Settlement of storm damage claim, additional damage from delays and make-safe failures, damaged contents, and compensation for claim handling
Text of the determination
Determination
|
Case number
|
12-24-117130
|
Financial firm
|
Allianz Australia Insurance Limited
Case number: 12-24-117130 2 July 2025
Determination overview
Complaint
The complainant lodged a claim with the financial firm (insurer) under the home insurance policy after storms damaged the insured property on or around 25 December 2023.
The insurer accepted the claim partially, for resultant damage. It denied liability for the storm damaged contents as the complainant has not takeout contents insurance cover. It refused liability for damage unrelated to the storm and caused by causes excluded under the policy.
The complainant seeks the insurer to cash settle for the repair cost, temporary accommodation and contents damaged due to its poor claim handling.
Issues and key findings
Is the insurer’s settlement fair?
No. The property condition has deteriorated significantly since claim lodgement. The insurer is responsible for the damage caused by the storm and because of its claim handling. It should reassess the damage and revise the scope of works. It is fair the insurer provides a cash settlement for the loss including temporary accommodation, given the claim delays.
Is the insurer liable for the damaged contents?
Yes. The insurer is not liable for contents damaged from the initial storm event because the complainant did not have contents insurance cover. It is however liable for the contents damaged from subsequent water ingress events to the property and mould infestation from the insurer’s trades’ actions/inactions.
Is the insurer required to pay compensation?
Yes. The insurer’s claim handling, delays in appointing trades, delays in arranging temporary accommodation and additional damage caused to the property by the trades caused severe stress, inconvenience and frustration to the complainant and his young family.
Why is the outcome fair?
The parties are bound by the policy terms and conditions. It is fair the insurer accepts liability for the damage caused by the insured event, additional damage caused by its appointed trades’ actions/inactions and pays compensation for its overall claim handling.
Determination
This determination is in favour of the complainant.
Within 14 days of being notified of the complainant’s acceptance of this determination, the insurer should pay $6,300 non-financial loss compensation. The insurer is required to assess the property and settle claim as explained in section 2.1 and settle the claim for the damaged contents as explained in section 2.2, within reasonable timeframes.
Reasons for determination
Is the insurer’s settlement fair?
No. The property condition has deteriorated significantly since claim lodgement. The insurer is responsible for the damage caused by the storm and because of its claim handling. It should reassess the damage and revise the scope of works. It is fair the insurer provides a cash settlement for the loss including temporary accommodation, given the claim delays.
Complainant must establish a claimable loss
When making a claim, the complainant has the initial onus of establishing he suffered a loss for which the insurance policy provides cover. The complainant must establish this on the balance of probabilities (i.e. that it is more likely than not).
If a claimable loss is established, the insurer has the onus of establishing, on the balance of probabilities, the application of any exclusion it relies on to reduce its liability.
There is no dispute between the parties the complainant has established a claimable loss for storm damage on or around 25 December 2023. The complainant says he accepted responsibility for the maintenance works required to the balcony and has since addressed this concern.
Parties provided different views on the additional damage to the property
The complainant says:
the insurer approved for the roof removal amid the storm season including leaving the windows open. The roof was left off for an extended period and the home has suffered from water ingress and flooding over 20 times
the last time anyone attended the property was in March 2025, when the house failed its asbestos hygienist clearance. Since then, there have been no further inspections, no structural assessments, no decontamination, and no progress on roof works or repairs. The property remains exposed, deteriorating, and contaminated, with no active project management or communication
his home is completely ruined and there is nothing salvageable
after removing the asbestos, the insurer’s trades had left asbestos pieces all throughout the property including inside the water tank, lawn, down pipes and on the public road
he seeks the insurer to remove all mould and asbestos from the property and then provide a cash settlement for the repairs so that he may rebuild the home and move back with his family without further delays
he also seeks a payout for temporary accommodation so that he can arrange temporary accommodation for the repair period
the property has never had a mould issue up until this claim.
