After a fire destroyed his mushroom shed, the complainant disputed the insurer's refusal to replace the slab and its cash settlement. AFCA upheld the slab exclusion but required an updated CM quote, a 15% uplift and reimbursement of up to $5,000 legal fees.

The slab needed replacement due to excluded construction defects, but a cash settlement must reflect current pricing and a contingency uplift, and legal costs were warranted given the complexity and the lawyer's role.

Issues

Subjects and remedies

home or building damagesmall businesspay claimpay compensation

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-129620 | Financial firm | Allianz Australia Insurance Limited Case number: 12-24-129620 28 August 2025 1 Determination overview 1.1 Complaint The complainant holds home building and contents insurance with the financial firm (insurer). He lodged a claim after his mushroom growing shed was damaged by a fire in October 2023. The insurer accepted the claim. Based on a scope of work (SOW) from each of builder AN and freezer panel supplier CM, it ultimately offered the complainant $78,572.06 in total as a cash settlement. However, it denied that the fire or its debris removal damaged the shed’s concrete slab (slab). The insurer says the slab requires replacement due to excluded causes. The complainant says the insurer’s cash settlement offer is inadequate, and that it should cover the slab’s replacement cost. This is because the complainant says the slab was compromised by the removal of fire related debris. The complainant seeks over $180,000 for the cost of repairs, plus legal costs, and interest. 1.2 Issues and key findings Is the insurer entitled to refuse to replace the slab? Yes. It is more likely than not the slab requires replacement because of construction defects, which are excluded from cover, rather than the fire or the insurer’s works. Is the insurer’s cash settlement offer reasonable? No. The SOWs from AN and CM reasonably reflect the extent of claim related repairs, but the insurer is yet to pay CM’s quoted amount and that quote is now over two years old. The insurer is to obtain an updated quote from CM then pay that amount as well as a 15% contingency uplift on the total cash settlement (except for the building code compliance costs). Is the insurer required to reimburse legal fees? Yes. The involvement of lawyer D assisted the complainant to establish an entitlement to a larger cash settlement than the insurer initially offered. The insurer is to reimburse the complainant for legal fees he paid to D to represent him, subject to a $5,000 maximum cap. Why is the outcome fair? It would not be fair to require the insurer to cover the damaged slab when the damage to it is from excluded causes. However, it is fair that the insurer pays a higher cash settlement to reflect current prices and to allow for contingencies, and that it reimburses some legal fees. 1.3 Determination This determination is partially in favour of the complainant. If the complainant accepts this determination, the insurer must: · cash settle the claim in accordance with section 2.2 below · within 14 days, reimburse the complainant for up to $5,000 in legal fees he has paid to D. 2 Reasons for determination The complainant is represented by lawyer D. For brevity’s sake the complainant and D are referred to below as ‘the complainant’ unless context requires otherwise. 2.1 Is the insurer entitled to refuse to replace the slab? Yes. It is more likely than not the slab requires replacement because of construction defects, which are excluded from cover, rather than the fire or the insurer’s works. ​​Complainant must show a claimable loss under the policy terms ​​​​The complainant is required to show, on the balance of probabilities (that it is more likely than not), that he suffered a loss claimable under the policy. This means he must show the loss was caused by a risk for which he is insured. Once the complainant proves the existence of a claimable loss, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proving on the balance of probabilities the application of the exclusion or condition. ​​​​Subject to the terms and conditions set out in the product disclosure statement (PDS), the policy covers the complainant for loss or damage to his home or contents caused by a listed insured event. Those events include ‘Fire’. ​​​On 28 October 2022, the complainant notified the insurer that in the early hours of that day his mushroom growing shed was significantly damaged by fire. The complainant accepts that the fire did not damage the slab. However, he says the fire exposed asbestos elements of the shed which had to be removed. This in turn undermined the slab’s ground support. The insurer accepted the claim and has paid and offered to pay amounts to cash settle the cost of repairs. However, it says the reason the slab requires replacement is excluded construction defects, not the fire or the removal of debris. Complainant says insurer should cover the slab’s replacement The complainant says as the shed was damaged by a fire, which is an insured event, the policy has been triggered, and the insurer is liable for the necessary rebuilding costs. He notes the insurer’s demolition company GD attended his property between 15 and 17 November 2022 to clean up asbestos debris left over from the fire. He says the work included removal of a boundary retaining wall which held soil on which the slab sat upon, as well as removal of contaminated soil which resulted in the end of the slab being exposed. The complainant relies on a report by engineer SA dated 2 June 2023. SA said that: · when it undertook its inspection on 25 May 2023, the shed’s structure had been removed with only the slab remaining · the slab’s western side had been poured against a steel sheet boundary fence, a large section of which had been removed to allow demolition of the shed · where the fence had been removed it was evident that the slab’s depth thickness varied