Borrowers disputed enforcement costs and about $20,000 interest accrued during a mortgagee-in-possession sale, alleging inflated costs and delay. AFCA found in favour of the bank and ordered nothing.

The enforcement costs were necessary and supported, and delays resulted from mandatory meth remediation and pool and electrical compliance steps rather than bank inaction.

Issues

Subjects and remedies

financial hardshiphome or building damageno remedy

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-24-117680 | Financial firm | St George Bank Case number: 12-24-117680 27 February 2026 1 Determination overview 1.1 Complaint The complaint relates to the bank’s conduct during mortgage enforcement proceedings. The complainants are the borrowers of the home loan facility which went into default. The complaint has been commenced by one of the borrowers, Mrs R on behalf of, and with the consent of, the other borrower, Mr R. On 25 May 2022, the bank obtained a default judgment for possession of the property. It took physical possession on 16 March 2023, and the property was eventually sold on 17 April 2024, with settlement occurring on 23 May 2024. The complaint centres on the enforcement costs charged to the loan account and the interest accrued due to delays in selling the property. The complainants dispute the necessity and reasonableness of various enforcement-related expenses, including charges for property maintenance, cleaning, decontamination, locksmith services, storage, removalists, legal fees, and valuations. Mrs R alleges that many of these costs were inflated, duplicated, or related to services not actually performed. She questions the involvement of multiple third-party contractors, some based in the Eastern States, arguing that their engagement led to excessive and unjustified costs. In addition, the complainants assert that the bank unnecessarily delayed listing and selling the property, which resulted in interest continuing to accrue on the loan. She maintains that the property could have been sold much earlier and that her instructions to list it promptly were ignored. She estimates that approximately $20,000 in interest was accrued between March 2023 and May 2024 due to these delays and argues that this financial impact was avoidable. The case manager issued a recommendation which was in favour of the bank and a copy of it is attached to this determination. The complainants rejected the recommendation. 1.2 Issues and key findings Were the findings in the recommendation correct? The findings in the recommendation were correct and are adopted in this determination. We have considered all further submissions provided after the recommendation. Do the complainants’ further submissions change the outcome? The complainants’ further submissions do not change the outcome because they do not introduce new information or evidence that challenges the findings already supported by the contemporaneous records and compliance documentation. Why is the outcome fair? The mortgagee in possession process can be a bewildering process to many people and if the process is not adequately explained, it can seem like certain steps being taken are unnecessary or delaying the sale process but in fact are required by law. The enforcement and sales process in this case did take a significant period and it is important to acknowledge that some of the causes of the delay were not the fault of the complainants. However, the information shows the bank acted reasonably, incurred necessary and properly supported costs, met mandatory compliance requirements, and progressed the sale as expeditiously as possible. Any delay in the process was not due to the bank’s actions but rather the circumstances in the case and the need to take additional steps due to the status of the property. I acknowledge the challenging time the complainants would have faced during this process and I have a great deal of sympathy for Mrs R and her children when faced with an uncertain future and a lack of consistent housing. I also acknowledge that Mrs R has invested a significant amount of time in this matter and will be frustrated by the outcome. However, the outcome is fair because the bank acted reasonably in the circumstances and acted in good faith to ensure the property was sold for not less than its market value at the time of sale. 1.3 Determination The determination is in favour of the bank. The bank is not required to compensate the complainants or take any corrective action. 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The findings in the recommendation were correct and are adopted in this determination. We have considered all further submissions provided after the recommendation. The findings in the recommendation were correct I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have considered all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied the case manager’s recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the AFCA Rules and any relevant law. Having reviewed all the relevant information, the recommendation was fair having regard to the circumstances of the complaint and AFCA’s usual approach. I agree with the findings of the recommendation and adopt them into this decision. The complainants rejected the recommendation The complainants rejected the recommendation for the following reasons: · The bank failed to provide original invoices, contracts, or scope-of-works documents for meth remediation, pool compliance, and other property works, making independent verification impossible. · Multiple documents relied upon by the bank were undated, inconsistently dated, or improperly completed, undermining their credibility. · Instances of double charging and duplicate invoicing were