Home / IAG / Determination 12-24-127644

Determination 12-24-127644

Adequacy of scope of works and cash settlement for accepted storm damage claim; additional non-financial loss

FirmIAG
Decided2025-04-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$10,156
Non-financial loss$1,000
Amount claimed$39,270
SourceAFCA PDF

Summary

The complainant disputed the insurer's scope of works and $6,502 cash settlement for storm damage to his holiday home and sought $39,270 based on his builder's quote. AFCA found the bedroom three carpet was omitted, ordered payment of $10,156 plus $1,000 non-financial loss and interest, but rejected the full builder's quote.

The carpet damage was on balance storm-related and omitted, but the builder's quote was unsubstantiated and the insurer was prejudiced by unapproved repairs (s54 Insurance Contracts Act), so liability was limited to the insurer's costed scope plus contingency.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-127644 | Financial firm | Insurance Manufacturers of Australia Pty Ltd Case number: 12-24-127644 4 April 2025 Determination overview Complaint The complainant holds a household insurance policy covering listed insured events (policy) with the financial firm (insurer). He lodged a claim with the insurer on 7 February 2024 for storm damage to his holiday home that occurred on 5 February 2024. The insurer accepts the claim and was prepared to authorise repairs to its panel builder (US). It offered to cash settle the complainant in the amount of $6,502 based on US’s SOW including a 20% uplift or proceed with repairs by US. It has also offered $1,000 compensation for his dissatisfaction with his claims experience. The complainant rejects this offer. He says the scope of works (SOW) is inadequate and appointed a local builder (AB) to rectify the damage. This is because of the insurer’s failure to adequately amend the SOW. The insurer says it has been prejudiced by the complainant commencing repairs without its authority. Issues and key findings Is the insurer’s SOW and cash settlement offer adequate? No. This is because the exchanged information shows the insurer’s SOW, on balance, omits storm related damage to the upstairs floor in the third bedroom. Is the complainant entitled to additional NFL? No. This is because, the exchanged information shows the insurer did not mishandle the claim to the extent that would warrant additional non-financial loss (NFL). Why is the outcome fair The outcome is fair because the exchanged information shows, on balance, the insurer’s SOW and cash settlement offer omit the damage to the carpet in bedroom three. It is fair to require the insurer to reimburse the cost incurred by the complainant to replace the carpet. The insurer’s offer of $1,000 NFL is adequate because the exchanged information shows the insurer did not mishandle the claim to the extent that would warrant an award of additional NFL. It would be unfair to require the insurer to pay more in this instance. Determination This determination is partially in favour of the complainant. Within 14 days of receiving notice the complainant accepts this determination the insurer is required to pay the complainant $10,156 plus $1,000 NFL. The insurer is also required to pay interest in accordance with section 57 of Insurance Contracts Act 1984 (the Act) from 11 June 2024 to the date the claim is settled. Reasons for determination Is the insurer’s SOW and cash settlement offer adequate? No. This is because the exchanged information shows the insurer’s SOW, on balance, omits storm related damage to the upstairs floor in the third bedroom. Policy covers insured events The complainant holds a household insurance policy with the insurer for the relevant period of 30 August 2023 to 30 August 2024. The policy is an ‘insured events’ policy. This means that not all loss and damage is automatically covered. Rather, only loss or damage caused by one or more of the insured events occurring during the period of insurance and not subject to the exclusions, is covered. One of the insured events listed under the policy is ‘storm’. On 7 February 2024, the complainant lodged a claim for storm damage to the home that occurred on 5 February 2024. Accordingly, the onus is on the complainant to establish the damage to the home is the result of storm event during the period of insurance. The policy consists of the Certificate of Insurance (COI) and Product Disclosure Statement. The policy must be read as a whole to ascertain the level of cover provided. It is not in dispute the insurer provided the policy documents to the complainant. The insurer is therefore entitled to rely on those terms when assessing the claim. The parties agree the complainant has established a valid claim. The insurer accepts the claim. The parties dispute the SOW and adequacy of the cash settlement offer. Policy cover is subject to terms, conditions, and exclusions Page 75 of the PDS says: How we settle your buildings claim We will choose to settle your claim for loss or damage to your home or 'other benefits' in one of the following ways. Our choice will have regard to the circumstances of your claim and consider any preference you may have. Arrange for repairers, builders or suppliers to repair or rebuild your home. If you agree, we can arrange for our preferred repairers, suppliers or builders to repair or rebuild your home. Pay you the reasonable cost to repair or rebuild your home. We can choose to: pay you pay your nominated repairer, supplier or builder, or provide you with store credits from one of our nominated suppliers. Page 69 of the PDS says: ​You must: co-operate fully with us, even if we have already paid your claim which includes: providing us with all the information, documents and help we need to deal with your claim. If we request information or documents that are relevant to your claim, we will provide an explanation as to why it is needed. … allow us to obtain quotations from any repairer or supplier. Parties disagree on SOW On