The insurer says:
rainwater entering buildings through non-storm related openings is typically not covered under the policy. However, due to the extreme weather conditions, it accepted liability for damage caused by the rainwater ingress, including mould remediation
the identified maintenance issues must be addressed at the complainant’s own expense as they are not storm-related but due to depreciation, deterioration, wear and tear, faulty design, and poor workmanship (Outdoor upper-level deck did not comply with the required step down to prevent water ingress and there was failed waterproofing from balcony)
temporary accommodation was extended beyond the policy limitations
it has approved mould remediation and removal of asbestos
it is unable to address the various concerns raised by the complainant about the extent of property damage and scope of repairs. Clearance certification is required before the experts including an engineer could attend the property to conduct further assessments.
Insurer’s delays caused additional damage to the property
The exchanged information shows other than the water ingress points via the balcony, no maintenance issues were identified by the insurer’s appointed builder K during its initial assessments.
The roof assessment and the leak detection test arranged by the insurer did not identify any issues with the roof or other internal leaks. The roofer did not identify any defects or evidence of a roof leak during their attendance. The leak detection test on the balcony was delayed by several months due to miscommunication between the insurer and K. The complainant accepted responsibility for this repair and requested the insurer progress the claim, given the delays (see section 3.2).
I accept the insurer is entitled conduct investigations to ascertain the proximate cause of the loss. Further all points of water ingress should be identified before commencing repairs avoiding the possibility of further damage occurring in the future. While ruling out the causes of the damage was a prudent action, it is unclear why the insurer did not arrange all the assessments soon after claim lodgement.
Delays in arranging various assessments following an elimination process, one assessment at a time, took more than the usual timeframes, causing extensive delays.
While the insurer says the complainant had indicated make safe works were not required in January 2024, the complainant says he informed the builder that make safe works by tarping the roof was not necessary as the water did not ingress via the roof. Other than a general comment, there is no further information on the reasons why the complainant may have refused make safe works given several areas of the property had suffered from water ingress after the initial storm event.
No drying equipment was used or any measures taken to dry out the water damaged areas. Given the insurer’s builder attended the property on several occasions, it is reasonable the builder would have noticed the need for make safe works to these areas.
None of the insurer’s experts also observed any mould at the property in the months following claim lodgement. On or around 22 April 2024, the complainant notified the insurer of mould growing at the property and the insurer commenced assessment and mould remediation in May 2024, a month after the notification. The mould continued to spread and contaminate the building and contents.
The complainant has provided several images showing the condition of the property after the insurer’s appointed builder’s tarping on the roof failed. The trades had also left some windows open. Subsequent storms and cyclones caused further water ingress and flooding to the property resulting in significant damage to the building and contents.
Failing to safely remove the asbestos had also contaminated several areas of the property which resulted in all works coming to a halt until a clearance certificate is obtained confirming the complete removal of asbestos particles.
Insurer liable for additional damage to the property
There is no persuasive information to show the mould infestation at the property was due to environmental factors because the complainant’s property is situated near a rain forest as suggested by the insurer.
As discussed above, it is unclear why the insurer did not make any arrangement to dry out the property after claim lodgement given the water ingress damage. There are no detailed notes showing the reasons why the complainant said make safe works were not required or what plans he had to dry out the property himself, at the time.
It is unclear if the second builder M who attended the property for assessment was provided a copy of all the assessment and investigations conducted by K and the trades who attended the property soon after claim lodgement. This is because M’s observations do not appear to have considered K’s initial assessments and findings.
I acknowledge the roof replacement was scheduled by the insurer in advance of any forecasted cyclone activity. While protective tarps were installed, the dislodged tarps during the storm events allowed water ingress into the property in addition to water ingress via the windows left open. Due to the asbestos contamination present on site, drying equipment could not be installed safely from March 2025.
Given the above, I am satisfied the mould infestation and additional water ingress to the property occurred due to the insurer’s poor and inadequate make safe works and delayed claim handling. Once the claim was lodged, the responsibility remained with the insurer to assess the property within reasonable timeframes and arrange make safe and repairs in a timely manner.
Section 3.2 shows various delays caused by the insurer and miscommunication between the insurer and its appointed experts/trades.
The condition of the property has continued to deteriorate, and it is fair the complainant refused to allow the insurer to progress with works until the scope of works included all repairs of damage caused by the insured event and additional damage caused by the insurer’s trades’ actions/inactions.