identified, including overlapping charges for meth sampling by different contractors without explanation. · Approved costs were inconsistent with expert recommendations and valuation advice, and there was no evidence that quoted works were completed prior to sale. · Pool compliance was incorrectly cited as a reason for sale delays, despite council confirmation that compliance requirements did not apply. · The bank delayed settlement despite sufficient surplus funds, negatively impacting one of the complainant’s credit files and causing unnecessary charges. · Reported credit card balances did not match the complainant’s records, indicating discrepancies that were not properly investigated. · No compensation was provided despite acknowledged errors and surplus funds, while additional fees and interest were applied. · The bank failed to supply remediation documentation, including clearance certificates and detailed reports, despite relying on these to justify charges exceeding $17,000. · The bank did not adequately respond to key AFCA inquiries, leaving critical issues unresolved. · No evidence was provided that meth contamination or remediation was reported to relevant authorities, as required by standard practice. · Selling agent responses revealed discrepancies and no substantiated basis for initiating meth testing at the property. · No storage information, contracts, or photos were provided for five storage units, and discrepancies were noted in insurance contributions and invoicing for chattel transition. 2.2 Do the complainants’ further submissions change the outcome? The complainants’ further submissions do not change the outcome because they do not introduce new information or evidence that challenges the findings already supported by the contemporaneous records and compliance documentation. Enforcement costs were reasonable and necessary The complainants reiterate concerns about missing original invoices, undated documents, and alleged duplication of charges. While I acknowledge these concerns and the amount of time expended by Mrs R in setting out her concerns, AFCA’s role is not to audit or verify the physical completion of works. Our assessment focuses on whether the bank acted fairly and reasonably in incurring costs necessary to secure, remediate, and prepare the property for sale. The invoices provided by the bank are consistent with industry practice and supported by contemporaneous records. The bank obtained competitive quotes for major works, including meth remediation, and selected the lower quote. Clearance certificates confirm that remediation was completed in accordance with national guidelines. While some invoices lack granular detail, this does not establish that works were not performed or that costs were unreasonable. The information supports that the bank’s approach was fair. The records show no evidence of duplication and align with the scope of the work The complainants assert that certain charges were duplicated or inflated. I have reviewed these claims against the documentation. The costs for removal, storage, compliance works, and remediation reflect bundled services delivered under strict timelines and complex circumstances. There is no persuasive evidence of double charging. The amounts charged align with the scope of work and urgency involved. Even if some individual costs could have been lower, the bank later waived over $8,000 in residual debt, which outweighs any disputed amounts. The information shows that accredited testing and valid clearance were obtained The complainants stated that the selling agent did not adequately substantiate the basis for initiating meth testing at the property. The selling agent has obligations under the Real Estate and Business Agents and Sales Representatives Code of Conduct 2016 and agents are required to ascertain material facts about any property they list. If the selling agent suspects that the property is contaminated, then they are well within their rights to have the property tested as the consequences for failing to take action could be significant for the selling agent. This is what occurred in these circumstances and the test results would suggest that the agent’s actions were justified. The complainants say that clearance certificates were not provided and that the testing company lacked proper accreditation. However, the information does not support these claims. The bank provided a clearance certificate dated 14 June 2023, confirming that contamination levels were reduced to within accepted safe thresholds following remediation. The remediation itself was carried out in line with national guidelines for clandestine drug laboratory clean‑up, and the documentation demonstrates that appropriate steps were followed. The complainants also question the qualifications of the testing company, but the evidence shows the laboratory was NATA‑accredited under ISO/IEC 17025, the recognised standard for methamphetamine sampling and analysis in Australia. While the complainants raised minor inconsistencies in the supporting material, these do not undermine the validity of the testing or the clearance process. The accredited documentation supports that the contamination was properly assessed, remediated, and certified as safe. Pool rectification was required to lawfully market the property The complainants maintain that pool compliance was misused to delay the sale. The information shows compliance works were legally required under WA regulations. The property could not be marketed until these issues were resolved, along with electrical safety requirements. These were not discretionary enhancements but mandatory steps to ensure lawful sale. The timeline demonstrates the bank progressed these tasks promptly and