Home / QBE / Determination 12-24-127065
Determination 12-24-127065
Delay and poor handling of fire repairs, with additional business interruption sought
Summary
A B&B owner's property was damaged by fire and repairs were delayed, including an insurer-ordered pause. AFCA found the insurer's handling caused unjustifiable delay and ordered a further six months of business interruption ($65,000) plus $2,000 for non-financial loss.
Some delays were unavoidable given location and heritage status, but the insurer's unexplained repair pause and poor oversight caused avoidable delays that fairly warrant six more months of BI and compensation.
Issues
- Poor claim handling primary · upheld“unjustifiable delays caused by the insurer's poor claim handling, including its decision to pause repairs without adequate notice or active handling”
- Claim amount dispute secondary · upheld“offer of three months BI ($32,500) not fair; fair to pay six months, $65,000”
- Delay secondary · upheld“insurer paused repairs from 28 June 2024 to 2 September 2024; cascading effect on repair schedule”
- Poor communication secondary · upheld“insurer failed to notify the complainant in a timely manner of the reasons for ceasing repairs in June 2024”
- Repairs or contractors secondary · unclear“disagreement over scope of repairs; no persuasive evidence on discussions or agreements for proposed repairs”
Subjects and remedies
broker or intermediarybusiness interruptionhome or building damagesmall businesspay claimpay non financial loss
Related
Text of the determination
Determination
|
Case number
|
12-24-127065
|
Financial firm
|
QBE Insurance (Australia) Limited
Case number: 12-24-127065 30 October 2025
1 Determination overview
1.1 Complaint
The complainant operates a bed and breakfast business and lodged a claim on its business pack insurance policy after a fire caused substantial damage to the property in September 2022.
The insurer agreed to repairs the property. The complainant is dissatisfied with the insurer’s handling of the repairs. The complainant says the insurer’s conduct has contributed to delays and seeks additional business interruption payments.
The insurer acknowledges there were delays but says the complainant contributed to the delays by requesting changes to the agreed scope of repairs. Furthermore, the insurer states the continuing repair delays are outside of its control, although it is actively monitoring the progress.
The insurer offered to pay the complainant three months of business interruption. The complainant says that this amount is not sufficient and remains dissatisfied with insurer’s overall handling of the claim.
1.2 Issues and key findings
Is the insurer liable for further business interruption?
Yes. It is fair the insurer pays the complainant an additional six months of business interruption.
Is the insurer liable for compensation?
Yes. The insurer is required to pay the complainant $2,000 compensation.
Why is the outcome fair?
Some delays were unavoidable due to the property's location and heritage status, which reasonably limited the insurer’s control. However, there were unjustifiable delays caused by the insurer’s poor claim handling, including its decision to pause repairs without adequate notice or active handling. These actions had a cascading effect, significantly impacting the complainant’s ability to organise and operate its business in 2025 as originally planned.
1.3 Determination
The determination is in favour of the complainant.
Within 14 of receiving notice the complainant accepts this determination, the insurer is required to pay him:
· $65,000 for the business interruption losses
· $2,000 as a compensation for non-financial loss.
2 Reasons for determination
2.1 Is the insurer liable for further business interruptions?
Yes. It is fair the insurer pays the complainant an additional six months of business interruption.
Policy provides cover for business interruption losses
The complainant holds a business pack insurance policy with the insurer, which provides cover for certain losses outlined in the product disclosure statement (PDS). This includes cover for property damage and business interruption (BI) losses, subject to specified limitations and exclusions.
It is not disputed that the property was significantly damaged by fire in September 2022, resulting in the closure of the business. The insurer accepted liability for the damage and agreed to complete the demolition and subsequent reinstatement of the property as required.
The policy provides cover for BI cover for a maximum of one year, with a sum insured of $130,000. The insurer has paid the sum insured of $130,000 plus an additional six months of BI following AFCA determination (1004703) in the amount of $65,000. It is likely the repairs to the property will be completed by end of 2025.