While the complainant arranging the Queensland Workplace Health and Safety assessment may have slightly delayed the claim, I am satisfied the exchanged information shows most of the claim delays were caused by the insurer and its appointed representatives and/or trades.
I acknowledge the insurer is required to complete the following before addressing the complainant’s various concerns about the extent of the damage sustained to the property including its safety:
asbestos decontamination and clearance certification
completion of roof works
full internal mould remediation and post remedial verification clearance
attendance by a qualified structural engineer to assess the property.
Once the above process is completed, the insurer is to submit a detailed scope of works listing the works required to reinstate the property to its pre-loss condition. A repair quote should then be obtained covering the works specified in the scope of works.
While the insurer’s liability under the policy is generally limited to the building sum insured ($400,715) including policy cover pursuant to the policy terms and conditions, the property damage caused by the insurer’s appointed representatives falls outside of the above sum insured. The complainant is also entitled to temporary accommodation until the above process is completed and a further allowance for the period of repairs, regardless of any applicable policy limit, for the above reasons.
Given the insurer’s claim handling so fair, it is fair the insurer cash settles the complainant for the repairs based on actionable quotes including allowances for transfer of risk and contingencies.
The insurer should also review and reimburse claim related expenses incurred by the complainant. Once detailed invoices are submitted, the insurer should review and settle this part of the claim in a timely manner.
Is the insurer liable for the damaged contents?
Yes. The insurer is not liable for contents damaged from the initial storm event because the complainant did not have contents insurance cover. It is however liable for the contents damaged from subsequent water ingress events to the property and mould infestation from the insurer’s trades’ actions/inactions.
Insurer not liable for the damaged contents from the original storm event
The complainant has not taken contents insurance cover. The initial claim lodgement noted the contents in the complainant’s daughter’s room were damaged by water ingress. The complainant says these items were discarded and were non-salvageable. The insurer is not liable for these contents. The complainant accepts the insurer’s decision in this regard.
Parties provided different views on cause of the damage to contents
The insurer refused to accept liability for the remaining damaged contents on the basis:
the complainant did not take out contents insurance cover
the complainant is responsible for removing, remediating or disposing of mould infested contents
the complainant refused to allow the restorer to discard any contents until the insurer accepted liability for the damage.
The complainant says:
all belongings that have been impacted from the insurer’s incompetence should be replaced via payout. This includes furniture, clothing, toys, decor, artwork, bedding, mattresses and all other personal items
the property does not have ventilation issues, and he has never had to dispose of any of the belongings due to mould until this storm event and the insurer’s delays
none of these contents would have been thrown away had the insurer acted in a professional manner within reasonable timeframes
the mention of mould being caused by ‘environmental factors’ was only given by a builder and not a qualified mould specialist or anyone in the field
it is concerning that the first time the insurer advised him to remove the contents from the house was after he had already reported the presence of widespread mould. But even then, the insurer insisted that all items remain inside the mould-infested house until a third-party inventory company could document them
he was forced to leave everything he owned in a contaminated environment, which led to further destruction of items that might have otherwise been saved. This instruction was unsafe and completely unreasonable. It placed the insurer’s administrative process above his health and the protection of his property.
Insurer liable for mould infested and water damaged contents from its actions
The complainant seeks the insurer to pay for the contents damaged due to delayed repairs, mould infestation and subsequent water ingress into the property on several occasions. The claim notes indicate the insurer’s restorer may have created a list of water damaged items and another list of mould infested items. These have not been shared with AFCA.
The initial site inspection report notes heavy rains had come into the property and flooded upstairs ruining all the complainant’s daughter’s belongings and her floor. No long-term damage was identified at the time.
The restorer attended in May 2024 and noted during rain events, water leaks from the balcony into the interior of the property caused by failed water proofing and damaging of the lower ceiling in the kitchen and that mould was growing in surrounding areas which needed rectification.
The insurer says it was not until 22 April 2024, four months later, the complainant reported the presence of mould damage to the contents. It is however unclear why K and the other experts did not identify any mould contamination during their various property visits.
While the insurer states the complainant refused make safe works and had failed to act promptly mitigating the loss, the complainant says the water damaged contents were discarded after the original storm event. They were not aware of mould contamination until they noticed this issue. The family resided at the property and used the contaminated contents until this issue was identified.