listed the property as soon as compliance was achieved. The complainants’ submissions do not establish unnecessary delay or unjustified interest charges The complainants argue that the bank delayed settlement despite surplus funds. The chronology shows delays were caused by contamination remediation and compliance obligations, not by bank inaction. Once these were completed, the property was listed, offers were received within days, and settlement occurred promptly. The claim of unnecessary delay and associated interest charges is not substantiated. The complainants’ further submissions do not change the outcome The complainant’s further submissions do not introduce new information or arguments that change the outcome. The bank acted fairly and reasonably in recovering enforcement costs and progressing the sale. The delays were due to mandatory compliance steps, not inaction. The determination is therefore in favour of the bank, and no compensation or corrective action is required. 2.3 Why is the outcome fair? The mortgagee in possession process can be a bewildering process to many people and if the process is not adequately explained, it can seem like certain steps being taken are unnecessary or delaying the sale process but in fact are required by law. The enforcement and sales process in this case did take a significant period and it is important to acknowledge that some of the causes of the delay were not the fault of the complainant. However, the information shows the bank acted reasonably, incurred necessary and properly supported costs, met mandatory compliance requirements, and progressed the sale as expeditiously as possible. Any delay in the process was not due to the bank’s actions but rather the circumstances in the case and the need to additional steps due to the status of the property and the circumstances of the complainant and her family. I acknowledge the challenging time the complainants would have faced during this process and I have a great deal of sympathy for Mrs R and her children when faced with an uncertain future and a lack of consistent housing. I also acknowledge that Mrs R has invested a significant amount of time in this matter and will be frustrated by the outcome. However, the outcome is fair because the bank acted reasonably in the circumstances and acted in good faith to ensure the property was sold for not less than its market value at the time of sale. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted our determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Issues not considered The complainants raised several additional matters, including concerns about discrepancies involving a credit card account. These issues were not part of the original complaint and do not have a direct or material connection to the key matters under review, namely, the enforcement costs applied during the mortgagee‑in‑possession process and the timing of the property sale. As such, they do not affect the outcome of this determination. AFCA’s role in this complaint is to assess the issues originally identified and those directly related to them. New or unrelated claims cannot be introduced at this stage of the process, as doing so would be procedurally unfair and outside the scope of the matters the bank was required to respond to. If the complainants wish to pursue concerns about the credit card account or other unrelated issues, they may raise them in a separate complaint, where they can be properly assessed on their own merits. Recommendation | Case number | 12-24-117680 | Financial firm | St George Bank Case number: 12-24-117680 17 November 2025 Recommendation overview 1.1 Complaint The complainant is challenging the bank’s conduct following its enforcement of a mortgage default. On 25 May 2022, the bank obtained a default judgment for possession of the property. It took physical possession on 16 March 2023, and the property was eventually sold on 17 April 2024, with settlement occurring on 23 May 2024. The core of the complaint centres on the enforcement costs charged to the loan account and the interest accrued due to delays in selling the property. The complainant disputes the necessity and reasonableness of various enforcement-related expenses, including charges for property maintenance, cleaning, decontamination, locksmith services, storage, removalists, legal fees, and valuations. She alleges that many of these costs were inflated, duplicated, or related to services not actually performed. In particular, she questions the involvement of multiple third-party contractors, some based in the Eastern States, arguing that their engagement led to excessive and unjustified costs. In addition, the complainant asserts that the bank unnecessarily delayed listing and selling the property, which resulted in significant interest accruing on her loan. She maintains that the property could have been sold much earlier and that her instructions to list it promptly were ignored. She estimates that approximately $20,000 in interest accrued between March 2023 and May 2024 due to these delays and argues that this financial impact was avoidable. 1.2 Issues and key findings Did the bank charge unreasonable or excessive costs as mortgagee in possession? No. The bank acted fairly and reasonably in recovering enforcement costs during the mortgagee sale, and the complainant’s objections were not supported by the information. Did the bank delay in selling the property after taking possession? No. The bank did not delay the sale; the time taken was due to mandatory remediation and compliance requirements, and the property was sold promptly once these were completed. Why is the outcome fair? The outcome is fair because the bank’s enforcement costs were necessary and lawful, and the delay in sale was due to mandatory compliance steps rather than inaction, with the bank later waiving significant debt as a goodwill gesture. 