claim lodgement the insurer appointed US to inspect the property, determine the cause of damage and prepare a costed SOW. US submitted its SOW and quote in the amount of $5,418 on 19 February 2024. Following submission of a roof report from SD the insurer accepted the claim on 23 March 2024. It was prepared to have US perform the works. The complainant disputed US’s SOW on 11 June 2024. He says it does not include the storm related damage to the upstairs floor in bedroom three. On 26 June 2024 the complainant advised the insurer he is obtaining his own quote. The exchanged insurer’s claim notes show the insurer contacted the complainant four times to follow up on his quote before the complainant lodged a complaint with AFCA on 9 August 2024. He submitted his builders’ quote in the amount of $39,270 on 30 October 2024. Insurer says SOW is adequate Following its internal review on 23 August 2024, the insurer appointed an engineer (CF) to inspect the home, provide an assessment report and SOW for all storm related damage. In its report dated 13 September 2024 CF identified the following damage required rectification: Remove and replace the plasterboard ceiling linings of the Ground Floor Kitchen. Prepare and paint the plasterboard ceiling and wall linings of the Ground Floor Kitchen Remove and replace the melamine shelving to the Built-in-Robe of Bedroom 3. Prepare and paint the plasterboard ceiling and wall linings of the Bedroom The insurer says:  US’s SOW includes all storm related damage because it is based on CF’s findings  US can complete the work required to rectify the damage caused by the event in accordance with the PDS.  it can offer to cash settle the complainant $5,418 plus a 20% uplift ($6,502 in total) and $1,000 NFL in acknowledgement of the delay and service issues. Complainant says SOW is incomplete The insurer’s claim notes record:  on 16 July 2024 the complainant told the insurer US had queried the floor swelling outside the walk-in robe when on site. This was not included in the SOW.  the insurer asked US to clarify the omission of the floor in the SOW the same day. US was authorised to reassess if necessary.  as the complainant was obtaining his own quote the insurer revoked its instructions to US on 2 August 2024  US submitted a variation dated 15 August 2024 in the amount of $1,716.50. The variation includes rectification of damage to bedroom three robe walls and the upstairs linen cupboard only; no mention was made of bedroom 3 carpet. The complainant says:  both US and CF agreed the bedroom carpet had been damaged when on site. However, the SOW omits the carpet.  he authorised repairs to AB without the approval of the insurer. This is because he had: > lost faith in the insurer due to their inability to include all storm related damage in the SOW. > noticed mould was beginning to form in the kitchen wall plaster.  he wants the insurer to: > pay full compensation for NFL up to AFCA’s limit of $6,300 > cash settle him based on his builder’s quote in the amount of $39,270 > pay interest on this amount > waive the excess on his claim > pay a 20% uplift on his builder’s quote and interest on the cash settlement amount. On balance bedroom three carpet is storm damaged I have carefully considered all exchanged information. I am satisfied, on balance, bedroom three carpet was storm damaged on 5 February 2024. This is because:  it is not in dispute rainwater entered the home through the metal roof damaging bedroom three and the kitchen below  water follows gravity; it had to pass through the upper floor to reach the floor below  the insurer accepts water has damaged the internal wall and ceiling linings, the walk-in robe in bedroom three and the storage cabinet at the top of the stairwell  if water has infiltrated enough to soak the plasterboard ceiling and wall linings below, then it is more likely than not, it may have pooled or tracked across the floor above damaging the carpet  the insurer initially instructed US to investigate the complainants concerns about the carpet which were revoked as the complainant was obtaining his own quote. The insurer is required to reimburse the complainant for the cost to replace the carpet in bedroom three accordance with the amount quoted by AB ($1,540 inc. GST) AB’s quote is, on balance, unsubstantiated AB says all damage included the SOW dated 23 September 2024 is a result of water welling in the roof between the kitchen and adjoining room for an extended period. The insurer rejects AB’s findings and SOW. It says:  AB’s quote: > fails to provide a full report on causation; there is no evidence to support its findings > does not provide a breakdown of measurements and quantities for each item in the SOW > includes several items not identified as damaged by US or CF with no evidence to prove they were damaged in the storm event. > is excessive due to the significant disparity with US’s costings  no extensive damage to the wood beams can be seen in the images provided  there is no major point of water entry on the roof; the damage was caused by capillary action of ponded water on the metal roof surface resulting in water tracking over the side lap sheets into the roof void  29.4mm of water fell on the recorded date of loss; this is insufficient to result in the extensive structural repairs being claimed. I am not persuaded all the work included in AB’s SOW is directly a result of the claimed storm event. This is because CF inspected the home on 30 August 2024 and found:  In relation to the kitchen and ground floor: > damage caused by mould growth on the plasterboard ceiling linings above the kitchen benchtop consistent with water ingress from above > elevated moisture in the plasterboard ceiling linings of the kitchen consistent with residual moisture ingress from above > no evidence of water damage to the remainder of the rooms on the ground floor.  