The insurer continued its investigations in the months following claim lodgement, delayed the leak detection test on the balcony, which was suspected to be the proximate cause of the initial water ingress. It failed to communicate with the complainant about the maintenance works that were required to the balcony and discuss any timeframes by when it expected these maintenance works to be completed.
The insurer says it promptly arranged restoration services with L attending on 22 May 2024, 5 June 2024, 5 July 2024, 11 July 2024, and 15 July 2024 to address the ongoing issues. This was however a month after the complainant notified it of the presence of mould. The mould assessment and remediation were further delayed because the insurer refused to accept liability for the contents contaminated by mould.
Given the above, the insurer has accepted mould contamination and damage to the building, make safe works and claim delays, I am satisfied the insurer is responsible for the mould contaminated, asbestos contaminated (if any) and water damaged contents because of its appointed trades’ actions/inactions.
The insurer is also responsible for removal and storage of contents during the repair period, for the same reasons discussed above.
Is the insurer required to pay compensation?
Yes. The insurer’s claim handling, delays in appointing trades, delays in arranging temporary accommodation and additional damage caused to the property by the trades caused severe stress, inconvenience and frustration to the complainant and his young family.
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. When considering non-financial loss compensation, AFCA looks at what is reasonable and fair in all the circumstances. In considering what is fair in all the circumstances, it is appropriate to factor the overall claims experience, rather than focusing on specific individual events.
Insurer’s overall claim handling was poor
The complainant says:
the insurer did not provide him and his young family with temporary accommodation until nearly six months after the initial event, and not until almost six weeks after he had formally notified it of the presence of black mould
his young family was exposed to serious health risks being placed in an unsafe, toxic environment for an extended period while the insurer delayed action
his family has been displaced from their home for almost a year, leaving him with devastating losses
his family has lost cherished mementos of their deceased child, now contaminated with black mould and other sentimental items. The emotional pain is overwhelming
the insurer placed him under extreme emotional, financial, and psychological pressure
the insurer’s handling of the roof, asbestos, structural damage, and follow-up works raises serious concerns
the prolonged displacement has caused severe depression and anxiety in their family with minimal living conditions, with only a few belongings
inadequate housing forced his family to rely on friends' homes or their front yard when the insurer was unable to secure accommodation due to leaving the booking until the last-minute including neglecting their two dogs due to insufficient accommodation.
While the insurer says it has acted in full compliance with the General Insurance Code of Practice, ensuring a thorough and equitable review of the claims, the insurer’s claim staff acknowledged and apologised to the complainant for the poor handling of the claim on several occasions during the claims process:
I completely agree that it is unacceptable the mould has been allowed to develop and I apologise this was not dealt with sooner. I have lodged this as a complaint for you and your complaint handler will be in touch with you to discuss the next steps.
The claim notes show the insurer’s call attempts at times were unsuccessful due to the complainant’s phone message bank being full. The complainant was available on email. If the complainant’s wife was unavailable to take the call, the insurer could have contacted the complainant. The claim notes show the insurer could have progressed the claim faster and this may have avoided the mould and additional damage to the property.
The insurer could have proactively arranged temporary accommodation and lack of resulted in the complainant and his family seeking shelter in the front yard of the property infested with mould and organising last minute stay with their friends. This would have been significantly stressful and inconvenient. There were issues experienced accommodating the two pets which caused further inconvenience.
Given the condition of the home and contents, the complainant and his young family were managing with the limited number of personal belongings they took when they vacated the property, for almost 12 months.
The insurer’s poor claim handling and make safe caused further damage to the property and until the insurer accepts liability for the claim related and other damage, the complainant remains stressed and anxious.
The complainant raised concerns with asbestos particles spread to the lawn, plumbing and other areas of the property. He had also entered the property with his family exposing them to the asbestos particles because the insurer had not safely removed them. This caused severe stress and emotional distress to the complainant and his family.
While the insurer has recently appointed a loss assessor and there is a plan to repair the property, I am satisfied the insurer could have better managed the claim.
Given the complainant’s experience and the insurer’s overall claim handling, it is fair in all the circumstances the insurer pays $6,300 non-financial loss compensation.