1.3 Recommendation The recommendation is substantially in favour of the bank. The bank is not required to compensate the complainant or take any corrective action. 2 Reasons for recommendation 2.1 Did the bank charge unreasonable or excessive costs as mortgagee in possession? No. The bank acted fairly and reasonably in recovering enforcement costs during the mortgagee sale, and the complainant’s objections were not supported by the information. Mortgagee’s right to recoup sale costs and AFCA’s role in reviewing them The bank is entitled to recover reasonable costs associated with a mortgagee sale. While it is not required to improve the property to achieve a higher sale price, as a private owner might, it is reasonable for the bank to undertake general upkeep and maintenance to prepare the property for sale. This may include cleaning, mowing lawns, repairing windows and doors, ensuring the property is secure and insured, and meeting any compliance requirements under relevant building codes or local regulations. There is no obligation on the mortgagee to enhance the property beyond basic maintenance. However, in some cases, limited improvements may be justified if they protect the mortgagor’s interests, for example, where the works materially improve the marketability or sale value of the property. In such cases, good industry practice is for the bank to obtain multiple competitive quotes and assess the likely impact of the works before proceeding. Once the bank has taken possession, it is generally entitled to reimburse itself for costs reasonably incurred in preparing the property for sale. These enforcement costs are typically recoverable under the loan’s terms and conditions. AFCA’s role in reviewing these costs is not to audit or verify the physical completion or quality of the works invoiced. AFCA is not an auditing body and does not have the power or resources to retrospectively confirm whether services were performed or whether they met any particular standard. Our focus is on whether the financial firm acted fairly, transparently, and in accordance with its obligations. In practice, AFCA generally accepts invoices provided by the financial firm as evidence that the works were carried out for the stated purpose, such as securing, cleaning, or preparing a property for sale. We do not inspect properties, interview contractors, or obtain independent reports to verify the necessity or execution of the works. Instead, we assess whether the costs appear reasonable in the circumstances and whether the firm’s decision-making process was appropriate. Where concerns are raised about duplication, inflated charges, or unnecessary works, AFCA will review the available documentation and consider whether the firm’s conduct was fair. However, AFCA cannot substitute itself for a regulator or auditor, it does not have statutory powers to compel third-party contractors or verify the physical completion of works. The complainant has raised concerns about enforcement costs applied during the mortgagee sale The complainant has disputed several invoices and corresponding enforcement expenses charged by the bank to her loan account. The list that follows summarises her key concerns in relation to the enforcement process. A complete list of the disputed expenses is provided in section 3.2 below. Possession and Property Preparation Costs · $14,242.33 for removalist, storage, locksmith, and supervision services, claimed to be excessive · $484 for boarding-up costs, alleged duplication and contractor-based interstate · $8,610 for cleaning, yard work, and repairs, many works allegedly not completed · $132 for yard maintenance, disputed as unnecessary · $17,692.40 for decontamination and electrical works, alleged duplication and inflated scope Contamination and Compliance Testing · $385 for contamination testing and $1,386 for assessment, disputed due to lack of WA accreditation · Contamination report challenged for factual inconsistencies and questionable sampling · Pool compliance reports disputed due to errors in pool type and features Valuation and Inspection Reports · Multiple $550 valuation invoices, disputed due to lack of detail · $677 for pest inspection, challenged as excessive compared to a $230 quote · $330 pool inspection, disputed due to the incorrect address error noted Electricity Charges · $85.84 and $14.49 in electricity charges, disputed as post-settlement and property was vacant Property Presentation and Inspections · $3,398 property presentation fee, disputed due to lack of detail and contractor location · Multiple $82 drive-by inspections, disputed due to lack of evidence Documentation and Evidence Concerns · Electrical safety certificates unsigned, no licence number, and power not connected · Contractor allegedly used incorrect ABN · Exhaust fan cover not cleaned or tested despite being listed · Sampling time recorded as 9:01pm, disputed as implausible I have reviewed the information provided by both parties regarding the enforcement costs applied during the mortgagee sale. I make the following comments on the reasonableness of the costs incurred, having regard to the documentation submitted, the bank’s obligations as mortgagee in possession, and the principles of fairness and transparency. The costs incurred to decontaminate the property were reasonable and justified The complainant asserts that the invoice of $17,692.40 from Company D was unjustified, claiming the work was not completed, the charges were excessive, and that certain items referenced in the quote, such as blinds and carpets, did not exist at the property. She