Complainant says insurers’ delays caused him further business interruption
Amongst other things, the complainant states:
· the insurer paused the repairs without notifying it
· the insurer directed the builder and loss adjuster not to communicate with the complainant
· as a result, the builder (PA) cancelled all subcontractors and materials ordered
· the flow on effect of the repair pause has resulted in significant delays
· the initial estimated date of the repair completion was Christmas 2024. However, the expected finish date was July 2025
· the insurer failed to consult it about the proposed build and repairs resulting in misunderstanding of the scope of repairs.
The complainant asserts that, due to these issues, the insurer should extend its cover and pay additional BI compensation.
Majority of delays were due to the insurer pausing the repairs
There is no dispute that the insurer ceased the repairs on 28 June 2024 and recommenced the repairs on 2 September 2024. The insurer states that the pause was necessary due to a significant increase in the repair costs, which exceeded the property’s sum insured by approximately $1.5 million. The exchanged evidence confirms that repairs were halted during this period.
The contemporaneous claim notes show:
· on 25 March 2024, the insurer’s loss adjuster (BH) notified the insurer that the repair budget would substantially exceed the building sum insured
· on 12 April 2024, the insurer received the PA’s budget and forwarded to the engineers
· on 5 June 2024, the complainant emailed BH and PA following up on repair issues, BH responded on the same day
· on 1 July 2024, the insurer instructed BH to cease work for seven days while it was awaiting legal advice from its solicitor (HW)
· on 30 July 2024, the insurer provided an update to the complainant’s broker (GL)
· on 9 August 2024, the insurer discussed the recommencement of the repairs
· on 1 and 11 November 2021, GL emailed the insurer requesting updates
· on 7 November 2024, GL followed up the insurer on changes to a door design.
The insurer states that it was initially notified of the significant increase in the repair reserve on 6 March 2024.
The insurer states that it needed to undertake further discussions with BH, PA, the engineer (ME) and HW before determining how to proceed. However, there is no conclusive evidence explaining the reason for the unexpected rise in repair costs.
The insurer states that BH notified PA on 14 August 2024 to recommence the repairs, and? PA advised he will need two weeks to re-mobilise.
The insurer says the repairs were progressing well until they were paused in June 2024. It also acknowledges that there were other delays related to the repairs. The exchanged information shows that parties disagreed on the extent of the insurer’s liability regarding:
· restoring the heritage roofline
· restoring? the old exhaust fan duct and flue
· changing the flat door on the plan to a sliding door
· the hot water and hydraulics plans.
I accept delays were in part caused due to the disagreement between the parties regarding the extent of the insurer’s liability. In summary, the insurer states:
· the roof is aged, and the builder is not prepared to warrant its watertightness without significant work and approvals due to its heritage status
· some of the repairs the complainant is seeking to be undertaken fall outside the approved plans, designs and previous approvals
· the complainant reviewed and agreed to the building plans approved in 2023
· it is reviewing the complainants’ requests and working with the relevant tradespeople such as BH and the local plumber to accommodate its requests.
I acknowledge the complainant argument that he was not consulted regarding the designs. However, neither party provided any persuasive evidence to establish the discussions, assessments or agreements for the proposed repairs.
It is fair the insurer pays an additional six months of business interruption
I have carefully considered the exchanged evidence. The property’s location and its heritage status understandably contributed to unavoidable delays. The complainant does not dispute the difficulty in securing resources locally. On balance, I accept that the insurer cannot control external factors contributing to these delays. Generally, insurers rely on external service providers to facilitate repairs, and in these circumstances, I do not accept that the insurer is required to compensate the complainant for these unavoidable delays.
However, I accept that the insurer’s handling of the claim has caused unjustifiable delays. There is no dispute that the insurer paused repairs from 28 June 2024 to 2 September 2024, a period of approximately two months. The insurer offered three months of business interruption compensation totalling $32,500. I am not satisfied that this offer is fair in the circumstances.