between 80 and 110mm · there were no edge beams visible, and the slab appeared to be supported on rubble · the slab did not appear to be founded adequately, and the absence of edge beams indicated a lack of structural integrity · the slab was not suitable to be reused for construction of a new shed and should be demolished and replaced with new footings to suit the new construction. The complainant submits that the removal of the asbestos debris the fire exposed resulted in the slab’s ground support being removed, rendering the slab unviable. Further, that the slab must be demolished and rebuilt to ensure the new shed meets building code requirements. He refers to the ‘building code compliance costs’ additional benefit on page 28 of the PDS: If you need to rebuild your home buildings after loss or damage, we’ll help pay the costs of complying with any statutory requirements. This is an extra amount, paid in addition to your buildings sum insured. No excess applies to this benefit. Insurer refused to replace the slab In April 2023, the insurer appointed building consultant AA to prepare a report in relation to the complainant’s concerns about the slab. The complainant initially agreed to AA attending his property but subsequently withdrew his consent and provided SA’s report instead. The insurer submits that: The report provided by [S] does not advise of any damage to the concrete slab caused by the fire. Rather the report indicates the slab requires replacement as it is not suited to the proposed growing shed due to the inadequacy of its founding and lack of structural integrity. In addition, the insurer says: · to the extent GD’s demolition and debris removal work may have damaged the slab, that would be limited to some scratching to its top surface · SA’s report confirms a section of the adjacent fence was removed, not the slab itself · the fence removal had not resulted in the slab requiring replacement, but had revealed the extensive pre-existing construction issues with the slab · the construction issues rendered the slab non-compliant and requiring replacement. The insurer says replacement of the slab is not covered because the PDS states on page 55 that there is no cover for loss or damage as a result of, caused by or arising from ‘inherent defects including faulty design or materials, structural defects or poor workmanship’. The insurer also notes that the coverage under the ‘building code compliance costs’ additional benefit is limited to $5,000. As GD may have scratched the top surface of the slab, the insurer has offered to pay that amount to the complainant. Insurer is entitled to refuse to replace slab Because the complainant did not consent to AA inspecting his property, the only expert report submitted to AFCA that comments on the damage to the slab is SA’s report. That report does not say the fire or the insurer’s works damaged the slab or mean it must be replaced. Rather, SA says the removal of the fence sections revealed major pre-existing construction issues which render the slab non-compliant and necessitate its replacement. I am therefore satisfied it is more likely than not the slab requires replacement because of construction defects, which are excluded, rather than the fire or the insurer’s works. Despite this, the insurer has acknowledged that its works may have caused scratching to the slab’s surface and has offered to pay the complainant the full $5,000 ‘building code compliance costs’ additional benefit. I am satisfied that is a reasonable offer and represents the limit of the insurer’s liability in relation to the slab. 2.2 Is the insurer’s cash settlement offer reasonable? No. The SOWs from AN and CM reasonably reflect the extent of claim related repairs, but the insurer is yet to pay CM’s quoted amount and that quote is now over two years old. The insurer is to obtain an updated quote from CM then pay that amount as well as a 15% contingency uplift on the total cash settlement (except for the building code compliance costs). ​Parties agree a cash settlement is reasonable The parties agree that it is reasonable for the claim to be cash settled. ​A cash settlement must be based on a reasonable quote for claim related repairs, actionable by a retail customer. An uplift is then typically applied to the quoted amount to allow for contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs. Insurer has made cash settlement offers The insurer appointed builder AN to provide a SOW and quote for claim related repairs. On 4 January 2023, AN quoted $29,829.36 but said that due to pre-existing issues with design and construction, it would not be able to rebuild the shed as it had been before the fire. On 24 February 2023, the insurer offered the complainant $29,829.36 as a cash settlement. The complainant raised questions about freezer panel partitions he had prior to the fire installed in the shed to facilitate its use for mushroom growing. The insurer concluded that the complainant had not obtained the required council approval when he converted what was a carport into an enclosed shed used for commercial mushroom farming. Therefore, the panels were part of an illegal build. On 17 October 2023, AN provided an updated SOW/quote totalling $31,859.85. On 12 December 2023, the complainant provided the insurer with a budget estimate prepared in early November 2023 by builder TP totalling $160,743.25, and a SOW/quote dated 7 March 2023 by panel supplier CM totalling $35,816. The insurer said CM’s quote was insufficiently itemised and maintained that the panels were part of an illegal build. However, it asked AN to review the reasonableness of TP’s budget. That resulted in AN providing a revised SOW/quote dated 6 February 2024 totalling $35,986.10. AN confirmed the quote was ‘based on a ‘like for like’ repair, using similar materials to match existing as near as possible’. On 9 February 2024, the insurer offered to pay the complainant AN’s revised quoted amount of $35,986.10 plus $1,769.96 