also raises concerns about outsourcing, suggesting it created unnecessary complexity and inflated costs. After reviewing the documentation, I find these assertions are not supported. Independent testing confirmed methamphetamine contamination at the property, posing significant health risks and requiring remediation in line with the Australian Government’s Clandestine Drug Laboratory Remediation Guidelines (2011) and Code of Practice (2019). The bank obtained two quotes, Company D at $17,692.40 and Company RP at $20,286.20, and selected the lower quote, demonstrating efforts to minimise costs. The remediation included electrical safety works, chemical decontamination, and validation testing, all essential to restore the property to safe levels. A clearance certificate dated 14 June 2023 confirms these works were completed successfully. The use of subcontractors was reasonable and consistent with industry practice for managing complex contamination cases. While the complainant questions reference to blinds and carpets, these were part of a standard remediation scope based on contamination reports, not evidence of unnecessary work. On balance, the charges were appropriate, the work was completed, and the process followed was prudent and aligned with best practice. Drug testing and clearance were conducted in accordance with recognized standards The complainant argues that Company E was not Department of Health accredited and therefore unqualified to perform contamination testing or issue clearance certificates. While Company E is not listed as DOH-accredited, the evidence shows it is NATA-accredited under ISO/IEC 17025 for methamphetamine sampling and analysis, a recognised benchmark for laboratory competence in Australia. NATA accreditation is explicitly referenced in the Australian Government’s guidelines as the standard for validation testing. Reports provided by Company E were based on NIOSH 9111 protocols, which are internationally accepted for methamphetamine residue testing. Minor inconsistencies in photo timestamps or protective gear do not invalidate the laboratory results, which were generated under controlled conditions and verified by Safework Health. The clearance certificate issued on 14 June 2023 confirms contamination levels were reduced to below safe guideline thresholds. The complainant’s concerns about interstate location are not relevant; accredited laboratories routinely service properties nationwide. The critical factor is the integrity of the sampling and analysis process, which the evidence demonstrates was properly conducted. Accordingly, I am satisfied that the testing and clearance process complied with national standards and the complainant’s objections are not supported. The costs incurred to secure and store property were reasonable and necessary The complainant disputes the $14,242.33 invoice for removal, storage, and related services, claiming the amount was excessive. The property presenter notes confirm that following the Sheriff’s execution of possession on 16 March 2023, goods and chattels remained at the property. The complainant was present during eviction, removed some belongings herself, and consented to the agent packing remaining items for storage. Photographs and updates show these goods were later relocated to a storage facility and ultimately to the complainant’s nominated address. The invoice reflects a bundled service that included securing the property, changing locks, arranging professional removal of goods, and providing storage for multiple units over an extended period. These actions were essential to protect the property, comply with legal obligations, and mitigate risks of damage or liability. Coordinating these services under strict timelines inevitably incurred significant costs. The amount charged aligns with the complexity and urgency of the task and is supported by detailed records. Repairs and compliance works were necessary and appropriately costed The complainant challenges the $8,610 invoice dated 20 October 2023, claiming repairs were not completed and the charge was excessive. The works outlined were not discretionary improvements; they included compliance-critical tasks such as electrical safety checks, gas compliance, and replacement of essential fixtures like smoke alarms and ceiling fans. These measures were required under Western Australian regulations to ensure the property could be marketed and sold lawfully and safely. While the complainant suggests photographs show no visible changes, many tasks involve functional and safety components rather than cosmetic alterations. Compliance checks and minor repairs often do not produce dramatic visual differences, yet they are vital for meeting statutory obligations. The bank’s decision to consolidate tasks into one visit was practical and reduced delays and holding costs. On review, the invoice reflects legitimate work carried out to protect the property’s value and meet legal requirements. The bank appropriately charged for valuation services The complainant disputes three $550 invoices for valuations, arguing that the term “Professional Fees” lacks detail and implies no work was performed. Professional fees for valuation services are standard industry practice and typically cover preparation, review, and submission of valuation reports, services essential in mortgagee-in-possession matters. The bank’s records confirm three valuations were completed and relied upon during the disposal process. While the invoices are not itemised, this reflects the nature of professional services, which are billed as a single fee for expertise and time. On balance, the charges were reasonable and proportionate to the services provided. The bank appropriately charged for