Complainant can lodge a new complaint if issues remain unresolved
The insurer should assess the damage and settle the claim as detailed above within reasonable timeframes. If the parties are unable to resolve any aspect of the claim in the future including further claim delays, the complainant is free to lodge a new complaint with AFCA for its review and consideration.
Supporting information
The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.
Claim notes
|
Date
|
Notes
|
3-1-2024
|
It rained that much that rain came in and over the hob of the outside door and flooded upstairs, ruining all of my daughter’s belongings and her floor. It went through the floor and down into the ceiling and walls of the kitchen and destroyed the ceilings, walls, bench top and stovetop. He came home from holidays and found damage through house He is carpenter and has cleaned up a lot Timber flooring is bowed, and he has had to prop up the floor
Its secure he has no immediate concerns
|
10-1-2024
|
io has advised that there are no make safe works needed io has advise he has had to hire generator for 9 days as he had no power
|
14-2-2024
|
claim is accepted
|
2-3-2024
|
Reviewed file and believe as cat event OK to allow internal damages, however we need to confirm no other damages from water in kitchen have contributed to flooring for example. Have
requested LDT to confirm this. Email sent to customer confirming acceptance.
|
12-3-2024
|
Our trade has attended on 06/03 to complete the leak detection report per previous communications. I have followed up with the trade to confirm receipt of the report and to confirm they note in their report regarding the kitchen floor.
|
22-4-2024
|
have advised io why roof report is needed
have advised io claim has been acceptance and that we need to cover all aspects to confirm cover
io was thankful and has advised there is mould present
have advised I will organise restorers to attend
|
17-5-2024
|
roof report was received on …on 25/04/2024 and was labelled and closed by previous consultant 09/05/2024 but no action was taken. This has caused further delays for the insured who was already frustrated with the time taken on the claim and the number of reports required. Mould resto was also not appointed as per file note 22/04
|
23-5-2024
|
[K] rec'd email from plumber who attended which conf he was under impression attending for underground leak -I conf attendance was supposed to be for LDT for balcony - -adv the LDT needs to be urgent as have a new complaint regarding the attendance
|
29-5-2024
|
Complaint email from insd - resto advised black mould present at property and insd will need to vacate.
Email from insd:
-LDT never completed on balcony, -queried furniture removal during resto, -furniture now mould damaged -conf 2 adults, 3 children, 2 dogs
|
31-5-2024
|
OBC to [K]…-adv we need to look into what has happened as clarification of LDT to balcony was sent multiple times and this was flagged as urgent but now has caused further delays on claim
insd conf they do not want any additional testing completed and are happy to accept balcony as maintenance
-discussed that maintenance would need to be completed prior to repairs or we can cash settle
-insd had not heard from [L]
|
4-6-2024
|
Resto report received from initial attendance:
Confirmed mould present as result of water ingress
MS completed and further attendances to take place for full resto
|
12-6-2024
|
Response from [L]:
-resto paused in bedroom pending asbestos testing
-asbestos confirmed present
|
17-6-2024
|
1. Looking for clarification on floor it's not salvageable and they're looking for confo if they should remove it
2. They have made an inventory list as requested, asking should they dispose of the non-restorable
items even though the INSD doesn’t hold contents cover
3. Asbestos test came back positive, they're removing the asbestos. In order to remove it all from the bedroom ceiling they would need to remove a section of the roof above as well as the solar. They're asking should they just remove a section of the ceiling where the mould is
|
18-6-2024
|
Response to [L] please do not remove the flooring if it is structural
2. please request the insd sign a waiver for removal of non-restorable contents
3. please only proceed with asbestos removal which is required for resto to be completed
|
27-6-2024
|
*insd advised he is considering CS for the repairs as he is tired of waiting *advised insd Restoration will be in touch early next week to confirm re-attendance
|
12-7-2024
|
- INSD adv that no one from resto has been in touch and house now completely covered in mould
- Apologised and adv I would follow this up
|
10-7-2024
|
Insd adv of TA concerns and mould growing at their property
Insd adv restorations have adv mould has spread all the way through their property causing damage to their contents which restorations need to disclose of Insd adv if [insurer] had of acted faster to the claim this would not be happening
|
11-7-2024
|
ATP adv restorations are at their property now doing assessment of contents items
|
12-7-2024
|
resto report required with update on claim and actions they are taking regarding BLD and CNTS.