for an additional 11 months of temporary fencing. On 23 August 2024, the insurer paid the complainant $37,756.06 ($35,986.10 plus $1,769.10). The insurer subsequently acknowledged the complainant’s position that when he bought the property, the carport was already an enclosed structure, and that he was not commercially farming mushrooms. In February 2025, the insurer indicated it was willing to add CM’s quoted amount to its settlement offer. Accordingly, its final cash settlement offer (partially paid) was: | AT final quote for shed reinstatement (paid) | $35,986.10 | CM quote for panel supply and installation | $35,816.00 | Temporary fencing (paid) | $1,769.96 | Building code compliance costs benefit | $5,000.00 | Total | $78,572.06 The insurer maintains that TP’s estimate should not be accepted because it: · is not a registered builder’s letterhead · is described as a ‘preliminary budget’ · allows for removal of debris that has already been completed · allows for removal and replacement of the slab · allows for considerable upgrades · includes items that are in CM’s quote · is excessive for the works quoted. Complainant says insurer’s final offer is inadequate ​The complainant says the insurer’s cash settlement offer is manifestly inadequate. He submits that AT’s SOW is not sufficient to encompass the claim related repairs, and its quote is underpriced. The complainant submits that: The…policy covers the cost of the rebuild, including removal of debris and associated professional costs. The policy does not exclude “betterment” or “improvement’. All [the complainant] seeks is a like for like replacement of the Outbuilding that was destroyed by the fire. The [TP] and [CM] quotes accurately reflect that cost, whereas the [AN] quote relied on by [insurer] does not. The complainant seeks the combined quoted amounts of TP and CM, less the insurer’s payments to date, meaning a further cash settlement of $158,803.19. Insurer must pay a higher cash settlement I am satisfied that AN’s SOW reasonably reflects the extent of the claim related repairs and is to be preferred over TP’s preliminary budget. This is because: · AN’s SOW has been prepared on a ‘like for like’ basis, includes necessary preliminaries such as home warranty insurance, and provides detailed itemisation and breakdowns · TP’s preliminary budget allows for completed works, for items covered by CM’s quote, and for removal and replacement of the slab which the insurer is not required to cover. As the insurer paid the complainant AN’s quoted amount within six months of the quote’s preparation, I am satisfied the quoted amount more likely than not reflected current pricing at the time it was paid. No interest is payable on that amount. There is no dispute between the parties that CM’s SOW reasonably reflects the extent of the claim related repairs it outlines. However, the quote was prepared more than two years ago so will not reflect current pricing. It is therefore reasonable to require the insurer to obtain an updated quote from CM reflective of current retail prices. The complainant is to provide the insurer with reasonable assistance in obtaining that quote if the insurer requests it. Within 14 days of receiving CM’s updated quote, the insurer is to provide a copy to the complainant and pay him the quoted amount. As the quote will represent current pricing, there is no need to require interest to be paid on it. In its cash settlement calculations, the insurer has not allowed an uplift for contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs. It should have done so. I am satisfied a 15% uplift is reasonable. The uplift is to be applied to all aspects of the cash settlement except the building code compliance costs benefit as the insurer is paying the sum insured for that benefit. The uplift is to be paid as follows: · $5,663.41 within 14 days of the complainant accepting this determination (15% of combined total of $37,756.06 the insurer paid on 23 August 2024) · 15% of CM’s updated quoted amount within 14 days of receiving the updated quote. I note that the excess has already been paid. 2.3 Is the insurer required to reimburse legal fees? Yes. The involvement of lawyer D assisted the complainant to establish an entitlement to a larger cash settlement than the insurer initially offered. The insurer is to reimburse the complainant for legal fees he paid to D to represent him, subject to a $5,000 maximum cap. ​AFCA may require insurer to contribute to a complainant’s professional costs ​​The AFCA Rules enable AFCA to require an insurer to contribute to the professional costs incurred by the complainant. These costs are, however, usually capped at a total of $5,000, unless special circumstances apply. ​​When considering whether to require an insurer to make a costs contribution, AFCA considers matters such as the complexity of the complaint and whether the complainant needed to incur costs to understand or establish their claim. Insurer is required to reimburse legal fees I am satisfied that this complaint has involved complex issues. Further, D’s involvement assisted the complainant to establish an entitlement to a larger cash settlement than the insurer initially offered. Following D’s involvement, the insurer withdrew its assertion the freezer panels should not be covered and agreed to pay CM’s quoted amount. Therefore, upon proof of payment, the insurer is to reimburse the complainant for legal fees he has paid D to represent him, subject to a maximum cap of $5,000. 2.4 Why is the outcome fair? It would not be fair to require the insurer to cover the damaged slab when the damage to it is from excluded causes. However, it is fair that the insurer pays a higher cash settlement to reflect current prices and to allow for contingencies, and that it reimburses some legal fees. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. I have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, I have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.