occupancy and drive by checks The complainant disputes multiple charges of approximately $82 each for occupancy and drive-by checks, arguing these were unnecessary and possibly never performed. The property presenter notes confirm these checks were part of the enforcement process, which is standard practice to verify property status and mitigate risk. While the invoices are brief, this reflects the nature of such services, which are billed as a flat fee for coordination and execution rather than itemised tasks. These checks were necessary to progress possession and disposal of the property, and the fees charged were reasonable and proportionate. The timber and pest inspection report was necessary and properly charged The complainant disputes the $677 invoice for a timber and pest inspection, claiming the cost was excessive compared to a quote she says she obtained for $230. However, she has not provided a copy of the alternative quote or invoice to substantiate this claim. The inspection was comprehensive, carried out by a licensed provider, and included a detailed assessment of structural and pest-related risks in accordance with Australian Standards. This was not a basic check; the report spans multiple sections, identifies structural issues, and provides recommendations essential for the mortgagee-in-possession process. The higher cost reflects the scope of work, urgency, and coordination required to ensure the property was safe and marketable. The property presenter’s fee was reasonable and supported by documentation The complainant disputes the $3,398 invoice for property presenting services, arguing that the invoice lacks detail and questions whether the company, as an interstate outsourcing firm, could have performed any work directly. The information confirms the company was appointed to manage the mortgagee-in-possession process, which involved coordinating multiple activities necessary to secure, remediate, and prepare the property for sale. These services included arranging inspections, liaising with trades, managing compliance issues, and overseeing works on-site through subcontractors. It is standard industry practice for property presenters to charge a consolidated fee for these services rather than itemising every task. The absence of granular detail does not indicate that no work was completed; rather, it reflects the nature of project management services. In these circumstances, the fee of $3,398 was reasonable and proportionate to the complexity and scope of work required. The bank did not charge unreasonable or excessive costs as mortgagee in possession I have considered all of the complainant’s concerns regarding enforcement costs applied during the mortgagee sale. While I have not commented on every individual disputed expense, given the number and repetition of issues raised, I have reviewed them all and they do not alter my overall view. The bank acted fairly and reasonably in recovering these costs, and the complainant’s objections are not supported by the information. It is also relevant that, following settlement, the bank waived the outstanding balance of $3,888.19 remaining on the complainant’s home loan and the balance of $4,603.31 owing on a joint credit card held by the complainant and the co-borrower. Both amounts were waived on a goodwill basis. Taken together, this represents a significant financial benefit to the complainant. Even if I were to accept that some individual expenses might have been higher than necessary, the combined goodwill concessions far exceed any disputed amounts. On balance, the complainant has been more than compensated, and I am satisfied that the bank’s overall approach was fair and reasonable. 2.2 Did the bank delay in selling the property after taking possession? No. The bank did not delay the sale; the time taken was due to mandatory remediation and compliance requirements, and the property was sold promptly once these were completed. The complainant says the bank delayed selling the property The complainant argues that the bank delayed selling the property for 12 months after taking possession on 16 March 2023. She claims this delay caused unnecessary interest charges totalling approximately $20,000, which she believes should be refunded. Her position is that the bank ignored her instruction to list the property immediately and instead allowed interest to accrue during this period. The bank took swift action following possession of the property The information shows the bank acted promptly following possession. On 16 March 2023, the Sheriff executed possession and the bank’s agent secured the property the same day. Locks were changed, goods were packed and moved to storage with the complainant’s cooperation, and an abandoned goods notice was issued. A valuation was ordered on 17 March 2023, indicating the bank’s intention to progress the sale without delay. The bank acted after meth contamination was suspected On 24 March 2023, the selling agent reported suspected methamphetamine contamination, triggering mandatory health and safety protocols. Chemical testing confirmed contamination above guideline levels. Under national standards, remediation was essential before marketing. Two quotes were obtained, and the lower quote was approved. Decontamination works were completed, and a clearance certificate was issued on 14 June 2023. These steps were not discretionary; they were required to ensure the property was safe and legally compliant. The bank could not list the property until compliance issues were resolved After remediation was completed in June 2023, the property could not be listed immediately because further statutory compliance issues had to be addressed: · The pool fencing was non-compliant under WA