The evidence does not conclusively establish the extent of repairs carried out between March and June 2024. During this time, the insurer was reviewing the budget for the remainder of the repairs. Contemporaneous evidence shows the insurer was aware of budget-related issues as early as March 2024 but did not communicate this to GL until August 2024.
I am not satisfied that the insurer’s decision to pause repairs is the sole contributor to the delays. Given the insurer’s difficulty in securing relevant repairers due to the property’s location, I accept that the eight-week pause had a cascading effect, requiring additional time for PA to reorganise the repair schedule.
There is no dispute that the insurer has managed the repairs from the outset, engaging several experts to assess its liability. There is no conclusive evidence to establish the basis of the sharp increase in the repair budget. In other words, I am unable to reach a definitive view on the extent to which the increase in the repairs reserve is linked to the insurer’s handling of the claim or the nature of the damage. That said, I accept that the insurer lost insight into the claim’s progress due to frequent changes in appointed experts and its layered communication model. All communication was routed through HW, and I accept that this structure contributed to avoidable delays.
While I acknowledge the complexity and high value of the claim, I consider that the insurer should have been more proactive and directly involved in the repair process, rather than relying solely on its agents.
The contemporaneous evidence shows GL has continuously sought updates regarding the recommencement of repairs, and the insurer was unable to provide meaningful responses to manage the complainant’s expectations. While this reflects poor customer service, it also indicates that the insurer was not actively managing the repair process.
On another note, I accept the complainant’s business is seasonal. In other words, there would be some periods where the business would not operate to generate income. Given the exchanged evidence indicates that the repairs were due to be completed by Christmas 2024 in the absence of any delays. I accept that the delays have materially affected the complainant’s ability to organise and operate its business in 2025. The extended disruption, compounded by poor communication and inconsistent oversight, has had a direct impact on the complainant’s planning and operational capacity.
The complainant’s policy includes a sum insured of $130,000 for Insurable Gross Profit, with an indemnity period of 12 months. Considering the above, I consider it fair that the insurer compensates the complainant for six months of business interruption. This equates to a total of $65,000.
2.2 Is the insurer liable for compensation?
Yes. The insurer is required to pay the complainant $2,000 compensation.
AFCA may award compensation for non-financial loss
AFCA may award compensation for non-financial loss in some circumstances. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some delays. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation.
The complainant is dissatisfied with the insurer’s handling of the claim, mainly the lack of communication and constant delays.
The insurer is required to pay the complainant $2,000
The contemporaneous claim notes show:
· the complainant initiated the majority of the contact with the insurer
· the insurer failed to provide fortnightly updates in some instances, despite previously committing to do so and advising the complainant of expected progress.
The exchanged evidence indicates that the relationship between the parties has significantly deteriorated. I acknowledge that several external parties were involved in the repairs due to the property's location and heritage nature. However, I accept that the insurer failed to notify the complainant in a timely manner of the reasons for ceasing repairs in June 2024 or communicate the basis of its decision in a transparent manner.
Although the insurer eventually explained the basis for the pause to GL, it did so only after the fact. I acknowledge that the insurer has since apologised to the complainant. Nonetheless, the delay in communication contributed to the breakdown in trust and further hindered the claim’s progress.
Given the circumstances, I consider it fair that the insurer pays the complainant $2,000 in non-financial compensation for the delays caused by its poor communication and handling of the claim.
2.3 Why is the outcome fair?
Some delays were unavoidable due to the property's location and heritage status, which reasonably limited the insurer’s control. However, there were unjustifiable delays caused by the insurer’s poor claim handling, including its decision to pause repairs without adequate notice or active handling. These actions had a cascading effect, significantly impacting the complainant’s ability to organise and operate his business in 2025 as originally planned.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
· the legal principles
· applicable industry codes or guidance
· good industry practice
· previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
· available documents
· the recollections of the parties
· all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.