In relation to bedroom three and upstairs area: > staining to the surface of the plasterboard wall linings of the built-in-robe consistent with water ingress from above > the plasterboard ceiling and wall linings of the built-in-robe are currently in a dry state > residual swelling was observed along the face edges of several of the shelves of the built-in-robe consistent with water ingress > no evidence of water damage in the remainder of the rooms on the first floor. I find CF’s report persuasive. This is because it was prepared by the suitably qualified building consultant who:  inspected each area of reported damage and identified all damage related to the storm event. The damage identified is consistent with US’s initial findings  observed no storm related damage to the remainder of the property  performed moisture readings in the affected areas validating the presence of residual moisture from water ingress originating from the roof  included annotated images in its report to support its findings  provided a detailed SOW including quantities and measurements. Insurer prejudiced by unapproved repairs The insurer says:  the complainant has proceeded with the repairs without authority  it was prepared to authorise repairs to US who can perform them for the quoted amount  the complainant is claiming for damages that are unsubstantiated at rates significantly above the prevailing market rate  under section 54(1) of the Act, it is entitled to reduce its liability to what it would have cost it to perform the rectification works, had the complainant not proceeded with the repairs  a 20% uplift on the complainant's quote is not required. This is because AB’s quote is extensive; there is no possibility of significant unforeseen damages which require repair. Given the deficiencies in AB’s SOW and CF’s findings I am satisfied, on balance, AB’s quote is unsubstantiated. I am also satisfied the insurer has been prejudiced by the complainant proceeding with repairs without prior approval. This is because the insurer was prepared to perform the works based on CF’s SOW. US confirmed they could do these works for the amount quoted. Therefore, the insurer is not required to reimburse the complainant for the full amount of AB’’s quote. The complainant says US would have submitted variations for damage outside the SOW discovered once rectification work commenced. I agree. However, I also accept this is addressed by the 20% contingency contained in the insurer’s offer. That contingency is to address the risk of further works required. There is no information to suggest this amount was unreasonable. Within 14 days of receiving notice the complainant accepts this determination the insurer is required to pay the complainant $ 10,156 calculated as follows. The insurer is also required to pay interest in accordance with section 57 of the Act from 11 June 2024 (the date the complainant initially told the insurer the SOW was inadequate) to the date the claim is settled Is the complainant entitled to additional NFL? No. This is because, the exchanged information shows the insurer did not mishandle the claim to the extent that would warrant additional NFL. Complainant claims entitlement to further NFL The complainant says he is entitled to NFL up to the full limit of AFCA’s jurisdiction due to the stress and inconvenience caused by the insurer’s mishandling of the claim. AFCA approach to non-financial loss ​Under the AFCA Rules, AFCA can award up to $6,300 compensation for non-financial loss. We will only award this type of compensation if a complainant suffers an unusual degree of stress, inconvenience, or delay because the insurer mishandled the claim. We recognise making a claim can be stressful and time-consuming, even if the insurer handles the claim correctly. We will not award compensation for the ordinary degree of inconvenience that comes with making a claim. We may reduce the amount of compensation we award if the loss was partially caused by the complainant’s actions or by factors outside the insurer’s control. Insurers offer of $1,000 NFL is reasonable The insurer denies there have been excess delays or stress caused by the overall claim management. However, it offered the complainant $1,000 NFL for any potential stress or inconvenience he may have experienced during the claim. The complaint rejects this offer. I am satisfied the insurer’s offer is reasonable. This is because the exchanged insurer’s claim notes show:  the complainant told the insurer he was arranging his own report on 26 June 2024  the insurer followed up the complainant for his quote/report on 12 July 2024, 16 July 2024, 22 July 2024, 2 August 2024  the AFCA complaint was lodged 9 August 2024  following its internal review the insurer appointed CF to inspect the home and report on the storm related damage on 23 August 2024  CF submitted its report the insurer on 13 September 2024  the insurer obtained a SOW from US and offered to cash settle the complainant in the amount of $6,502 (including a 20% uplift) or proceed with repairs by US  the complainant submitted AB’s quote in the amount of $39,270 on 30 October 2024. The complainant does not dispute the insurer’s timeline. He has not provided his own timeline or any evidence to show how the insurer’s claim handling has caused him sufficient stress and inconvenience to warrant additional NFL. Given the above I am satisfied, on balance, the insurer’s offer of $1,000 is fair in all the circumstances. The insurer is not required to compensate him more. Why is the outcome fair? The outcome is fair because the exchanged information shows, on balance, the insurer’s SOW and cash settlement offer omit the damage to the carpet in bedroom three. It is fair to require the insurer to reimburse the cost incurred by the complainant to replace the carpet. The insurer’s offer of $1,000 NFL is adequate because the exchanged information shows the insurer did not mishandle the claim to the extent that would warrant an award of additional NFL. It would be unfair to require the insurer to pay more in this instance. Supporting information The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.