regulations. Rectification was required before sale to avoid liability and ensure compliance with the Building Act. This work was approved and completed in March 2024. · Power could not be connected because a fuse wedge was missing from the board. The energy company advised this on 21 March 2024, and an electrician attended in early April to rectify the issue. A reconnection request was submitted on 3 April 2024. Without power, the property could not be marketed or inspected safely. These delays were due to external utility requirements and compliance obligations, not bank inaction. · Updated valuations were needed to reflect the property’s condition and compliance status. Valuers were unable to provide “as if complete” figures until pool and electrical works were finalised. These steps were essential for accurate pricing and insurer approval. These were not optional enhancements; they were legal and safety requirements. The timeline shows the bank continued to progress these steps rather than leaving the property idle. The bank listed the property promptly after compliance was achieved Once compliance was achieved, the bank moved quickly. The property was listed online on 7 April 2024 with a price of $445,000. Multiple offers were received by 17 April 2024, and the highest offer of $520,000 was accepted. Contracts were signed, and settlement occurred on 23 May 2024. The bank did not delay in selling the property after taking possession While the complainant asserts that the bank delayed for 12 months, the information shows the period before listing was driven by contamination remediation, pool and electrical compliance, and valuation requirements, all necessary to ensure lawful and safe sale. These were not caused by inaction or disregard for the complainant’s interests. On balance, the information supports that the bank did not unreasonably delay selling the property after taking possession. The claim of excessive delay and associated interest charges is not substantiated. A full chronology of events can be found in section 3.3 below. 2.3 Why is the outcome fair? The outcome is fair because the bank acted reasonably on both issues raised. First, the enforcement costs were necessary to secure, remediate, and prepare the property for sale, including meth contamination clearance, pool compliance, and electrical safety works, all mandated under law. The bank later waived over $8,000 in residual debt on a goodwill basis, which outweighs any disputed amounts. Second, the alleged delay was not due to inaction but to mandatory remediation and compliance steps. Once these were completed, the property was listed promptly, multiple offers were received, and settlement occurred quickly. Taken together, the bank’s approach was fair, transparent, and proportionate. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has assessed this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this recommendation to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Enforcement costs | Invoice Date | Invoice Amount | Description | Loan debit date | Loan debit amount | 8 Feb 2021 | $88 | Drive-by | 23 Feb 2021 | $82 | 11 Feb 2021 | $82.50 | Field call | 12 Mar 2021 | $82.5 | 4 Oct 2021 | $82.5 | Field call | 28 Oct 2021 | $82 | 8 Oct 2021 | $88 | Drive-by | 9 Nov 2021 | $76.88 | 28 Jun 2022 | $95.98 | Attempt fee | 22 Jul 2022 | $93.41 | 28 Jun 2022 | $95.98 | Service fee | 22 Jul 2022 | $93.41 | 15 Aug 2022 | $82.5 | Field call | 7 Sep 2022 | $82 | 16 Aug 2022 | $88 | Legal fee | 7 Sep 2022 | $76.88 | 22 Mar 2023 | $14,242.33 | Removalist fee, storage fee, locksmith fee etc | 18 Apr 2023 | $14,242.33 | 19 Apr 2023 | $385 | Lab testing | 9 May 2023 | $385 | 21 Apr 2023 | $2,471.70 | Storage fee | 30 May 2023 | $2,471.70 | 3 May 2023 | $1,386 | Lab testing detailed assessment | 28 Jun 2023 | $1,386 | 23 May 2023 | $330 | Pool safety inspection | Nil | Nil charge | 23 May 2023 | $1,235.85 | Storage fee | 14 Jun 2023 | $1,238.85 | 30 May 2023 | $484 | Decontamination process etc | 21 Jun 2023 | $484 | 31 May 2023 | $17,692.40 | Electrical make safe, decontamination process etc | 13 Jul 2023 | $17,692.40 | 5 Jun 2023 | $1,045 | Supervised access fee | 13 Jul 2023 | $1,045 | 6 Jun 2023 | $2,880 | Removalist & disposal fee etc | 13 Jul 2023 | $2,683.34 | 23 Jun 2023 | $550 | Valuation fee | 13 Jul 2023 | $550 | 4 Aug 2023 | $677 | Pest inspection report fee | 28 Aug 2023 | $630.85 | 21 Sep 2023 | $550 | Valuation fee | 11 Oct 2023 | $550 | 20 Oct 2023 | $8,610 | Internal clean, yard clean, electricity safety check etc | 16 Nov 2023 | $8,610 | 22 Jan 2024 | $132 | Yard maintenance | 22 Feb 2024 | $132 | 25 Jan 2024 | $3,927 | Pool compliance, rubbish removal etc | 27 Feb 2024 | $3,927. | 20 Feb 2024 | $6,290 | Pool compliance works | 21 Mar 2024 | $6,290 | 20 Mar 2024 | $550 | Valuation fee | 3 May 2024 | $550 | 28 Mar 2024 | $120 | Yard maintenance | 23 Apr 2024 | $120 | 24 Apr 2024 | $3,398 | Property presenter fee | 22 May 2024 | $3,398 | 17 May 2024 | $85.07 | Electricity charges | 6 Jun 2024 | $85.84 | 21 May 2024 | $14.36 | Electricity charges | 12 Jun 2024 | $14.49 3.3 Chronology of key events | Date | Description | 16 Mar 2023 | · Possession secured 11am on 16 March 2024 · COM on site and packed her belongings into cars, with another load left at front of property to collect later in the day · COM removed her two dogs · Agent packed remaining goods for removalist · Abandoned Goods Notice requested | 20 Mar 2023 | Agency R appraisal $320,000 - $360,000. Proposed commission 3.3% incl. GST and a private treaty marketing campaign of $1,429 | 23 Mar 2023 | Valuer attended property, but keys did not work | 24 Mar 2023 | Agent suspects property may have been used as a lab to manufacture illicit drugs. Valuation