneath the shower, outside of the shower, the stripped bathtub, and the cellar area. | Insurer’s builder (JL) Assessment report 3 October 2023 | · Attended property on 27 September 2023. · Recommends claim should be cancelled due to no resultant damage. · Believes the damage has been occurring for an extended period of time. · Attended in July for a leak in the same bathroom. · Condition of the dwelling is poor. · A leak occurring behind the shower wall has flooded the cellar. · Shower has failed a flood test and there is an unsealed shower spindle. · Building is over 150 years old and there are external wall vents that can allow water to enter beneath the property near the footpath. · Water entering the ceiling cavity is causing mould to form. · Resultant water damage due to cellar being refilled with water. · Tenant stated a hissing noise was heard behind the wall and had a plumber inspect which led to the discovery of the leak into the cellar. · JL capped off the shower water supply to prevent further leaks. · Previous leak was behind the bath in the same bathroom. · Recommends cash settlement of any repair work as unable to warrant due to defective areas which may recur over time. · Includes photos of mould on the bathroom ceiling only, some wall cracks showing, and cellar filled with water, also notes cellar wall wet on bathroom side and flooring underneath bathroom is also damp. | Insurer’s engineer (CR) Assessment report 8 January 2024 | · Attended property on 21 December 2023. · Following instructions to determine the causation of the wall cracking damage and whether recent leaks have contributed to them. · Notes a prior leak in June 2023 occurred and was repaired. Second leak occurred in September 2023. · Building is approximately 150 years old. · Property in average condition taking its age, current damage notwithstanding. · 110mm of rainfall noted in June 2023 which is within the top 5th percentile for that month of the year. · Reviewed water bills from May, August, and November 2023 and found them to be high compared to other periods. · Previous leak detection invoice confirmed repair of a leak behind the bath in June 2023. A foot deep of water in the cellar following the leak. Replaced leaking pipe with new pipe. · Previous JL report from 7 July 2023 reviewed which said water in cellar due to a leak occurring over a space of weeks. Only detected when the occupants could hear the leak some time after it began. Two feet of water in the cellar at time of inspection. · No other way to locate and repair the leak than to remove the bathtub. · Waterproof membrane of the bathtub compromised by the repair work. Extent of cellar damage unknown until water pumped out. · Reviewed JL report from October 2023, nothing different to the notes above. · Reviewed the BL report from September 2023, nothing different to the notes above. · Reviewed an assessment of works prepared by MN dated 3 January 2023 (no other copy provided to AFCA) which proposed bridging supports or underpinning the granite foundations so the bathroom floor and be removed to properly scope the repair work. · Cracked damage is typically due to long term differential movement affecting the building footings. · Complainant did not notice any damage prior to July 2023. · Photos indicate damage was notice progressively between June 2023 and December 2023. · Complainant could not confirm if some cracking damage was new or pre-existing. · There are signs of previous repair attempts at each damage location which confirms damage is differential footing movement occurring over a long period of time. · Unbroken paint over defects in the study shows damage present there since the last time the walls were painted. · Wall moisture readings showing relatively normal at the halfway point up the wall in the claimed area of water damage. But lower down the readings are higher indicating rising damp. · No evidence of a damp proof course showing building is vulnerable to rising damp. CR says a brick degrading near the base of the wall supports this theory. · Cellar drained at the time of the inspection, but remains damp. · Partial collapse of the cellar wall contributed to by the leak from the bathroom. · Collapsed soil has not reached the masonry foundations and are not undermined by the collapse. Wall appears to be constructed on loose soil and rubble. Bush log added at some point to help retain the soil. · Timber bearer construction is vulnerable to deflection, but no damage appears related to the defect. · Floor level survey completed with a 30mm variance between the entry way and bedroom 3. Floor levels align with differential footing movement. · Steepest rate of floor level deviation is in bedroom 3 which can be attributed to heave towards the bathroom or subsidence toward the western wall. No movement damage observed in this room. · Trees located proximate to the building which can cause abnormal soil moisture conditions and create differential footing movement. · Building does not meet current building codes in a variety of ways. · Describes the mechanism of differential footing movement. · Footing system is considered low strength and stiffness compared to modern footing systems. · CR does not believe the high rainfall noted in local area around the time of the first leak is the cause of water ponding in cellar. Periods of recent heavy rainfall beforehand have not had the same affect on the property. · Water seeping through the cellar wall is due to the bathroom leaks. This is considered the primary contributing factor. · Water seeping would not have resulted in cellar wall partial collapse if it were properly constructed. · Damage to the walls is the result of footing heave, not subsidence. · CR does not agree with the underpinning proposed by MN as it may create other stiffness issues and cause more damage. · CR concludes the damage is due to long term differential movement of the footings. Footings are vulnerable as they are inadequate and being affected by the reactive soils, site drainage, nearby trees, and recent leaks. · Previous repairs support the damage is long term in nature. | Complainant’s builder (MN) Rebuttal email 12 April 2024 | · Highlights there was resultant damage to the walls adjacent to where the leaking pipes ran. · Complainant has contacted BB immediately to arrange make safe work urgently in the circumstances. · A slight leak was occurring from the area close to the shower breach assembly. · Complainant was advised she should not have proceeded with bathtub removal without insurer’s consent and assessment occurring first. · MN believes complainant took appropriate action in the circumstances. · The repairs would have been attended to sooner if the insurer had not slowed the process down. · The cellar had to be pumped clear of water more than once. · The reports from Youi paint a picture of a home which has been “let go” which does not align with his assessment of the home and his involvement in its renovation in the past. · Carrying out the recommended remedial works to modern day standards would likely encounter problems due to heritage listing requirements. · Insurer’s quote for the repair of the cellar wall would not cover even 5% of the actual cost of repairing the damage.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.