- 2x CNTS list required one for storm damaged CNTS and one for mould damaged CNTS.
|
24-7-2024
|
*Insured said when is building repairs going to start, I said cash settlement was requested
*she it was originally however the restoration has not been completed, and the mould is getting worse.
*I said we were told restoration was completed, she got extremely irate and said no restoration has been completed.
*said [L] no come to her house mould is still there and is getting worse and asbestos
*I said can she hold while i call [L]. …I investigated further and we realised [L] confirmed that the builders need to remove the asbestos mould removal.
*I have sent them a message on …asking if they can start working on the asbestos mould as it is spreading fast.
|
25-7-2024
|
[L] advise cannot complete mould remediation until solar panels removed, this then changed to a full roof removal.
|
30-7-2024
|
PENDING
- Roof repairs mostly/unclear why roof repairs are being included, need to understand if this is due to asbestos or maintenance which is excluded.
…
Intro myself and that I will be managing the claim.
- Advised INSD we have [MK] report and resto sow has been approved.
- Advised bld sow can take time and is often not completed until resto is finished to see full sow required.
- Advised INSD they can remove their cnts from the property so resto can begin.
- INSD understood and asked what is in the resto sow?
- Advised of areas as per resto sow.
- INSD was unhappy with this and said she was told the full house is being removed all walls and ceilings and she will not proceed with resto until this is advised.
- Advised the best thing we can do is move fwd with resto to start repairing the property and things can change.
- INSD said no she is not doing that and asked me if all walls and ceiling is being removed, unless I tell her this she is not proceeding.
- Advised I cannot say that, but I will f/up with MK and provide an outcome.
|
11-9-2024
|
We have received the asbestos testing back and it has come back as positive for the vinyl flooring. As we have accepted the hybrid flooring in order to successfully complete the replacement of this
the asbestos vinyl flooring which sits underneath will have to be removed also. This means the kitchen cabinetry will require removal in order to facilitate these works. It does seem the rest of the materials which we thought would contain asbestos have tested negative. Insured not completing the proper maintenance required on the balcony.
|
5-10-2024
|
flooring underneath damages hybrid flooring is asbestos - due to this, entire kitchen will need to be removed
Maintenance - There are signs of ongoing water ingress in the hallway ceiling, which is near the laundry, this is believed to be asbestos. The cause and location of the water ingress is the balcony, however, it is not near the door. It enters through the other side of the balcony which as reported in our First Report appears to be an ongoing issue with signs of historical repairs.
Insured has requested -The Insured has advised their only acceptable solution for this claim is if Insurance carries out the mould remediation and asbestos removal as required. Then the Insured has expressed their intention to cash settle the reinstatement portion of the claim. The Insured has advised they do not feel comfortable managing the asbestos removal and mould works.
|
6-11-2024
|
We have completed a dual visit with the insured, builder, restoration and asbestos contractor to figure this one out completely. [S] will be submitting a revised quotation for some increased asbestos ceiling originally missed in the original submission. The internals will need to be completed first as the asbestos is friable and the building will need to be under negative pressure for contamination reasons. Oven and rangehood
The Insured believes [insurer] advised them these are contents items. It is our understanding these are building items and can be considered. We acknowledge water may have passed through these appliances. It would be prudent to complete an electrical assessment on these items to determine if they are damaged from the claimed event.
|
12/2024
|
LA following up on email sent 3/12 regarding trades have commenced works and resto is under way over weekend water leached into where they are currently works causing damage to areas already working on and trades are on site today
questioned as to how water got in - LA advised water tank overflowed and filled up entire back yard like a pool and seeped straight over doorway
Time being just want walls stripped to allow to naturally dry - strip out should come in at less than $1,000 and will submit variation for repairs to toilet
has roof repairs and mould remediation taking place in January subject to maintenance being done
Agreed that toilet strip out can occur however as one off won't be authorised again should water enter again in the future
|
2-1-2025
|
Email from LA advising that internal strip out and asbestos removal was completed before the Christmas break.
Due to the newly discovered leak restoration has not been completed until property is watertight.