put on hold and chemical analysis (meth testing) ordered. | 3 Apr 2023 | Company L update front door damaged and quote being arranged to resecure property. No sign of successful forced entry | 11 Apr 2023 | Agent advises front door lock has been tampered with. Company E will be attending 18 April 2024 for chemical testing and asked entry to the granny flat also be checked. | 19 Apr 2023 | Safework Health WA provides company E with a surface testing report, related to a sample taken 17.4.24. Regarding methamphetamine, six sample tubes reported as exceeding the working range. Report shows National Association of Testing Authorities (NATA) accreditation. Company E report chemical levels are above guideline and quote for a detailed assessment. | 24 Apr 2023 | Valuation cancelled | 5 May 2023 | Company E report and remediation plan received, with recommendation to engage decontamination company to remediate rooms that have tested over guidelines | 9 May 2023 | Company L advise bank that COM has contacted it about her goods in storage and asked if a removalist can be arranged for her. Quotes are being obtained. | 16 May 2023 | Mortgage insurer agrees to removal quote of $2,550 to move all goods and chattels to COM’s address | 23 May 2023 | Emergency call out to property to resecure front door. (RSCPA had been onsite to remove a kitten abandoned under house and reported front door broken into) | 24 May 2023 | Company D instructed to proceed with works under remediation quote | 1 Jun 2023 | Removal of goods from storage to COM scheduled 7am on 2 June 2023 | 5 Jun 2023 | Company P report all items from 5 units removed from Storage on 2 June 2023 and delivered to COM at suburb Y. Truck departed storage facility at 9.15 and agent took photos showing units were empty. | | | 14 Jun 2023 | Company E clearance certificate after decontamination works - testing results at safe levels | 23 Jun 2023 | Valuation ‘as is’ and ‘as if’: $280,000 (range $270,000 - $290,000) Valuation notes comment that property is below average presentation, ‘properties use as a lab for manufacture of illicit drugs’ and ‘not suitable for rent’. | 30 Jun 2023 | Valuer asked to provide ‘as if complete’ figure without quotes | 4 Aug 2023 | Pest inspection performed and building inspection performed | 22 Aug 2023 | Building and pest report received and awaiting quotes | 12 September 2023 | Quotes received from agent ‘As if complete’ valuation ordered based on quote and reports | 21 Sep 2023 | Valuation ‘as is’: $280,000 (range $270,000 - $290,000) Valuation ‘as if’: $290,000 (range $280,000 - $300,000) – references a building and pest report; and quote to remedy critical issues in building report. | 28 September 2023 | Agent asked to provide updated appraisal | 1 Oct 2023 | Updated Agency R appraisal of $320,000 to $360.000. Proposed commission 3.3% and marketing $1,529 | 23 Oct 2023 | LMI Insurer agrees to commission 2.2% incl. GST and marketing $1,529 | 1 Nov 2023 | Agency R appointed under and exclusive agency agreement based on a commission 2.2% incl. GST and marketing of $1,529. List price is stated TBA | 16 Nov 2023 | Agent confirms property is still secured and contractor still working onsite. Company L note another submission (quotes) may be required, because contractor has identified non-compliance issues with pool and electricity | 5 Dec 2023 | Company L waiting for quotes to achieve ‘as if complete’ valuation | 29 Dec 2023 | Company L recommend sale ‘as is’ | 5 Jan 2024 | Bank approves further works $3,927 to sell ‘as is’ | 19 Jan 2024 | Agent provided a certificate that pool is not compliant. Company L recommends making fence compliant and selling with pool empty. | 5 Feb 2024 | Bank approves further works $6,290 to make the swimming pool compliant | 6 Mar 2024 | Valuation ordered and power connection request made to company S | 20 Mar 2024 | Valuation ‘as is’ $420,000 (range $400,000 - $440,000). Condition comments: damage to flooring/internal walls/internal paint/windows, pool out of commission and pool fencing not up to code. Valuer advised property to be sold as is. | 21 Mar 2024 | Company S advice power cannot be connected because a fuse wedge was missing from the board, and an electrician will need to rectify this | 22 Mar 2024 | Council issue swimming pool compliance certificate | 3 Apr 2024 | Power connection request sent to company S | 7 Apr 2024 | Property listed online for sale. Listing price $445,000 | 17 Apr 2024 | 7 offers received: o $520,000 | Deposit: $1000 | 14 days finance | 28 days settlement o $455,000 | Deposit: $20000 | 21 days finance | 28 days settlement o $445,000 | Deposit: $3500 | 28 days finance | 21 days settlement o $420,000 | Deposit: $15000 | 14 days finance | 28 days settlement o $363,000 | Deposit: $1000 | 21 days finance | 28 days settlement o $420,000 | Deposit: $5000 | unconditional | 28 days settlement o $410,000 | Deposit: $5000 | 19/04/24 finance |To coincide with the successful settlement of buyer’s Bank approved $520,000 offer | 23 May 2024 | Settlement completed 3.4 Issues not considered The complainant has raised numerous additional issues, including but not limited to concerns about the timing of the settlement statement, queries about internal bank notes, and allegations that her redraw limit was increased without consent. I have not investigated these matters because I do not consider them material to the outcome, and even if established, they would not change my decision. This is because the complainant has already been adequately compensated by the bank, which waived more than $8,000 owed under her home loan and joint credit card by way of a debt waiver. On balance, this represents a significant financial benefit and addresses any residual concerns.