External/roof repairs will commence mid-late Jan whilst quote and scope of works arranged for CS of the reinstatement repairs.
|
21-1-2025
|
INS had installed a concrete slab for an extension under construction, trades noted that the slab fills with water and overflows causing more damage to rear pantry door and bedroom door …advised previously we will accept these on a good faith basis due to minor impact on items already requiring repair
Repairs due to commence late January and take 4 weeks
Once external work and final asbestos removal are complete [S] will re-attend and finalise the strip out and de-contamination
Once the above are complete trades will re-attend and provide quote for internal resultant damages which the INS wishes to CS
|
24-2-2024
|
Repairs were due to start on 19/02 but got delayed until Monday 24/02. Works should have commenced from today and should only take a week or two to complete. LA will then get restoration completed and once resto complete LA will then arrange 2 trades to provide the quote for internal repairs
All inclusive we should have quotes by early April
|
3-3-2025
|
Multiple emails received
INS to LA + Builder
Noting issues -
Tarp on roof not correctly installed, Eaves not covered at all
Timber + Gyprock damaged - Asbestos still on site, potentially now in plumbing Windows were left open etc
|
7-4-2024
|
Email from LA advising ELS report and scope received last Friday and attached INS has raised a complaint directly with Workplace health and safety Queensland which are completing their own assessment and review which the builders will need to comply with. WHSQ, ELS, BBM and R are all working together to ensure the works are completed in line with legislation and in full (no more issues).
LA awaiting a confirmation on date for the works to commence as the workplace review is taking place but seems to be moving along quickly
Expert Reports
|
Expert
|
Key points
|
Financial firm’s builder (K)
Report
31-1-2024
|
As requested, [K] Building Group attended the insured property to inspect the claimed damages. The insured advised they returned home overnight to find water
damages to the lower level floor, kitchen ceiling. The insured advised the upper level Bed 2 floor and contents were damaged as a result of the event. The insured advised Bed 3 door no longer closes also.
|
Financial firm’s builder (K)
Report
20-2-2024
|
Outdoor upper level deck does not comply with required step down to prevent water ingress.
A building including any associated sitework is to be constructed in a way that protects people and other property from the adverse effects of redirected surface water.
|
Financial firm’s builder (K)
Report
6-3-2024
|
Following our on-site inspection, we believe the damage to the floorboards in the kitchen was caused by water damage. Water has dripped onto the floorboards from either the ceiling or from the mezzanine flooding during the heavy storm events.
|
Financial firm’s builder (K)
Report
24-4-2024
|
Provide a brief overview of the cause - Probable balcony leak.
Based on the inspection and any discussions, what is the
proximate cause of damage? Inspections of the roof did not identify any defects or evidence of a roof leak during attendance. Damages do not appear to be a result of a roof leak.
Are there any other comments you would like to make related
to the cause of damage? Damages appear to originate from the mezzanine level and it is recommended that balcony/ external door leak detection be conducted to ascertain origin of the leak.
|
Financial firm’s restorer
Report
22-5-2024
|
WORKS CARRIED OUT
Attendance Date: Tuesday 22/05/2024
Attended the property to assess mould/water damage.
Conducted inspection, photographed and documented the affected areas. Conducted moisture readings within the affected areas, which returned dry standard moisture readings
Applied anti-microbial solution to affected areas as required to sanitise affected areas. HEPA vacuumed the affected areas.
No equipment on site.
Recommended Scope of Works:
It is recommended to carry out inspection and assessment of affected areas. strip-out works of mould affected areas.
|
Financial firm’s builder (K)
Report
29-5-2024
|
There is no internal water leak at the moment; however, during rain events, water leaks from the balcony into the interior of the property. This is presumed to be due to failed waterproofing on the balcony. Has the leak been occurring over a long period of time? Leak has been occurring since 25/12/23.
Any additional comments - Attended the site to perform a comprehensive leak detection test. Upon thorough inspection, no internal water leak was detected anywhere on the property. Leak is presumed to be due to failed waterproofing.
|
Financial firm’s builder (K)
Report
31-5-2024
|
There is no internal water leak at the moment; however, during rain events, water leaks from the balcony into the interior of the property caused by failed water proofing, and damaging of the lower ceiling in the kitchen, also mould is growing in surrounding areas. This needs to be rectified.